These technical specifications are comprehensive construction standards developed by Escambia County, Florida for engineering and public works projects, specifically covering roadway, infrastructure, and transportation construction requirements. The documents outline detailed technical specifications for various construction activities including clearing and grubbing, earthwork, drainage systems, aggregate base preparation, asphalt paving, concrete work, traffic signage, pavement markings, and related civil engineering processes. The specifications provide comprehensive guidance on materials, installation methods, quality control, testing procedures, measurement, and payment protocols for county-level infrastructure projects.
The technical specifications are aligned with Florida Department of Transportation (FDOT) standards and incorporate federal highway administration guidelines, ensuring consistent quality and performance across county construction projects. The documents establish precise requirements for material composition, installation techniques, testing protocols, and contractor responsibilities, with specific attention to environmental considerations, safety standards, and technical performance metrics. Funding for projects utilizing these specifications may come from various sources including local area sales taxes (LOST IV), Florida Department of Transportation Regional Incentive Program (TRIP) funds, and other local and state transportation infrastructure funding mechanisms. The specifications serve as a comprehensive technical reference and contractual framework for engineering and construction work within Escambia County's public infrastructure development initiatives.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Quintette_Road-95A_Alignment_-_Design_Services.pdf | ||
| Manual_on_Uniform_Traffic_Control_Devices_(MUTCD)_-_FHWA.html | HTML file | |
| FDOT.mhtml | MHTML file | |
| 2-5-2024_Escambia_BOCC_Board_Minutes.pdf | ||
| Aeiral_Exhibit_2.JPG | JPG image | |
| FDOT_TRIP_Application_-_STAMPED.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC WORKS DEPARTMENT
Engineering Division
Escambia County Technical Specifications
GENERAL EXCEPTIONS*: Any reference to FDOT Standard Specifications for Road and Bridge Construction, L atest Edition, D ivision I G eneral R equirements & Covenants shall be excluded and not applicable to any specification referred herein or otherwise listed in this document.
Work shall comply with requirements of FDOT Standard Specifications for Road and Bridge Construction, latest edition, as modified herein.
*Note: The General Exception above does not apply when utilizing Federal Highway Administration (FHWA) funding.
County Engineer Effective Date: February 01, 2015 Revised : July 1, 2020Joy D. Blackmon, P.E.
3363 West Park Place • Pensacola, Florida 32505
(850) 595-3440 • www.myescambia.com i
INDEX TO ESCAMBIA COUNTY TECHNICAL SPECIFICATIONS
Section Title
01000
01300
02230
02300
02320
02340
02400
02410
02440
02460
02500
02580
02600
02800
02900
03300
03310
03350
04000
04020
04030
04040
04060
04090
Definitions
Submittals
Clearing and Grubbing
Earthwork
Underdrain and Exfiltration Trench
Riprap
Graded Aggregate Base
Recycled Concrete Aggregate Base (Crushed Concrete)
Superpave Asphalt Base
Sand Clay Base
Superpave Asphalt Concrete
Hot In-Place Reclaimed Asphalt and Resurfacing Stormwater
System
Fencing
Grassing
Portland Cement Concrete
Tied Concrete Block
Pervious Concrete Paving
Traffic Control Signs
Post Mounted Street Name Signs
Span Mounted Signs
Pavement Markings
Maintenance of Traffic
Construction of Traffic Signals
SUPPLEMENTAL FDOT/FHWA SPECIFICATIONS
LAP Div. 1
Sand-Clay Base (2000 Edition)
Sand-Clay Base Material (2000 Edition)
LAP Division 1 Specifications (FHWA/FDOT Projects Only) mebush Cross-Out
DEFINITIONS - 01000 06/20
- 1 -
SECTION 01000 – DEFINITIONS AND TERMS
PART 1 - GENERAL
These Specifications are written to the bidder, prior to award of the Contract, and to the Contractor.
Any reference to Florida Department of Transportation Standard Specifications for Road and Bridge Construction, Latest Edition, Division I, General Requirements and Covenants shall be excluded and not applicable to any specification referred to, or otherwise listed, in this document.
1.1 ABBREVIATIONS AND ACRONYMS
The following abbreviations and acronyms, when used in the Contract Documents, represent the full text shown.
AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute ADS Advanced Drainage Systems AISI American Iron and Steel Institute ARB Asphalt Rubber Binder ARMI Asphalt Rubber Membrane Interlayer ASTM American Society for Testing and Materials CEI Construction Engineering Inspections CRSI Concrete Reinforcing Steel Institute CTQP Construction Testing Qualification Program ECUA Escambia County Utilities Authority EOR Engineer of Record ERC Engineered Crumb Rubber FAC Florida Administrative Code FDACS Florida Department of Agriculture and Consumer Services FDEP Florida Department of Environmental Protection FDOT Florida Department of Transportation FHWA Federal Highway Administration FM Florida Method HMAC Hot-Mix Asphaltic Concrete LBR Limerock Bearing Ratio MOT Maintenance of Traffic MUTCD Manual on Uniform Traffic Control Devices NCHRP National Cooperative Highway Research Program NPDES National Pollutant Discharge Elimination System NS Non-Structural OSHA Occupational Safety and Health Administration PE Professional Engineer PG Performance Grade PVC Polyvinyl Chloride QA Quality Assurance
- 2 -
QC Quality Control RAP Reclaimed Asphalt Pavement RCA Recycled Concrete Aggregate SHS Standard Highway Signs SP Superpave USDA United States Department of Agriculture USDOT U.S. Department of Transportation VFA Voids Filled with Asphalt VMA Voids in Mineral Aggregate
Each of the above abbreviations, when followed by a number or letter designation, or combination of numbers and letters, designates a specification, test method, or other code or recommendation of the authority or organization shown.
