V2401015Switchgear.docx

DOCX document 31 KB Posted

Attached to
Electric Switchgear Maintenance & Testing Federal contract opportunity
Solicitation number
DTRT5715Q80076
Issued by
Department of Transportation Immediate Office of the Secretary Transportation

View the file

Other files for this federal contract opportunity

Other files attached to Electric Switchgear Maintenance & Testing, newest first.
File Type Posted
Switchgear_final_SOW.docx DOCX document
Switchgear_Questions.docx DOCX document
Switchgear_One_Line.pdf PDF
Wage_Determination_2005-2255_Revision_18_Dated_7-8-15.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. DTRT5715Q80076 PR No.V2401015

STATEMENT OF WORK

ELECTRIC SWITCHGEAR MAINTENANCE AND TESTING

Department of Transportation Volpe National Transportation Systems Center Cambridge, MA

Introduction/Background

The Volpe Center’s high voltage electricity is distributed through two 13.8Kv feeds to a series of switchgear substations located in all six Volpe buildings. Each switchgear system consists of a switch, breaker and transformer. This requirement is for cleaning, maintenance and testing of switchgear in accordance with National Electrical Testing Association (NETA) standards.

Scope of Work

The contractor shall provide all equipment, parts and personnel necessary to perform all maintenance and testing of switchgear including switches, breakers and transformers for the switchgear listed below:

Building
Floor
Designation
Feed
Kirk Key
Manufacturer
1
13
101A
A

Westinghouse

1
13
102A
A

Westinghouse

1
1
101B
B

Westinghouse

1
1
102B
B

Westinghouse

3
G
401A
A
From B4
Westinghouse
4
1
401B
A
From B3
Westinghouse
5
1
301A
A

Westinghouse

5
Courtyard
Main
A&B

Westinghouse

5
1
Chiller
Bldg. 5
From B5
Square D
6
1
601A
Bldg. 5
From B5
Westinghouse

In order to accomplish this work under the safest conditions, a series of electric shutdowns will be required. All shutdowns are to be performed on Saturdays outside of heating and cooling season (shoulder seasons) to minimize disruption to building occupants. Volpe Center Office of Facilities Management personnel will coordinate electrical shutdowns with building occupants, contractor and the local utility company.

The suggested shutdown schedule is as follows:

Shutdown #
Power Feed
Switchgear
Buildings Affected
Refeed
1
A&B
Main, 301A
All
Local Utility
2
A
101A, 102A, 401A
Top 1, 3
301A, 401B
3
B
101B, 102B, 401B
Bottom 1, 4
401A, 301A
4
None
301A, 601A,2400V, Chiller
5 & 6
None

Shutdown #1 will require the assistance of the local electrical utility, Eversource. The contractor shall coordinate efforts with Eversource while cleaning/maintenance of main switchgear.

All shutdown schedules are weather-dependent. Final decision on shutdown status will be made by the COR on the day before the scheduled shutdown and determined by weather conditions for operational safety.

Prior to any shutdown, government personnel will energize emergency generators for computer rooms and life safety circuits.

This is a suggested schedule only as the contractor will be required to submit a shutdown schedule and maintenance/testing plan for approval by the Contracting Officers Representative (COR).

Work Requirements Contractor shall perform thorough site inspection of all switchgear. Review drawings, reports and one-line diagram. Then submit a shutdown schedule and maintenance/testing plan for approval by the COR.

Assemble all equipment and personnel to secure power, complete maintenance/testing, and restore power to the facility within a 12 hour timeframe.

Provide all tools, parts and personnel to perform complete testing, cleaning and maintenance on two (or more) switchgear substations during a single shutdown.

Shutdown of main switchgear (Building 5) will require assistance from the electric utility. The contractor shall coordinate efforts with Eversource and subcontract high-voltage utility services.

Certain switchgear assemblies are double-ended and will require disconnect or refeed with Kirk Key interlocks. Contractor will ensure Kirk Key procedures are in place prior to any shutdown. All switchgear must be completely de-energized before cleaning.

Service and confirm function of multi-function protection relays.

In addition to switchgear in Building 6, provide testing and maintenance for 2400V transformer and grounding resistor bank & relay.

Switchgear shall be inspected, adjusted, cleaned and tested in accordance with NETA Sections 7.2.1.2, Transformers, Section 7.5.1.2, Switches, Section 7.6.1.1, Circuit Breakers (attached) and associated Sections 3, 4 & 5.

Check batteries and charger at Building 5 main switchgear for proper operation.

Electrical conductors outside the switchgear housing are not included in this SOW. The intent of this contract is to perform maintenance on, not replace, switchgear components. Contractor will be responsible for replacing any control circuit fuses and indicator lights. Any damage to equipment will be brought to the attention of the COR.

Contractor shall perform all work in accordance with NETA Section 5.1, OSHA, NFPA, and state, local and utility safety standards and provide safety briefing prior to commencement of work.

Contractor shall provide documentation that all contractor personnel meet qualification and requirements of NETA Section 3.

Submit test report in accordance with NETA Section 5.4

Deliverables

Description
Format
Due Date
Shutdown Schedule and Maintenance/ Testing Plan from site survey
MS Word
30 days from Notice to Proceed
Testing Report
MS Word
90 days from Notice to Proceed

All deliverables shall be provided to COR

Government Furnished Information

Volpe Electric 1-Line Diagram

Previous Testing Reports

References

NETA Section 3. Qualifications of Testing Organization and Personnel NETA Section 4. Division of Responsibility NETA Section 5. General NETA Section 7. Inspection and Testing Procedures Can be found at: http://www.netaworld.org/sites/default/files/public/ansineta_ats2013_intro_toc_scope.pdf

Place and Period of Performance

All work will be performed at the Volpe Center, 55 Broadway, Cambridge, MA 02142. Period of performance will be Sepetmber 01, 2015 through December 31, 2015.

Pre-Bid Site Visit

A pre-bid site visit is scheduled for August 12, 2015 and all interested contractors are invited to attend. All notifications of attendance should be emailed to Contracting Officer (CO). Questions concerning the SOW shall be forwarded in writing to the Contracting Officer (CO). Comment by Guy, Christine (VOLPE): Select a date for site visit

Sustainability

To the maximum extent possible and consistent with the Federal Acquisition Regulations Part 23, the Government requires during the performance of the work under this Statement of Work (SOW) the Contractor to provide or use products that are: energy efficient (ENERGY STAR® or Federal Energy Management Program (FEMA)-designated); water-efficient; bio based; environmentally preferable (e.g., EPEAT-registered, or non-toxic or less toxic alternatives); non-ozone depleting; or made with recovered materials. Unless otherwise identified in this SOW, each recovered materials or bio based product provided and delivered must meet, but may exceed, the minimum recovered materials or bio based content of an EPA- or USDA-designated product. The sustainable acquisition requirements specified herein apply only to products that are required to be: (1) delivered to the Government during contract performance; (2) acquired by the contractor for use in performing services (including construction) at a Federally-controlled facility; (3) furnished by the contractor for use by the Government; or (4) specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance.