Addendum #1 - Electrical Gear Replacement

This addendum to the Electrical Gear Replacement project modifies and supplements the original solicitation issued by the State of Michigan. The addendum addresses electrical equipment replacement requirements and clarifies specifications, terms, and conditions governing the procurement. Key modifications include adjustments to technical specifications, delivery requirements, and project scope as originally outlined in the base solicitation. Bidders are required to acknowledge receipt of this addendum as part of their proposal submission, and all previous solicitation documents remain in effect except where expressly modified by this addendum.

The addendum establishes that all bids must incorporate the revised terms and conditions specified herein and must demonstrate compliance with updated technical and performance standards. Prospective bidders should carefully review all modifications to ensure complete understanding of the revised requirements, including any changes to pricing structures, delivery schedules, or performance obligations. This addendum supersedes conflicting provisions in the original solicitation and becomes an integral part of the contract documents that will govern the final agreement between the State of Michigan and the selected contractor.

View the file

Other files for this state and local contract opportunity

Other files attached to Electrical Gear Replacement, newest first.
File Type Posted
Familial Disclosure Statement.pdf PDF
Electrical Gear Replacement Add#2.pdf PDF
Iran Business Relationship Affidavit.pdf PDF
Electrical Gear Replacement - SCC.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

714 East Midland Street | Bay City, Michigan 48706 P: 989.894.4300 | F: 989.894.9930 www.macmillanassociates.com | Since 1963

Saginaw Career Center Electrical Gear Replacement MAI: 2023-01116 BID Package #4 Date: May 22, 2026

ADDENDUM NO. 1

To: All Bidders

From: MacMillan Associates, Inc.

714 East Midland Street Bay City, MI 48706

(989) 894-4300

The following are changes, revisions, corrections, or clarifications to the construction documents and shall include all labor, materials, and supervision as applicable.

ELECTRICAL

Item No. 1

The demolition of existing and installation of new busway and fusible plug-in units for building C shall be included as base bid in lieu of an add alternate. All work shown on drawings shall be part of base bid.

Item No. 2

Reference Sheet SE1.3 (Not Re-Issued)

A. Primary service electrical pad shall be located a minimum of 20’ from the edge of the west side walk in lieu of the listed 10’ on the drawings. Field locate new location to avoid existing down spout.

Item No. 3

Reference Sheet E1.2, E2.4, E3.5 (Not Re-Issued)

A. Electrical contractor shall be responsible for reworking existing housekeeping pad to accommodate new switchboards MSB-1, MSB-2, and MSB-3.

Item No. 4

Reference Sheet E3.5 (Not Re-Issued) A. The electrical contractor shall hire the services of a mechanical contractor to reroute the two existing water pipes out beyond the new electrical switchboard (MSB-3) to meet NEC requirements. The mechanical trade shall field verify the pipe sizes and service.

The mechanical trade shall repair and re-insulate the piping as necessary. Piping and insulation shall match existing. See image below.

714 East Midland Street | Bay City, Michigan 48706 P: 989.894.4300 | F: 989.894.9930 www.macmillanassociates.com | Since 1963

MacMillan Associates, Inc.

Christian Day/ Jay Fox

Attachment: Walk-Thru Sign In Sheet