Use standards, specifications, test methods, or other codes as specified in the current edition at the time of the bid opening.
1.2 DEFINITIONS
The following terms, when used in the Contract Documents, have the meaning described:
Advertisement - The public announcement, as required by law, inviting bids for work to be performed or materials to be furnished, usually issued as “Notice to Contractors,” or “Notice to Bidders.”
Bidder - An individual, firm, or corporation submitting a proposal for the proposed work.
Bridge - A structure, including supports, erected over a depression or over an obstruction such as water, highway or railway, or for elevated roadway, for carrying traffic or other moving loads, and having a length, measured along the center of the roadway, of more than 20 feet between the inside faces of end supports. A multiple-span box culvert is considered a bridge, where the length between the extreme ends of the openings exceeds 20 feet.
Calendar day - Every day shown on the calendar, ending and beginning at midnight.
Contract - The term “Contract” means the entire and integrated agreement between the parties there under and supersedes all prior negotiations, representations, or agreements, either written or oral. The Contract Documents form the Contract between the County and the Contractor setting forth the obligations of the parties thereunder, including, but not limited to, the performance of the Work and the basis of payment.
Contract Documents - The term “Contract Documents” includes: Advertisement for Proposal, Proposal, Certification as to Publication and Notice of Advertisement for Proposal, Appointment of Agent by
- 3 -
Nonresident Contractors, Non-collusion Affidavit, Warranty Concerning Solicitation of the Contract by Others, Resolution of Award of Contract, Executed Form of Contract, Performance Bond and Payment Bond, Specifications, plans (including revisions thereto issued during construction), Addenda, or other information mailed or otherwise transmitted to the prospective bidders prior to the receipt of bids, work orders and supplemental agreements, all of which are to be treated as one instrument whether or not set forth at length in the form of contract.
Contract Bond - The security furnished by the Contractor and the surety as a guaranty that the Contractor shall fulfill the terms of the Contract and pay all legal debts pertaining to the construction of the project.
Contract Letting - The date that the County opened the bid proposals.
Contract Time - The number of calendar days allowed for completion of the Contract work, including authorized time extensions.
Contractor - The individual, firm, joint venture, or company contracting with the County to perform the work.
Contractor’s Engineer of Record - A Professional Engineer registered in the State of Florida, other than the Engineer of Record or his subcontracted consultant, who undertakes the design and drawing of components of the permanent structure as part of a redesign or Cost Savings Initiative Proposal, or for repair designs and details of the permanent work. The Contractor’s Engineer of Record may also serve as the Specialty Engineer. The Contractor’s Engineer of Record must be an employee of a pre-qualified firm. Any Corporation or Partnership offering engineering services must hold a Certificate of Authorization from the Florida Department of Business and Professional Regulation.
As an alternate of being an employee of a pre-qualified firm, the Contractor’s Engineer of Record may be a pre-qualified Specialty Engineer. For items of the permanent work declared by the State Construction Office to be “major” or “structural”, the work performed by a prequalified Specialty Engineer must be checked by another pre-qualified Specialty Engineer.
An individual Engineer may become pre-qualified in the work groups listed in the Rules of the Department of Transportation, Chapter 14-75, if the requirements for the Professional Engineer are met for the individual work groups. Pre-qualified Specialty Engineers are listed on the State Construction Website. Pre-qualified Specialty Engineers will not be authorized to perform redesigns or Cost Savings Initiative Proposal designs of items fully detailed in the plans.
Controlling Work Items - The activity or work item on the critical path having the least amount of total float. The controlling item of work will also be referred to as a Critical Activity.
- 4 -
County - Escambia County Florida
Culverts - Any structure not classified as a bridge that provides an opening under the roadway.
Delay - Any unanticipated event, action, force or factor which extends the Contractor’s time of performance of any controlling work item under the Contract. The term “delay” is intended to cover all such events, actions, forces or factors, whether styled “delay”, “disruption”, “interference”, “impedance”, “hindrance”, or otherwise, which are beyond the control of and not caused by the Contractor, or the Contractor’s subcontractors, materialmen, suppliers or other agents. This term does not include “extra work”.
Department - Florida Department of Transportation.
Department of Transportation - Florida Department of Transportation.
Developmental Specification - See definition for Specifications.
Engineer - The Professional Engineer, registered in the State of Florida, other than the Engineer of Record or his subcontracted consultant, acting as the project's Construction Engineering Inspection Manager. The Engineer may be County in-house staff, or a consultant retained by the County
Engineer of Record - The Professional Engineer or Engineering Firm registered in the State of Florida that develops the criteria and concept for the project, performs the analysis, and is responsible for the preparation of the Plans and Specifications. The Engineer of Record may be County in-house staff, or a consultant retained by the County.
