amendmentA001.pdf

PDF 1 MB Posted

Attached to
CO PFH 80-2(3), Guanella Pass Road Federal contract opportunity
Solicitation number
DTFH68-08-B-00012
Issued by
Department of Transportation Federal Highway Administration

About this file

Amendment A001

View the file

Other files for this federal contract opportunity

Other files attached to CO PFH 80-2(3), Guanella Pass Road, newest first.
File Type Posted
guanella A003.pdf PDF
guanella A002.pdf PDF
APPENDICES.pdf PDF
InvitationforBid.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

mcgehee Typewritten Text mcgehee mcgehee

REVISED 03/25/08

AMENDMENT A001

TABLE OF CONTENTS

Page No.

Notice to Bidders and Offerors ...........................................................................................1 to 4

SF-1442 Solicitation, Offer, and Award .................................................................... A-1 to A-2

Additional Solicitation Information............................................................................ A-3 to A-4

Bid Schedule Instructions and Basis for Award .......................................................... B-i to B-ii

Bid Schedule ..............................................................................................................B-1 to B-59

SF-24 Bid Bond ..........................................................................................................C-1 to C-2

SOLICITATION PROVISIONS

Representations and Certifications/Bidder Qualifications...........................................D-1 to D-5

Instructions to Bidders ..................................................................................................E-1 to E-5

CONTRACT CLAUSES

Index to Contract Clauses ........................................................................................................F-1

Contract Clauses ......................................................................................................... F-2 to F-13

Minimum Wage Schedule............................................................................................G-1 to G-7

SPECIAL CONTRACT REQUIREMENTS

General.......................................................................................................................... I-1 to I-12

Construction................................................................................................................ I-12 to I-46

Materials ..................................................................................................................... I-47 to I-49

APPENDICES

Department of the Army 404 Permit....................................................................................... Appendix A

Colorado 401 Certification ..................................................................................................... Appendix B

Sample Timber Sale Contract ................................................................................................ Appendix C

Xcel Energy Security Screening Questionnaire...................................................................... Appendix D

Arapaho and Roosevelt National Forests and Pawnee National Grasslands Noxious Weed Management Plan.........................................................................................Appendix E

Spill Response..........................................................................................................................Appendix F

Material Use and Staging Area Agreement ............................................................................ Appendix G

CO PFH 80-2(3)

Guanella Pass Road

AMENDMENT A001

I-16

Implement approved modifications within seven calendar days following the date of the inspection when deficiencies or necessary corrections were first noted.

(7) Application. At least 10 days prior to the commencement of construction submit an application form consistent with Part IA of the GP and certification that the SWMP is complete to:

Colorado Department of Public Health and Environment Water Quality Control Division

WQCD-P-B2

4300 Cherry Creek Drive South Denver, Colorado 80246-1530

The application form can be downloaded from:

http://www.cdphe.state.co.us/wq/PermitsUnit/stormwater/SWConstructionApplication.pdf.

Include a copy of the signed application and certification in the SWMP.

(8) Inactivation Notice or Transfer of Permit. When the site has been finally stabilized submit an Inactivation Notice to the CDPHE at the above address. Submit a Notice of Transfer and Acceptance to CDPHE if the responsibility for storm water discharges from the project is transferred to another agency prior to final stabilization.

(d) Contract for the Sale of Mineral Material (aggregate) and Special Use Permit. The Arapaho National Forest has approved a contract for the Sale of Mineral Material for this project.

Mineral material for this project will be free-use as long as it is utilized within the ROW. A Special Use Permit has been obtained from the Arapaho National Forest to authorize activities within Temporary Construction Easement areas. Both the contract and permit were applied for and will be held by the Federal Highway Administration for this contract. All requirements for these permits are included in the contract through the FP-03 and these Special Contract Requirements.

(e) Timber Sale Contract. A timber sale contract is required to harvest and purchase merchantable timber from National Forest Lands. (See subsection 201.06 for definitions of merchantable timber.) Approximately 15.4 ccf (1,540 cubic feet) of timber will be removed for this project having an estimated value of $650. The final volume and value will be determined when the clearing limits have been established and the timber is cruised using standard USFS appraisal methods. The contract shall be awarded and money collected prior to the start of clearing and grubbing operations. An example of the Timber Sale Contract is in the Appendices.

I-63

Guanella Pass Road

AMENDMENT A001

Measurement

157.15 Add the following:

Normal maintenance of erosion control devices as directed by CO will be measured under Section 623 – General labor. Do not measure maintenance required due to damage from equipment or the contractor’s operations.

Section 158. – WATERING FOR DUST CONTROL

Construction Requirements

158.03 General. Add the following:

See Subsection 105.02 (a) for government furnished water sources.

Section 201. – CLEARING AND GRUBBING

Description

201.01 Delete the text and substitute the following:

This work consists of clearing and grubbing within the clearing limits designated by the CO based on the dimensions shown in the plans, adjusted to fit field conditions.

