This document outlines rework and repair procedures for nonconforming materials under a federal contract. The contractor must document rework procedures and submit them to the Government Quality Assurance Representative for review prior to implementation. Repair procedures require submission of a Request for Deviation/Waiver to the Contracting Officer for written approval. For any rework or repair submission, the contractor must include a description of the original nonconformance and corrective actions to prevent recurrence. The procedure must also include reinspection provisions taking precedence over technical requirements and providing assurance that items meet reprocessing standards. These requirements flow down to all contractors, suppliers, vendors and subcontractors.
The related federal contract opportunity is a competitive solicitation from the Department of the Air Force Materiel Command Lifecycle Management Center for F-22 thermal batteries. Teledyne Risi and Chemring Energitic Devices are eligible to bid on providing 100 each of their respective battery models by the unspecified response date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment FA281321R3039 001.pdf | ||
| Solicitation FA281321R3039.pdf | ||
| CDRLs 21-50107.pdf | ||
| Form 1653.pdf | ||
| Form 807- 015873591.pdf | ||
| Form 807- 015155924.pdf | ||
| SPI F01-515-5924.pdf | ||
| Thermal Battery Quali (Signed).pdf | ||
| SPI F01-587-3591.pdf | ||
| FORM 158 FD2020-21-50107.pdf | ||
| TransInstruction4.pdf | ||
| SOW SPI.pdf | ||
| JFQR F-22 Thermal Battery Master_Signed.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(ES7034)