Galley_Deck_Repairs_Quote_Sheet.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
TS GOLDEN BEAR Galley Deck Repairs Federal contract opportunity
Solicitation number
DTMA9417Q00023
Issued by
Department of Transportation Maritime Administration

About this file

Quote Sheet

View the file

Other files for this federal contract opportunity

Other files attached to TS GOLDEN BEAR Galley Deck Repairs, newest first.
File Type Posted
Galley_Deck_Repairs_SOW.pdf PDF
Galley_Deck_T&C.pdf PDF
SF1449.pdf PDF
ATTCH_CLAUSES.pdf PDF
wage_determination_Solono_Co_2005_rev_18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

TS Golden Bear - Galley Deck Repairs--Quote SheetEstimated costs - LaborEstimated costs - MaterialTotal Estimated costs
Item #1 - Remove following to allow room for deck removal - Soup pots (3); Soup pot foundation; Drain tray in front of soup pots; Grease Trap; all foundation below all these items; drain pipe from steamer; heat box in serving area; Other areas that are deemed necessary by awarded contractor
Item #2 - Cover all cabinets and galley equipment to protect from removal of top coat and underlayment and scaling of steel
Item #3 - Ballast tank covers - Modify to include new outside ring to allow for cover over the manhole cover; Details to be supplied during the ship check walk thru; 2 locations = fabricate new ring SS material to allow 3/4" seating area
Item #4 - Remove present top coat and underlayment tile and dispose of same; Do Not remove underlayment below tile until all tile removed and inspection by COR and CE and Chief Mate
Item #5 - Inspect the underlayment below the tile and report same via CFR as to condition and useability for new top coat and list total areas good and bad
Item #7 - Provide costs to do the following: (1) Remove 400 sq ft of the underlayment orignally set below the removed tile under Item #5; (2) Add underlayment to height of remaining underlayment for the 400sq ft including the mechanical scaling of steel to SP3 in preparation to priming same- approximately 400 square feet
Item #8 - Fabricate and install new soup pot foundation using pipe and mild steel shaped to fit bottom of soup pots and grease trap and rectangular soup pot. Make arrangement to allow for access to apply underlayment and top coat. Coat with 2 coats of primer and 2 coats of top coat per Chief Mate specifications
Item #9 - Apply proper amount of underlayment and coving to make up height to fit new ballast tank covers
Item #10 Apply Phoenix One-Step to all areas to maximum allowable manufacturer's specifications - cove all sides
Item #11 Apply 2 layers clear coat to all areas with non-skid
Item #12 Reinstall Soup Pots and Grease trap and drain and other equipment removed for access
Item #13 Remove all dust protection and clean up to satisfaction of Chief Mate and Chief Engineer
Supplementary Labor -- 60hrs @ $80/hr
Supplementary Material -- $10,000$ 10,000.00
Total Costs$ 10,000.00