201.03 General. Add the following:

Prior to the start of any clearing or grubbing operations, obtain a timber harvest permit as described under Subsection 107.01 and establish slope stakes and tentative clearing limits in accordance with Subsection 152.03 (c) and (d) and the details shown on the plans. Mark existing trees more than 125 mm diameter breast height (DBH) and other significant vegetation along the clearing limits proposed to be removed with white surveyors ribbon. Schedule and attend a site meeting with the CO and the designated representatives of the Forest Service and Clear Creek County to determine which vegetation, rock formations, or other features located along the tentative clearing limits will remain and which will be removed. Schedule these meetings after completing staking and marking for a minimum of 750 meters of continuous roadway. Schedule subsequent meetings as the staking progresses.

During the meetings the CO will either approve the clearing limits as staked or direct the Contractor specifically how to adjust the clearing limits to preserve existing vegetation, rock formations, or other features. When directed, recatch slope stakes at a new slope ratio in

I-64

Guanella Pass Road

AMENDMENT A001

REVISED 03/25/08

accordance with Subsection 152.03(l). Re-establish clearing limits and adjust markings on existing trees and vegetation to be removed along the clearing limits, in accordance with the directions of the CO.

If any revisions to the clearing limits are required after they have been approved, schedule another meeting with the CO and the designated representative of the Forest Service to review and approve the changes. Maintain the markings and the clearing limit stakes for the duration of the contract. Upon completion of the contract remove all markings and stakes.

When completing any construction operations near the clearing limits adjust operations as necessary to avoid damage to the vegetation designated to remain in place. Remove existing vegetation designated for removal in a way that does not damage adjacent vegetation that is to remain. Restore, repair, or replace all vegetation damaged by unauthorized cutting, improper operation of equipment, stockpiling of materials, or tracking of grass and other areas by equipment in accordance with Subsection 107.02. Install temporary fencing prior to clearing and grubbing operations in all sensitive locations as shown on the plans, or designated by the CO.

Maintain temporary fencing for the duration of the contract and remove upon completion.

201.05 Grubbing. Insert the following before the first paragraph:

Limit the combined grubbing and grading operations area to 3 hectares of exposed soil at one time.

201.06 Disposal. Add the following after the first sentence:

Merchantable timber is defined as Saw Logs and Products Other Than Logs. Saw Logs are greater than 180 millimeters in diameter, at least 2.4 meters in height, and are a minimum of 33 1/3% sound. Products Other Than Logs (POL) are a minimum of 125 mm and maximum of 180 millimeters in diameter, at least 2.5 meters in length, and are a minimum of 50% sound. All other timber material is considered slash and will be disposed of according to 203.05 (e). All merchantable timber shall be removed from the project within 30 days of falling.

All timber greater than 180 millimeters in diameter will be reduced into 1.2 meter sections or less. No timber larger than 1.2 meter in length will be allowed to be removed from the project.

All other timber material is considered slash and will be disposed of according to Subsection 203.05(e). All timber shall be removed or disposed of from the project within 30 days of falling.

Section 202. – ADDITIONAL CLEARING AND GRUBBING

Description

202.01 Add the following:

This work also consists of the scaling and cleaning of brow at the top of existing cut slopes.

I-101

Guanella Pass Road

AMENDMENT A001

258.03 General. Add the following:

Provide vertical contraction/expansion joints in concrete stem as shown on the plans and at 7.315 m maximum spacing to coincide with form liner vertical “saw tooth” joint pattern. Construct vertical expansion joints in the concrete stem, including the simulated stone masonry surface treatment, for its full height at 21.945 m maximum spacing.

Construct wall footing with vertical steps to follow the bottom of wall profile as shown in the plans. Locate steps along the bottom of wall at distances divisible by 7.315 m (unless otherwise noted) to coincide with the form liner joint pattern. Provide vertical step heights in 0.305 m increments to match the “saw tooth” joint geometry of the form liner pattern.

Construct the top of wall, including to following the roadway shoulder profile as shown on the plans. Do not step top of wall.

Provide the simulated stone masonry surface treatment at the ends of wall. Return the form liner pattern around the corner at the ends of all walls per form liner manufacturer’s recommendations to produce an aesthetically pleasing continuation of the stone pattern.

Bottom of footing shall extend 1.0 m minimum below finished grade for frost protection. Footing shall be embedded an additional amount as required to provide minimum bench width between toe of footing and finished fore slope of adjacent grade as shown on the plans.

Measurement

258.08 Delete the second ,third, and fourth paragraphs and substitute the following:

Measure each wall by the lump sum.

Do not measure the following for payment: wall excavation, wall backfill, wall select backfill, foundation fill, structural backfill, structural concrete, reinforcing steel, simulated stone masonry surface, joint material, geocomposite sheet drain, perforated pipe, outlet pipe, and temporary traffic barrier.

Payment

258.09 Delete the text of this Subsection and substitute the following:

The accepted reinforced concrete retaining walls will be paid for under 25701 lump sum pay items for each wall.