Atch_4_Bozeman_FTC_Submittals.pdf
PDF 14 KB Posted
- Attached to
- BOZEMAN WATER CLARIFIER Federal contract opportunity
- Solicitation number
- F17PS00722
About this file
Submittals Bozeman FTC Water Clarifier
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_F17PS00722_Amd_0002.pdf | ||
| F17PS00722-001.pdf | ||
| Atch_6_Bozeman_FTC_Past_Perf_Quest.doc | DOC document | |
| Atch_1_Bozeman_FTC_Clarifier_Spec.pdf | ||
| Atch_7_F17PS00722_1-4.pdf | ||
| Atch_5_Bozeman_FTC_Wage_Det_MT34.pdf | ||
| Sol_F17PS00722.pdf | ||
| Atch_3_Bozeman_FTC_Drawing_Coversheet.pdf | ||
| Atch_2_Bozeman_FTC_Clarifier_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET 1 OF 1
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
D - No Action Taken. See Comments. Resubmission Required.
E - disapproved. See Comments. Resubmission Required.
PROJECT NAME: Wastewater Effluent Clarifier Rehabilitation ENGR. PROJECT NO.: 16-013C LOCATION: Bozeman Fish Technology Center CONTRACT NO.: WO#: F2014246938
CONTRACTOR:
Spec.
Section Number
Spec.
Paragraph No.
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals etc )
Contractor's Submittal Number
Date Submitted
Action Taken
Date Resubmitted
Action Taken Comments
01 33 00 1.1B1 Preliminary Schedule of Shop Drawings, Samples, & Proposed substitutes 1 Due 7 days after NTP
01 33 00 1.1B2 List of Permits and Licenses to be obtained by contractor 1 Due 7 days after NTP
01 33 00 1.2A Revised Schedule of Shop Drawings, Samples, & proposed substitutes 1
At the Preconstruction Conference
01 33 00 1.2A Revised list of Permits and Licenses to be obtained by contractor 2
At the Preconstruction Conference
01 33 00 1.2A Preliminary Sschedule of values per 01 29 73 2 At the Preconstruction Conference
01 33 00 1.2A 60-day plan of operation per 01 32 16 2 At the Preconstruction Conference
01 33 00 1.2A Detailed layout of field office per 01 52 00 2 At the Preconstruction Conference
01 33 00 1.3 Shop Drawings 3
PROJECT SUBMITTAL LIST