The Contractor shall not employ the Engineer of Record as the Contractor’s Engineer of Record or as a Specialty Engineer.
Equipment - The machinery and equipment, together with the necessary supplies for upkeep and maintenance thereof, and all other tools and apparatus necessary for the construction and acceptable completion of the work.
Extra Work - Any “work” which is required by the Engineer to be performed and which is not otherwise covered or included in the project by the existing Contract Documents, whether it be in the nature of additional work, altered work, deleted work, work due to differing site conditions, or otherwise. This term does not include a “delay”.
- 5 -
Highway, Street, or Road - A general term denoting a public way for purposes of vehicular travel, including the entire area within the right-of-way.
Holidays - Days designated by the Board of County Commissioners as holidays, which include, but are not limited to, New Year’s Day, Martin Luther King’s Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and the following Friday, and Christmas Day.
Inspector - An authorized representative of the County assigned to make official inspections of the materials furnished and of the work performed by the Contractor.
Laboratory - The testing laboratory used by the Contractor.
Major Item of Work - Any item of work having an original Contract value in excess of 5% of the original Contract amount.
Materials - Any substances to be incorporated in the work under the Contract.
Median - The portion of a divided highway or street separating the traveled ways for traffic moving in opposite directions.
Plans - The approved plans, including reproductions thereof, showing the location, character, dimensions, and details of the work.
Proposal (Bid, Bid Proposal) - The offer of a bidder, on the prescribed form, to perform the work and to furnish the labor and materials at the prices quoted.
Proposal Form - The official form or the expedite program generated bid item sheets on which the County requires formal bids to be prepared and submitted for the work.
Proposal Guaranty - The security furnished by the bidder as guaranty that the bidder will enter the Contract for the work if the County accepts the proposal.
Right-of-Way - The land that the County has title to, or right of use, for the road and its structures and appurtenances, and for material pits furnished by the County.
- 6 -
Roadbed - The portion of the roadway occupied by the subgrade and shoulders.
Roadway - The portion of a highway within the limits of construction.
Section - A numbered prime division of these Specifications.
Special Provisions - See definition for Specifications.
Specialty Engineer - A Professional Engineer registered in the State of Florida, other than the Engineer of Record or his subcontracted consultant, who undertakes the design and drawing preparation of components, systems, or installation methods and equipment for specific temporary portions of the project work or for special items of the permanent works not fully detailed in the plans and required to be furnished by the Contractor such as but not limited to pot bearing designs, nonstandard expansion joints, MSE wall designs and other specialty items. The Specialty Engineer may also provide designs and details for items of the permanent work declared by the State Construction Office to be “minor” or “non-structural”. The Specialty Engineer may be an employee or officer of the Contractor or a fabricator, an employee or officer of an entity providing components to a fabricator, or an independent consultant. For items of work not specifically covered by the Rules of the Department of Transportation, a Specialty Engineer is qualified if he has the following qualifications:
1) Registration as a Professional Engineer in the State of Florida,
2) The education and experience necessary to perform the submitted design as required by the Florida Department of Business and Professional Regulation.
Specifications - The directions, provisions, and requirements contained herein, together with all stipulations contained in the Contract Documents, setting out or relating to the method and manner of performing the work, or to the quantities and qualities of materials and labor to be furnished under the Contract.
Developmental Specification - A specification developed around a new process, procedure, or material.
Special Provisions - Specific clauses adopted by the Department that add to or revise the Standard Specifications or Supplemental Specifications, setting forth conditions varying from or additional to the Standard Specifications applicable to a specific project.
Standard Specifications - Florida Department of Transportation “Standard Specifications for Road and Bridge Construction” a bound book, applicable to all construction contracts containing adopted requirements, setting out or relating to the method or manner of performing work, or to the
- 7 -quantities and qualities of materials and labor.
Supplemental Specifications - Approved additions and revisions to the Standard Specifications, applicable to all construction contracts.
Technical Special Provisions - Specifications, of a technical nature, prepared, signed, and sealed by an Engineer registered in the State of Florida other than the State Specifications Engineer or his designee, that are made part of the Contract as an attachment to the Contract Documents.
Technical Specifications - Escambia County Florida “General Paving and Drainage Technical Specifications” developed for all construction contracts containing adopted requirements, setting out or relating to the method or manner of performing work, or to the quantity and quality of materials and labor.
State - State of Florida.
Sub-article - A headed and numbered subdivision of an Article of a Section of these Specifications.
Subgrade - The portion of the roadbed immediately below the base course or pavement, including below the curb and gutter, valley gutter, shoulder and driveway pavement. The subgrade limits ordinarily include those portions of the roadbed shown in the plans to be constructed to a design bearing value or to be otherwise specially treated. Where no limits are shown in the plans, the subgrade section extends to a depth of 12 inches below the bottom of the base or pavement and outward to 6 inches beyond the base, pavement, or curb and gutter.
Substructure - That part of a bridge structure below the bridge seats, including the parapets, backwalls, and wingwalls of abutments.
Superintendent - The Contractor’s authorized representative in responsible charge of the work.
