Questions_and_Answers.pdf
PDF 82 KB Posted
- Attached to
- CO FLAP 301(1) RED DIRT BRIDGE Federal contract opportunity
- Solicitation number
- DTFH6816B0008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Tabs.pdf | ||
| Bid_Opening_Summary.pdf | ||
| Questions_and_Answers.pdf | ||
| Questions_and_Answers.pdf | ||
| Red_Dirt_Bridge_Plans-Cross_Sections_FINAL_stamped.pdf | ||
| Red_Dirt_Road_Bridge_Inspection_Report.pdf | ||
| Red_Dirt_Bridge_Plans_FINAL_stamped.pdf | ||
| Red_Dirt_Bridge_Geotechnical_Report_FINAL.pdf | ||
| DTFH6816B00008_IFB.pdf | ||
| Red_Dirt_Bridge_Hydraulics_Report_FINAL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTFH6816B00008 04/25/2016
CO FLAP 301(1)
RED DIRT BRIDGE
04/21/2016
QUESTION #1
Under the pavement markings for the above mentioned project I cannot find what type of material the type D solid references, nor the other type D for the stop bar?
Response: Type D is Epoxy Marking. It is indicated in Section 634.01 of the FP-14.
04/25/2016
QUESTION #2
Section 108.1 states contract completion date by March 15, 2017. Section 107.10(9) states no construction of temporary levy or platforms until August 15th.
With the time constraints working in the waterway and completion date of March 15, 2017, this will require working during winter months. If there are weather delays will the completion date be extended?
Response: FHWA does anticipate that winter work and cold weather protection will be required for this project.
The completion date will only be extended for weather delays if the contractor can prove that the conditions during construction are worse than average conditions over the past 10 years and actually prevent construction of critical path items.