Pavement Recommendation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| VETS-100A-Form.pdf | ||
| FP03_Errata.pdf | ||
| IFB_Solicitation_Book_FTNP-GWMP_1A109.pdf | ||
| Categorical_Exclusion_Form_(NEPA).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| FP03_Eng_.pdf | ||
| Plans_FTNP-GWMP_1A109.pdf | ||
| ADV_Subcontracting_Plan.doc | DOC document | |
| Synopsis_FTNP-GWMP_1A109.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 3 Pages
Form FHWA-201 (Rev. 11-67)
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA- 121 for informal correspondence. MINUTE-MEMO
M:\PROJECTS\gwmp\1a109\Techserv\Pavement\Correspondence\PRA-GWMP 1A109 Pavement Memo.doc
SUBJECT: Pavement Recommendation for PRA-GWMP 1A109
TO MESSAGE/COMMENT FROM/DATE
R. Satasiya PS&E Project Manager
And:
C. Burnell Highway Design Manager
Through:
A. Teikari Highway Design Engineer
To support developing 95% PS&E for the project, we’re submitting our findings and pavement recommendations for the project PRA-GWMP 1A109. The project site is located along the George Washington Memorial Parkway in Arlington County, VA. The project consists of the resurfacing and rehabilitation of the Mainline Parkway between the Boundary Channel Bridge and the Reagan National Airport ramps (~1.6 miles) and adjacent ramps. Please note that upon completion further analyses, this recommendation is subject to change, and any changes will be included as an addendum to this memo.
Mainline Parkway (NPS Routes 0001 & 0002)
Based on our pavement condition survey and field investigation on May 13th and 14th, 2014, the existing mainline Parkway is exhibiting moderate to high severity fatigue cracking, longitudinal and transverse cracking, potholes, patch deterioration, and oxidation. In order to provide ride quality improvements, we are recommending the existing asphalt concrete (AC) pavement be milled to a depth of 4-inches, and overlaid according to the minimum requirements laid out below in Table 1 between stations 570+76.80 to station 587+00 in the northbound lanes and between stations 570+76.80 to station 586+10 in the southbound lanes. The permissive specifications for Warm-Mix Asphalt (WMA) should also be included as an option.
Table 1. Mainline Parkway Pavement Recommendations
Layer Minimum Thickness
(in)
Comments
AC Surface Course 1 ½
Superpave Asphalt Concrete Pavement (SACP), 0.3 to < 3 x 106 ESAL’s, 3/8”
Nominal Maximum Size Aggregate (NMSA), Type I Smoothness
Asphalt Tack Coat --- AC Tack Coat as per Section 412 of the
FP-03 Specifications
AC Base Course 2 ½ SACP, 0.3 to < 3 x 106 ESAL’s, ¾”
NMSA
Asphalt Tack Coat --- AC Tack Coat as per Section 412 of the
FP-03 Specifications
Additionally, an area in the southbound lanes between station 586+10 to 588+70 will require spot repairs. These areas, along with any others identified in the field requiring further repair after milling by the CO, should be reconstructed
S. O’Brien Pavement Engineer
B. Eshbaugh Pavement Team Leader
S. Whittemore Technical Services Engineer
05/22/2014
Page 2 of 3 Pages
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to according to the minimum requirements laid out in Table 2 below.