Superstructure - The entire bridge structure above the substructure, including anchorage and anchor bolts, but excluding the parapets, backwalls, and wingwalls of abutments.
Supplemental Agreement - A written agreement between the Contractor and the County, and signed by the surety, modifying the Contract within the limitations set forth in these Specifications.
Supplemental Specifications - See definition for Specifications.
- 8 -
Surety - The corporate body that is bound by the Contract Bond with and for the Contractor and responsible for the performance of the Contract and for payment of all legal debts pertaining thereto.
Technical Special Provisions - See definition for Specifications.
Technical Specifications - See definition for Specifications.
Traveled Way - The portion of the roadway providing for the movement of vehicles, exclusive of shoulders and auxiliary lanes.
Unilateral Payment - A payment of money made to the Contractor by the Department pursuant to Section 337.11(12), Florida Statutes (2009), for sums the Department determines to be due to the Contractor for work performed on the project, and whereby the Contractor by acceptance of such payment does not waive any rights the Contractor may otherwise have against the Department for payment of any additional sums the Contractor claims are due for the work.
Work - All labor, materials and incidentals required to execute and complete the requirements of the Contract including superintendence, use of equipment and tools, and all services and responsibilities prescribed or implied.
Work Order - A written agreement between the Contractor and the County modifying the Contract within the limitations set forth in these Specifications. Funds for this agreement are drawn against the Initial Contingency Pay Item or a Contingency Supplemental Agreement.
Working Day - Any calendar day on which the Contractor works or is expected to work in accordance with the approved work progress schedule.
END OF SECTION 01000
SUBMITTALS - 01300 01/15
SECTION 01300 - SUBMITTALS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
Drawings and General and Supplemental Provisions of the Contract apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for submittals required for performance of the Work, including, but not limited to the following:
1. Submittal Procedures
2. Contractor’s Construction Schedule
3. Daily Construction Reports
4. Shop Drawings
5. Product Data
6. Samples
7. Quality Assurance Submittals
8. Licenses
9. Pictures, Video of Pre-Construction Conditions
B. Administrative Submittals: Refer to other Sections and other Contract
Documents for requirements for administrative submittals. Such submittals include, but are not limited to, the following:
1. Permits
2. Applications for Payment
3. Performance and Payment Bonds
4. Insurance Certificates
5. List of Subcontractors
6. Licenses
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, inspections, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination. The County reserves the right to withhold action on a submittal requiring coordination with other submittals until all related submittals are received.
3. Processing: To avoid the need to delay construction as a result of the time required to process submittals, allow enough time for submittal review, including time for re-submittals. Allow 2 weeks for initial review.
Allow additional time if the County must delay processing to permit coordination with subsequent submittals.
a. If an intermediate submittal is necessary, process the same as the initial submittal.
b. Allow 2 weeks for reprocessing each submittal.
c. No extension of Contract Time will be authorized because of failure to transmit submittals to the County sufficiently in advance of the Work to permit processing.
B. Submittal Preparation: Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
1. Provide a space approximately 4 by 5 inches on the label or beside the title block on Shop Drawings to record the Contractor's review and approval markings and the action taken.
2. Include the following information on the label for processing and recording action taken.
a. Project Name.
b. Date.
c. Name and Address of the Engineer.
d. Name and Address of the Contractor.
C. Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Four copies of each submittal (three hard copy and one digital) shall be transmitted. Transmit each submittal from the Contractor to the County, (copy Engineer) using a transmittal form. The County will not accept submittals received from sources other than the Contractor. Submittals must be approved by Contractor prior to review by County. On the transmittal, record relevant information and requests for data. On the form or on a separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor's certification that the information complies with Contract Document requirements on each submittal.
1.4 CONSTRUCTION SCHEDULE/DOCUMENTATION
A. Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart-type, contractor’s construction schedule. Submit within 10 days of the issuance of the Notice to Proceed. The contractor shall submit an updated schedule at least once per month, showing any schedule changes. This may be requested up to three times per month by the County. Include dates of shop drawing submittals.
B. Cost Correlation: At the head of the schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of Work performed as of the dates used for preparation of payment requests.
C. Pre-Construction Site Conditions Photos/Video: Contractor shall submit a DVD of photos and video of the site conditions prior to the performance of any work.
D. Licenses: All required licenses to perform work shall be submitted prior to the commencement of construction.
1.5 DAILY CONSTRUCTION REPORTS
Prepare a daily construction report recording the following information concerning events at the site, and submit duplicate copies to the County at weekly intervals including, but not limited to:
1. Work performed.
2. Approximate count of personnel at the site.
3. Count and type of major equipment at the site.
4. High and low temperatures, general weather conditions, including daily rainfall amount from gauge installed on site jointly recorded by contractor and county representative.
5. Accidents and unusual events.
6. Meetings and significant decisions.
7. Stoppages, delays, shortages, and losses.
8. Emergency procedures.
9. Orders and requests of governing authorities.
10. Change Orders received, implemented.
11. Material Expenditures.
1.6 SHOP DRAWINGS
A. Submit shop drawings for structures to be approved by the EOR.
B. Shop Drawings – Including, but not limited to the following information:
1. Dimensions.
2. Identification of products and materials included by sheet and detail number.
3. Compliance with specified standards.
1.7 PRODUCT DATA
Product Data - Include the following information:
1. Manufacturer's printed recommendations.
2. Compliance with trade association standards.
3. Compliance with recognized testing agency standards.
4. Application of testing agency labels and seals.
1.8 SAMPLES
Submit samples as specified in the technical specifications.
