Engineering Implementation Plan - B-1 Transient Tail Stand-updated.docx

DOCX document 13 KB Posted

Attached to
B-1 Transient Tail Stands Federal contract opportunity
Solicitation number
FA812523R0004
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This engineering implementation plan outlines the milestones and responsibilities for providing one transient tail maintenance stand set for B-1 bombers. The contractor must deliver plans for review within 30 days of award, parts for assembly within 120 days, and install the equipment to conduct fit and function checks by 150 days. The contractor is then responsible for addressing any punch list items by 170 days and submitting final documentation by 230 days after award. The related federal contract opportunity is a solicitation from the Air Force Materiel Command Air Force Sustainment Center to provide one B-1 transient tail maintenance stand. The contractor must analyze workload requirements, design the stand, develop instructional materials, and conduct a fit test, including delivery.

View the file

Other files for this federal contract opportunity

Other files attached to B-1 Transient Tail Stands, newest first.
File Type Posted
H3WA14 Combined Synopsis.docx DOCX document
SOW - B-1 Transient Tail Maintenance Stand Extra Requirements.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Engineering Implementation Plan One (1) Transient Tail Maintenance Stand Set for B-1 Bomber Maintenance

Milestone 1 – Prefabrication review (PFR) Estimated Completion Date: 30 days after contract award Responsible Parties: Contractor, Project POC Contractor shall deliver PFR based on SOW requirements to 76 AMXG/MXDEB office for review and discussion Milestone 2 – Parts delivered Estimated Completion Date: 120 days after contract award Responsible Parties: Contractor Contractor shall deliver stand parts for assembly.

Milestone 3 – Equipment Assembly, Fit, and Function Check Estimated Completion Date: 150 days after contract award Responsible Parties: Contractor, Project POC Contractor shall deliver and install equipment in order to ensure proper equipment fit and functionality. Installation steps are as follows: The upgrade will be completed on-site. Contractor will ensure all space, foundation, utility requirements are met. Contractor will perform functional check to ensure test stand operational prior to “Milestone 4.” Contractor shall schedule and perform fit and function check with project POC (Engineer), to ensure proper equipment fit and functionality per SOW requirement. Contractor and Project POC will walk-through and put together a list of punch-list items for corrective actions.

Milestone 4 – Punch-list Estimated Completion Date: 170 days after contract award Responsible Parties: Contractor, Project POC Contractor shall ensure all punch-list items are addressed. A final walk-through shall be conducted with contractor and Project POC.

Milestone 5 – FOC Documents Estimated Completion Date: 230 days after contract award Responsible Parties: Contractor, Project POC FOC (Full Operational Capability) documents will be submitted to properly account for equipment on the CACRL account.