ESD150-SpecificationsStyleGuide-Rev01.pdf
PDF 228 KB Posted
- Attached to
- Professional Structural Engineering, Architectural, and Geotechnical Services State and local contract opportunity
- Solicitation number
- Not on record
- Issued by
- San Diego County, California
About this file
The document is the ESD-150 Specifications Style Guide created by the San Diego County Water Authority's Engineering Department in July 2004. This comprehensive guide establishes standardized formatting, writing, and documentation protocols for preparing technical specifications within the organization. The style guide provides detailed instructions on document preparation, including margin specifications, font requirements, header and footer formatting, and specific guidelines for language usage, such as handling numbers, abbreviations, dates, and terminology.
Key stylistic recommendations include using 11-point Times New Roman font, spelling out numbers zero to nine, consistently using "shall" for contractor requirements, avoiding vague phrases like "adequate" or "satisfactory", and maintaining precise cross-referencing methods. The guide also specifies technical formatting details like using CSI (Construction Specifications Institute) format, printing double-sided, and stamping cover sheets with a Registered Engineer stamp. The document is designed as a living document that can be updated to meet the evolving needs of the Water Authority, with a clear procedure for suggesting modifications to the guide.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| ESD 160 - Design Manual Vol.2.pdf | ||
| RFP with Exhibits A_B_C_D.pdf | ||
| ESD 120 - Drafting Manual.pdf | ||
| ESD 160 - Design Manual Vol.1.pdf | ||
| ESD260-ConstCostEstimatingGuide.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SDCWA
San Diego County Water Authority Engineering Department
SPECIFICATIONS
STYLE GUIDE
ESD-150 July 2004
ESD150 Specifications Style Guide
8/6/04 i REV 01
Purpose The purpose of this document is to outline the standard format and style to follow in developing San Diego County Water Authority specifications.
Revisions and Maintenance
The guide is a living document that evolves to meet the changing needs of the Water Authority.
Users may suggest changes or additions to this by following the procedure described in ESD 510 Engineering Policies, Procedures, and Practices, Section 3.9, Engineering Standard Documents Guidelines.
Personnel entrusted with this guide are responsible for maintaining it in a current and updated condition as revisions are published.
Disclaimer The information provided herein is for the convenience and use of the Water
Authority. Any use of the information by any entity other than the Water Authority is at such entity’s own risk, and the Water Authority assumes no liability for such use.
Validation The San Diego County Water Authority Engineering Department’s ESD 150
Specifications Style Guide is hereby accepted and approved.
John Economides, Director of Engineering San Diego County Water Authority
REV 01 8/6/04 1
Water Authority Preparation
Water Authority staff will prepare the following items:
• Notice Inviting Bids
• Bid Proposal (Consultant to prepare the bid sheet)
• Contract
• Bond and insurance forms
• Schedules B-1 and B-2
• SCOOP forms
CSI Format Prepare final technical specifications in CSI format.
Margins One-inch inside margin. .5-inch top, bottom, and outside margin. Mirror margins.
Header Do not include a header.
Footer 8 point, Times New Roman, specification #, file path\file name, section name, and section #-page #. Example:
Specification # Section Name File Path\File Name (automatically updated) Section #-Page #
Headings 11 point, Times New Roman, all capitals, regular font style (not bold).
Body 11 point, Times New Roman.
Abbreviations & Acronyms
Use “San Diego County Water Authority” on first use of name. Subsequent occurrences may be shortened to “Water Authority”.
Minimize the use of parenthesis.
Use industry-standard abbreviations and acronyms on first (and subsequent) occurrences.
Include abbreviations and acronyms, which are not industry-standard, in the Abbreviations section of the specification.
Numbers Spell out numbers from zero to nine.
Spell out numbers at the beginning of a sentence.
Use numerical figures for any number with ”percent”, a fraction, or a decimal point.
Use a preceding zero for any number with a decimal point and a value of less than
1.0 (for example, “0.25” instead of “.25”).
Units of Measure
Spell out units of measure (for example, “feet”, “foot”,” inches”, “degrees”, and” percent”).
Hyphens Hyphenate number and unit of measure when followed by a noun (for example, “ten-foot pipe”).
Hyphenate compound numbers (for example, “thirty-four”).
Dates Format dates as per the following example: “November 10, 2003”.
Do not use weeks; specify calendar or working days (for example, “14 calendar days”).
8/6/04 2 REV 01
Words & Phrases to Exclude
• “insofar as possible”
• “as soon as practicable”
• “adequate”
• “satisfactory”
• “in the opinion of”
• “competent”
• “it is preferred”
• “appropriate”
• contractions (for example, use “is not” instead of “isn’t”)
Shall Use “shall” in place of “should”, “is”, “are”, and “be” (for example, “The dials shall be white, with black scale markings.”).
Use “shall” for the Contractor (for example, “the Contractor shall be responsible for…”).
Use “will” for the Water Authority (for example, “The Water Authority will…”).
Avoid using “shall” (except when following examples above); replace with command verbs (for example, “Design, prepare, and submit full line interconnection diagrams for all the equipment furnished under this Contract.”
Consistency Use terms consistently throughout the document (for example, use ”plans” not
“drawings”, etc.).
References Refer to other parts of the Contract Documents per the following example:
“Refer to Section #, Part #, Paragraph #, Item #, Sub-Paragraph #, Sub-Item #”, etc.
QA/QC all references to other sections of the Contract Documents to ensure accurate cross-references.
Approval If approval is needed, specify per the following example:
“Engineer will approve in writing” or “obtain written approval of the Engineer”
Additions & Revisions
If additions or revisions exist, specify per the following examples:
“Delete Section 01530, Part 1.03, Paragraph A, Item 1 and replace with the following:”
“Delete Section 01530, Part 1.03 “in its entirety” and replace with the following:”
“Add Section 01530, Part 1.03, Paragraph B as follows:”
Cover Format cover sheet per the attached example.
Printing Print double-sided.
Stamp Stamp cover sheet of the specifications with Registered Engineer stamp per the attached example.
CONTRACT DOCUMENTS
FOR
CONSTRUCTION OF
RANCHO PENASQUITOS
PRESSURE
CONTROL/HYDROELECTRIC
FACILITY
SPECIFICATION 546
DECEMBER 2003
Place Registered Engineer stamp here
File details come from the government source that posted it. Updated .