1.9 QUALITY CONTROL (QC) / QUALITY ASSURANCE (QA) SUBMITTALS
A. Submit the QC Plan to the County for approval within 21 calendar days after the Notice to Proceed. The County will review the QC Plan and respond to the Contractor within 21 calendar days of receipt.
If at any time the Contractor is not in compliance with the approved QC Plan, or a part thereof, affected portions of the plan will be disapproved. The contractor shall cease work in the affected operation(s) and submit a revision to the County. If the QC Plan, or a part thereof, must be revised, submit the revision to the County. The County will review the revision and respond within seven calendar days of receipt.
Continue to work on operations that are still in compliance with the approved sections of the QC Plan.
B. Certifications: Where other Sections of the Specifications require certification that a product, material, or installation complies with specified requirements, submit to the County a certification from the manufacturer stating compliance with specified requirements.
C. Inspection and Test Reports: Requirements for specific testing are included in the technical specifications.
1. Submit to the County: Two (2) copies (one hard copy and one digital) of the inspection and test reports from a qualified, independent, geotechnical engineering testing agency, under the direction of a P.E., licensed in the State of Florida.
2. All testing required by these specifications shall be at the contractors’ expense.
3. No additional work within/upon the tested area shall proceed until submitted test results confirm compliance with specification requirements.
4. Areas where submitted test results indicate non-compliance shall be removed, replaced, and retested. Extents of area out of compliance shall be determined by testing at 25’ increments, in each direction within the construction area, until passing results are achieved.
5. Variations from testing requirements and frequency of testing may be authorized by the County and will be documented in writing.
1.10 ENGINEER'S ACTION
Except for submittals for the record or information, where action and return are required, the County will review each submittal, mark to indicate action taken, return to contractor within the timeframe allotted herein. Compliance with specified characteristics is the Contractor's responsibility.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01300
CLEARING AND GRUBBING - 02230 06/20
SECTION 02230 - CLEARING & GRUBBING
A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions shall apply to this Section.
B. Florida Department of Transportation, Standard Specifications for Road and Bridge Construction, Latest Edition, Section 110
C. Emerald Coast Utility Authority (ECUA) Engineering Manual, Latest Edition.
A. This Section includes, but is not limited to, the following:
1. Protection of existing trees indicated to remain.
2. Removal of trees and other vegetation.
3. Clearing and grubbing.
4. Removing above-grade improvements.
5. Removing below-grade improvements.
B. Extent of clearing & grubbing shall remain in County Rights-of-Way, easements (temporary or permanent), or approved written work agreement areas, unless otherwise noted or instructed.
1.3 PROJECT CONDITIONS
Provide protection for all public land corners and monuments within the limits of construction. Any Monuments disturbed while performing the work will be replaced at the contractor’s expense.
PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION
3.1 SITE CLEARING
A. General: Remove trees, shrubs, grass, and other vegetation, improvements, or obstructions, as required, to permit installation of new construction. Remove similar items elsewhere on site or premises as specifically indicated. Removal includes digging out and off-site disposal of stumps and roots.
Carefully and cleanly cut minor roots and branches of trees indicated to remain in a manner where such roots and branches obstruct installation of new construction.
B. Clearing and Grubbing: Clear site of trees, shrubs, and other vegetation, except for those indicated to remain.
1. Completely remove all stumps within the roadway. Remove roots and other debris to a depth of 12” below the ground surface or finished grade, whichever is lower.
2. Use only hand methods for grubbing inside drip line of trees Indicated to remain.
3. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated in accordance with Section 2300.
C. Removal of Improvements: Remove existing above grade and below grade improvements as indicated and as necessary to facilitate new construction, and other work as indicated.
3.2 DISPOSAL OF WASTE MATERIALS
A. Burning: Burning is not permitted on County property. Requests to burn will be considered on a case by case basis. If approved, Contractor is to acquire permits and provide copies to the County.
B. Removal from County Property: Remove waste materials and unsuitable or excess topsoil from County property and dispose of offsite in a legal manner.
PART 4 - MEASUREMENT/PAYMENT
4.1 METHOD OF MEASUREMENT
A. Lump Sum Payment: When direct payment is provided in the Contract for the quantity to be paid for as the lump sum quantity cleared and grubbed, no additional measurements will be made.
B. Payment By The Acre/Square Yard: For areas of Clearing and Grubbing that are designated to be paid for separately by the acre or square yard, the quantity to be paid for will be determined by measurement of the areas shown on the plans or authorized by the County to be cleared and grubbed, and acceptably completed.