Table 2. Spot Reconstruction Recommendations
Minimum Thickness
Course 1 ½
Superpave Asphalt Concrete Pavement (SACP), 0.3 to < 3 x 106 ESAL’s, 3/8”
Nominal Maximum Size Aggregate (NMSA), Type I Smoothness
Asphalt Tack Coat --- AC Tack Coat as per Section 412 of the
FP-03 Specifications
AC Base Course 2 ½ SACP, 0.3 to < 3 x 106 ESAL’s, ¾”
NMSA
Asphalt Tack Coat --- AC Tack Coat as per Section 412 of the
FP-03 Specifications
AC Base Course 4 SACP, 0.3 to < 3 x 106 ESAL’s, 1”
NMSA
Asphalt Prime Coat --- AC Prime Coat as per Section 411 of the FP-03 Specifications
Aggregate Base Course 8
Base Aggregate, Grading C or D, according to Subsection 703.05(b) of the FP-03 Specifications
Geotextile --- Geotextile, Type II-B, as per Section 714 of the FP-03 Specifications
The section of the Parkway south of station 586+10 in the southbound lanes and station 587+00 in the northbound lanes to the project terminus, along with the adjacent ramps, are exhibiting moderate to high severity transverse and longitudinal cracking, oxidation, and areas of fatigue cracking. These sections, however, do not have an existing pavement structure capable of supporting a 4-inch mill and overlay during construction. Therefore, in order to improve ride quality, we are recommending the existing AC pavement be milled to a depth of 1 ½-inches and overlaid according to the minimum requirements laid out below in Table 3.
Page 3 of 3 Pages
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to
Table 3. Section Overlay Recommendations
Minimum Thickness
Course 1 ½ SACP, 0.3 to < 3 x 106 ESAL’s, 3/8”
NMSA, Type I Smoothness
Asphalt Tack Coat --- AC Tack Coat as per Section 412 of the
FP-03 Specifications
Attached are photos of typical existing conditions, spot repair design analysis, and pavement coring results.
cc: Pavement (S. O’Brien), Highway Design (B. Beucler), TS Reading w/ attachments
Photo #1: Southbound G.W. Memorial Parkway
Photo#2: Northbound G.W. Memorial Parkway
Photo #3: North End of Project Limits - Southbound
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare Computer Software Product
Flexible Structural Design Module
GWMP Mainline South of Humpback
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 1,618,648 Initial Serviceability 4.2 Terminal Serviceability 3 Reliability Level 90 % Overall Standard Deviation 0.49 Roadbed Soil Resilient Modulus 7,000 psi Stage Construction 1
Calculated Design Structural Number 4.31 in
Rigorous ESAL Calculation
Performance Period (years) 20 Two-Way Traffic (ADT) 98,578 Number of Lanes in Design Direction 3 Percent of All Trucks in Design Lane 60 % Percent Trucks in Design Direction 60 %
Vehicle Class
Percent of
ADT
Annual
Growth
Average Initial Truck Factor
(ESALs/ Truck)
Annual % Growth in
Truck Factor
Accumulated 18-kip ESALs over Performance Period
1 0.1 2 0.0004 0 123 2 99.5 2 0.0007 0 214,868 3 0.2 2 1.2 0 740,391 4 0.1 2 1.85 0 570,718 5 0.1 2 0.3 0 92,549
Total 100 - - - 1,618,648
Growth Simple
Total Calculated Cumulative ESALs 1,618,648
Specified Layer Design
Material Description
Struct Coef.
(Ai)
Drain Coef.
(Mi)
Thickness (Di)(in)
Width
(ft)
Calculated
SN (in)
1 SACP 0.44 1 8 11 3.52
2 GAB 0.12 1 8 11 0.96
Total - - - 16.00 - 4.48
Core Direction Location AC (in) Base (in) PCC (in)
SB‐01 Southbound 583+20 9.5 ‐ ‐
SB‐02 Southbound 593+10 4.5 4 ‐
SB‐03 Southbound 608+20 5.5 4 ‐
SB‐04 Southbound 631+75 7 ‐ 6
NB‐01 Northbound 636+90 6.5 ‐ 7
NB‐02 Northbound 617+25 4.5 4 ‐
NB‐03 Northbound 614+10 4.5 ‐ ‐
NB‐04 Northbound 597+25 5.5 4 ‐
NB‐05 Northbound 582+75 8 4 ‐
GWMP 1A109 ‐ Pavement Coring Results
| 2014-05-22T16:26:05-0400 | |
| SEAN E OBRIEN |
| 2014-05-23T08:50:17-0400 | |
| WILLIAM H ESHBAUGH JR |
| 2014-05-23T11:58:26-0400 | |
| MOUNIR A ABOUZAKHM |
File details come from the government source that posted it. Updated .