QA.pdf
PDF 75 KB Posted
- Attached to
- CA-BLM-5910(1) Federal contract opportunity
- Solicitation number
- DTFH6815B00003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Tabulation_Report.pdf | ||
| Bid_Tabulation_Report.pdf | ||
| Kaweah_Bid_Summary.pdf | ||
| Amendment_A001.pdf | ||
| FY13_Kaweah_River_Bridge_Inspection_Report.pdf | ||
| FY13_Kaweah_Flume_Bridge_Inspection_Report.pdf | ||
| CA-BLM5910(1)-100_plans.pdf | ||
| DTFH6815B00003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CA BLM 5910(1), East Fork Kaweah River Bridge Replacement
Questions & Answers
March 3, 2015
Question: What are the liquidated damages for the CA BLM East fork if the Kaweah bridge project?
Answer: See Table 108-1, Charge for Liquidated Damages for Each Day Work Is Not Substantially Completed located in Section 108.04 of the FP-14. A link to the FP-14 is located on page A-I of the solicitation.
March 4, 2015
Question: I reviewed the plans and specifcations for the above reference project and have the following questions:
1. Drawings are not fully clear on what's existing vs. new. Please provide As-Builts to clarity.
Answer: The existing Kaweah Bridge structure is shown on sheets S4, S5, and the top of S6. The existing typical section for the 6 Mile Flume bridge is shown on the top of sheet S13.
2. Are there any pictures available of existing bridge? If so, please email me a copy.
Answer: See the Structure Inspection Reports (to be posted to Fedbizops shortly) for photos.
3. When is the last day to submit questions?
Answer: See page A-iii of the solicitation.
Question: What is the engineers estimate amount for project # DTFH 68 15 B 00003.
Answer: See page A-3 of the solicitation.