4.2 BASIS OF PAYMENT
A. General: Price and payment will be full compensation for all Clearing and Grubbing required for the roadway right-of-way and for lateral ditches, channel changes, or other outfall areas, and any other Clearing and Grubbing indicated, or required for the construction of the entire project, except for any areas designated to be paid for separately or to be specifically included in the costs of other work under the contract. Price and payment, either lump sum or by the acre/square yard will be full compensation for all the work specified in this Section, including all necessary hauling, furnishing equipment, equipment operation, furnishing any areas required for disposal of debris, leveling of terrain and the landscaping work of trimming, etc., as specified herein.
B. Lump Sum Payment: Payment shall be made at the lump sum contract price for Clearing and Grubbing, lump sum.
C. Payment: Payment shall be made at the per unit contract price for Clearing and Grubbing, per acre or square yard.
END OF SECTION 02300
EARTHWORK - 02300 06/20
SECTION 02300 – EARTHWORK
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.
Bridge Construction, Latest Edition, Sections 120, 160, and 902
A. This Section includes preparing and grading for pavement, curb, subgrades, drainage features, and general site work.
B. Related Sections: The following Sections contain requirements that relate to this Section.
1. Section 2230 "Clearing & Grubbing" for clearing, grubbing, and tree protection.
2. Section 2600 “Stormwater System” for installation of stormwater systems.
1.3 DEFINITIONS
A. Base Course: The layer placed immediately beneath the surface pavement in a paving system.
B. Borrow: Soil material obtained off-site when enough approved soil material is not available from on-site excavations.
C. Embankment (Fill): Compacted fill material needed to construct the roadway.
This typically excludes the base and pavement portions of the roadway and shoulders, unless the EOR specifies for them to be incorporated into the fill material.
D. Excavation (Regular): The removal of material encountered to subgrade elevations necessary for the construction of the roadway, ditches, ponds, channels, or sidewalks.
E. Subgrade: The uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, base, drainage fill, or topsoil materials.
F. Subbase Course: The layer placed between the subgrade and base course in a paving system.
G. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below ground surface.
H. Topsoil: Topsoil is defined as the surface layer of soil found normally to a depth of at least 4 to 8 inches that typically contains organic materials. Satisfactory topsoil is reasonably free of roots, clay lumps, stones, other objects over 2 inches in diameter, and any other objectionable or deleterious material.
I. Unauthorized Excavation: Removing materials beyond indicated subgrade elevations or dimensions without direction by the County. Unauthorized excavation, as well as remedial work directed by the Engineer, shall be at the Contractor's expense.
J. Unsuitable Material: Removal and disposal of any material such as muck, wood, rock, peat, garbage, non-compactable soils in dry condition, and any other material that is considered by the County Engineer to be unsuitable.
K. Utilities: On-site above ground utilities, overhead utilities and underground utilities including pipes, conduits, ducts, and cables, as well as related appurtenances and underground services within building lines.
1.4 SUBMITTALS
A. General: Submit the following in accordance with Section 1300, "Submittals.”
B. Product Data and Samples of the following:
1. 1-lb representative samples of each proposed fill and backfill soil material from borrow sources as selected by the County.
2. 12-by-12-inch sample of filter fabric.
3. Representative samples of the proposed base and sub-base materials.
C. Test Reports: In addition to test reports required under field quality control, submit the original directly to the County from the testing services, with a copy to the Contractor:
1. Laboratory analysis as specified in 1.1 (Related Documents) of each soil material proposed for fill and backfill from borrow sources.
2. One optimum moisture-maximum density curve for each soil material.
3. Report of actual unconfined compressive strength and/or results of bearing tests of each stratum tested.
1.5 QUALITY CONTROL / QUALITY ASSURANCE
A. Codes and Standards: Perform earthwork complying with all requirements of authorities having jurisdiction.
B. Testing and Inspection Service: A qualified independent geotechnical engineering testing agency, under the direction of a Professional Engineer, licensed in the State of Florida to classify, perform soil tests, and provide inspection services for quality control. All proposed borrow soils will require the testing agency to verify that soils comply with specified requirements and to perform required field and laboratory testing. Contractor shall replace materials removed for testing purposes. Should any work or materials fail to meet the requirements set forth in the plans and specifications, contractor shall reimburse for additional and re- testing.
1.6 PROJECT CONDITIONS
A. Site Information: Data in the subsurface investigation Report, if available, is used for the basis of the design and is available to the contractor for information only. Conditions are not intended as representations or warranties of accuracy or continuity between soil borings. The County will not be responsible for interpretations or conclusions drawn from this data by the Contractor.
B. Existing Utilities: After location of utilities by the appropriate utility company, it is the Contractor's responsibility to protect all such utility lines, including service lines and appurtenances, and to replace at his own expense any that may be damaged by the Contractor's equipment or forces during construction of the Project.
1. Provide a minimum of 48-hours’ notice to the County and receive written notice to proceed before interrupting any utility.
2. The contractor is responsible for contacting all utility companies to verify locations of all existing utilities, utility-related obstructions, or utility relocations that he may encounter during construction.
3. Adequate provision shall be made for the flow of existing sewers, drains, and water courses encountered during construction, and structures which may be disturbed shall be satisfactorily restored by the Contractor at his expense.
C. Should uncharted, or incorrectly charted, piping or other utilities be encountered during the work, consult the County immediately for directions.
Cooperate with the County and utility companies in keeping respective services and facilities in operation.
PART 2 – PRODUCTS
2.1 SOIL MATERIALS
A. General: Soils used as fill shall be clean sands, similar to existing soils, with less than 5% passing the number 200 sieve when existing subgrade conditions are considered wet, as per the County. Soils as described above with less than 15% passing the number 200 sieve and meeting the requirements of the FDOT Standard Specifications Section 902-6 may be used when existing subgrade conditions are considered dry, as per the County. The sand shall have a maximum dry density of at least 100 pounds per cubic foot, according to the Standard Proctor compaction test, AASHTO T-99, ASTM D698. Provide approved borrow soil materials from off-site when enough satisfactory soil materials are not available from on-site excavations.
If the Contractor elects to import any materials, then he will do so only with the approval of the County and at his own expense, unless separate payments for such items are called for in these specifications. Provide laboratory certification that soils meet requirements of specifications.
B. Sub-Base Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, or sand. The material shall be stabilized in accordance with FDOT Standard Specifications Section 160-5.4. ASTM D 2940, with at least 95 percent passing a 1-1/2-inch sieve, and not more than 8 percent passing a No. 200 sieve.
PART 3 - EXECUTION
3.1 DEWATERING
A. Prevent surface water and subsurface or groundwater from entering excavations, from ponding on sub-grades in work areas, and from flooding project site and surrounding area.
B. Protect subgrades and foundation soils from softening and damage by rain or water accumulation.
The Contractor shall prevent the accumulation of water in excavated areas, and shall remove, by pumping or other means, any water that accumulates in the excavation. The Contractor shall prevent the accumulation of water in both structural and trench excavations and shall remove, by well point system or by other means, water which accumulates. The Contractor shall provide, install and operate a suitable and satisfactory dewatering system, when needed to dry sub-grades or other work areas. The Contractor shall comply with the latest testing requirements as set forth by the applicable regulatory agency. At a minimum, the contractor shall test once prior to dewatering, once within the first week of dewatering, and once every thirty (30) days while dewatering.
C. Establish and maintain temporary drainage ditches and other diversions outside excavation limits to convey rainwater and water removed from excavations to collection or runoff areas. Do not use trench excavations as temporary drainage ditches. Discharged water shall be clean, not silt or sediment laden, prior to discharge to untreated system and/or waters of the State.
3.2 EXCAVATION
A. Explosives: Not permitted.
B. Strip topsoil and significant root systems to whatever depths encountered in a manner to prevent intermingling with underlying subsoil or other objectionable material. Remove heavy growths of grass from areas before stripping. Where existing trees are indicated to remain, leave existing topsoil in place within drip lines to prevent damage to root systems.
3.3 STABILITY OF EXCAVATIONS
A. Comply with local codes, ordinances, and requirements of authorities having jurisdiction to maintain stable excavations.
B. All excavation work shall conform to all applicable OSHA Publications, Latest
Editions. The Contractor's method of providing protective support to prevent cave-ins shall conform to OSHA requirements. Slope excavations, shoring, and trench box usage in the field must be based on tabulated data and designed by the Contractor. The contractor is solely responsible for job site safety and shall not be compensated for required safety equipment/ devices.
3.4 EXCAVATION FOR STRUCTURES
Excavate to indicated elevations and dimensions within a tolerance of plus or minus 0.10 foot. Extend excavations enough distance from structures for placing and removing concrete formwork, maintaining a safe slope, installing services and other construction, and for inspections.
A. Footings and Foundations: Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.
B. Pile Foundations: After piles have been installed, remove loose and displaced material. Excavate to final grade, leaving solid base to receive concrete pile caps.
C. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Appurtenances: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 0.10 foot.
3.5 EXCAVATION FOR WALKS AND PAVEMENTS
Excavate surfaces under walks and pavements to indicated cross sections, elevations, and grades. Consider Dewatering and other sections as applicable.
3.6 EXCAVATION FOR STORMWATER SYSTEMS
Excavate and compact the backfill of trenches to the densities specified for embankment or subgrade, as applicable, and in accordance with the requirements of Section 2600. Consider Dewatering and other sections as applicable.
3.7 STORAGE OF SOIL MATERIALS
Stockpile excavated materials acceptable for backfill, fill soil, and topsoil materials, including acceptable borrow materials. Stockpile soil materials without intermixing.
Stockpiles shall be placed, graded, and shaped to drain surface water and prevent erosion. Cover to prevent wind-blown dust and/or erosion. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.
3.8 BACKFILL
A. Backfill excavations promptly, but not before completing the following:
1. Acceptance of construction below finish grade including, where applicable, filter fabric installation and gravel bedding.
2. Surveying locations of underground utilities for record documents.
3. Testing, inspecting, and approval of underground utilities.
4. Removal of trash and debris from excavation.
5. Removal of temporary shoring, bracing, and sheeting unless specified to remain.
B. No backfill material shall be placed, spread or rolled during unfavorable weather conditions. When the work is interrupted by heavy rain, backfill operations shall not be resumed until the moisture content of the fill is as previously specified to achieve proper compaction.
3.9 FILL
A. Preparation: Remove vegetation, topsoil, debris, wet and unsatisfactory soil materials, obstructions, and deleterious materials from ground surface prior to placing fills. Plow strip or break up sloped surfaces steeper than 1:4 so fill material will bond with existing surface. In order to ensure proper bond and prevent slipping between the original ground and fill, the surface of the original ground shall be scarified to a depth of at least three inches. Each layer of fill material shall be compacted until the required density is achieved, and the density achieved should be verified in accordance with specifications using in-place density testing.
B. When subgrade or existing ground surface is to receive fill and has a density less than that required for fill, break up ground surface to depth required, pulverize, moisture condition or aerate soil and re-compact to required density.
- 7 -
C. Place fill material in layers to required elevations for each location listed below.
1. Under grass, subbase or base material, use satisfactory excavated or borrow soil material.
2. Under walks and pavements, curbs, steps, ramps, building slabs, footings and foundations use subbase and/or base material.
3.10 MOISTURE CONTROL
A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill layer before compaction to within 2 percent of optimum moisture content.
B. Do not place backfill or fill material on surfaces that contain excessive moisture.
C. Remove and replace or scarify and air-dry satisfactory soil material that is too wet to compact to specified density. Stockpile or spread and dry removed wet satisfactory soil material.
3.11 COMPACTION
A. Place backfill and fill materials in layers or lifts not more than 12 inches in loose depth for material compacted by heavy compaction equipment, and not more than 8 inches in loose depth for material compacted by hand-operated tampers.
B. Place backfill and fill materials evenly on all sides of structures to required elevations. Place backfill and fill uniformly along the full length of each structure.
C. Percentage of Maximum Dry Density Requirements: Compact soil to not less than the following percentages of maximum dry density according to ASTM Modified Proctor):
1. Under structures, building slabs, steps, and pavements, compact each layer of backfill or fill material at a minimum of 98% Modified Proctor of the material’s maximum dry density.
2. Under lawn or unpaved areas, compact each layer of backfill or fill material at 95% Modified Proctor maximum dry density.
3.12 GRADING
A. General: Uniformly grade areas to a smooth surface, free from irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.
- 8 -
1. Provide a smooth transition between existing adjacent grades and new grades.
2. Cut out soft spots, fill low spots, and trim high spots to conform to required surface tolerances.
B. Site Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances:
1. Lawn or Unpaved Areas: Plus, or minus 0.10 foot.
2. Walks: Plus, or minus 0.10 foot.
3. Pavements: Plus, or minus ½ inch.
3.13 STABILIZED SUBGRADE
A. For stabilized subgrade, the type of materials, commercial or local, is at the Contractor's option and no separate payment for stabilizing materials will be made (other than as may be paid for as borrow).
B. When stabilizing is designated as Type B, compliance with the bearing value requirements will be determined by the Limerock Bearing Ratio Method.
Minimum LBR shall be 40.
It is the Contractor's responsibility that the finished roadbed section meets the bearing value requirements, regardless of the quantity of stabilizing materials necessary to be added. Also, full payment will be made for any areas where the existing subgrade materials meet the design bearing value requirements without the addition of stabilizing additives, as well as areas where the Contractor may elect to place select high-bearing materials from other sources, within the limits of the stabilizing.
C. After the roadbed grading operations have been substantially completed, the Contractor shall make his own determination as to the quantity (if any) of stabilizing material, of the type selected by him, necessary for compliance with the bearing value requirements. The contractor shall notify the Engineer of the approximate quantity to be added, and the spreading and mixing-in of such quantity of materials shall meet the approval of the County as to uniformity and effectiveness.
3.14 FIELD QUALITY CONTROL
A. Testing Agency Services: Allow testing agency to inspect and test each subgrade and each fill or backfill layer. Do not proceed until test results for previously completed work verify compliance with requirements.
1. Perform field in-place density tests according to ASTM D 1556 (sand cone method), ASTM D 2167 (rubber balloon method), ASTM D 293
- 9 -
(drive cylinder method), or ASTM D 2922 (nuclear method), as applicable.
a. Field in-place density tests may also be performed by the nuclear method according to ASTM D 2922, if calibration curves are periodically checked and adjusted to correlate to tests performed using ASTM D 1556. With each density calibration check, check the calibration curves furnished with the speedy moisture meter according to ASTM D 3017.
b. When field in-place density tests are performed using nuclear methods, make calibration checks of both density and speedy moisture meter at beginning of work, on each different type of material encountered, and at intervals as directed by the Engineer.
2. Paved Areas: Make at least one field density test of subgrade, base, and each compacted fill layer for every 300 linear feet of roadway or equivalent area, but in no case less than two tests. Tests shall be staggered to ensure representative sampling.
3. Unpaved Areas: Make at least one field density test of each compacted fill layer or subgrade for every 1000 square yards of area, but in no case less than two tests.
4. Other tests may be required at County’s discretion.
If, in the opinion of the County, based on testing service reports and inspection or the Engineer’s observations, subgrades, fills, or backfills are below specified density, scarify and moisten or aerate as needed, or remove and replace soil to the depth required, re-compact, and re-test until required density is obtained at no additional expense.
3.15 REPAIR & CORRECTIONS
A. Protecting Graded Areas: Protect newly graded areas from traffic and erosion.
Keep free of trash and debris.