DRAFT GC_Schedule.pdf

PDF 12 MB Posted

Attached to
ACC Replacement 21 Area Initial Outfitting Project Federal contract opportunity
Solicitation number
W9127S21Q6003
Issued by
Department of the Army Corps of Engineers Engineering District Little Rock

About this file

This document provides details on an upcoming federal contract opportunity for an initial outfitting project at Camp Pendleton, California. The U.S. Army Corps of Engineers Little Rock District intends to issue a Request for Quote for the ACC Replacement 21 Area Initial Outfitting Project with an estimated value between $5-10 million. The simplified acquisition procedures of FAR Part 13 and commercial items procedures of FAR Part 12 will apply to this requirement, which will be set aside solely for Service-Disabled Veteran-Owned Small Businesses. Interested parties can submit questions through ProjNet until July 18, 2021, and quotes are due on July 23, 2021. This Special Notice provides advance notice of the forthcoming solicitation and anticipated requirement.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

www.soltekpacific.com 2424 Congress Street San Diego CA 92110 P 619.296.6247 | F 619.296.7109 Contractor License #886641 EOE

Ltr 1099-23 February 26, 2021

FEAD Camp Pendleton Building 22101, MCB, Camp Pendleton Camp Pendleton, California 92055-5229 Attention: LT JG Acosta Construction Manager

Reference: P-9906 Area 21 Ambulatory Care Center Replacement

Contract N62473-I8-D-5885, Task Order N62473-20-F-5350

Subject: Revised CPM Baseline Schedule

Dear LT JG Acosta, Attached for your review is our revised cost loaded Construction Baseline Schedule with a data date of 9-30-20 and a run date of 2-25-21. In this schedule we have incorporated the Government’s following review comments

Dated January 22, 2021 & February 17, 2120

As well as the mutually agreed up item during our meetings of

February 04, 2021 & February 23, 2021

To assist with the Government’s review of our schedule, we have provided the following:

32 Page Time Scale Logic Diagram ( 1.10.4.A ) 32 Page Previous Month Comparison ( 1.10.4.B ) 01 XER File ( 1.10.4.C ) 08 Page Schedule Leveling Log Report ( 1.10.4.D ) 02 Page Baseline Schedule Narrative ( 1.10.4.E ) 33 Page Complete Schedule with Cost Plot ( 1.10.4.F ) 01 Page Schedule Variance Control (Cash Curve ) Report ( 1.10.4.G )

03 Page Longest Path Plot without WBS ( 1.10.4.H ) 04 Page Baseline Check List ( 1.10.4.I ) 02 Page Summary of Screen Shots ( 1.10.4.J )

We look forward to meeting with you to discuss and come to a mutual understanding of any of the remaining Gov’t review comments that need to be incorporated into our revised Baseline Schedule.

Should you have any questions, comments or concerns about the information provided above or attached, I can be reached via my e-mail ( dcarlin@soltekpacific.com ) or my cell phone at 619-987-1925 and you can also reach out to Oscar Lucio ( olucio@soltekpacific.com ) or Oscar’s cell phone at 619-807-8244.

Sincerely, . cc. Michelle Barlow, Dave Carlin Daniel Ramos, Jim Vieira

Don Rote Job Site File Oscar Lucio Project Manager mailto:dcarlin@soltekpacific.com mailto:mrogan@soltekpacific.com

Activity ID Activity Name Original Duration

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post CommentsP-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments542 542 30-Sep-20 27-Oct-22 1

Project MilestonesProject Milestones 542 542 30-Sep-20 27-Oct-22 1

Management MilestonesManagement Milestones 542 542 30-Sep-20 27-Oct-22 1

MS-110 Notice to Proceed 0 0 0% 30-Sep-20 14 OWN

MS-100 Contract Award 0 0 0% 30-Sep-20* 0 OWN

MS-190 FF&E Installation Complete 0 0 0% 02-Mar-22 66 GC

MS-130 Phase 1 Substantial Completion 0 0 0% 04-Apr-22 10 GC

MS-170 Commissioning Complete 0 0 0% 12-Apr-22 37 GC

MS-180 HVAC Testing Complete 0 0 0% 11-May-22 16 GC

MS-200 Customer Move Complete 0 0 0% 27-May-22 4 GC

MS-150 Phase 2 Substantial Completion 0 0 0% 15-Sep-22 29 GC

MS-160 Phase 3 Substantial Completion 0 0 0% 27-Sep-22 21 GC

MS-120 Projected Completion 0 0 0% 27-Oct-22 1 OWN

MS-140 Contract Completion Date (CCD 10-30-22) 0 0 0% 27-Oct-22* 2 OWN

PermitsPermits 436 436 24-Dec-20 19-Sep-22 27

PER-1000 Permit - SWPPP Notice of Intent 10 10 0% 24-Dec-20 08-Jan-21 29 GC

PER-1020 Permit - APCD Notice 10 10 0% 05-Apr-22 18-Apr-22 34 GC

PER-1010 Permit - SWPPP Notice of Termination 10 10 0% 06-Sep-22 19-Sep-22 27 GC

Pre-Construction PhasePre-Construction Phase 232 232 30-Sep-20 19-Aug-21 248

Submittals, Review and Procurement (General)Submittals, Review and Procurement (General) 119 119 30-Sep-20 15-Mar-21 305

PAS-530 Prepare and Submit Commissioning Firm 5 5 0% 30-Sep-20 06-Oct-20 389 GC

PAS-540 Prepare and Submit T&B Firm 25 25 0% 30-Sep-20 03-Nov-20 209 GC

PAS-550 Prepare and Submit - Site Utility Repair Plan 25 25 0% 30-Sep-20 03-Nov-20 51 GC

PAS-100 Prepare and Submit Bond and Insurance 25 25 0% 30-Sep-20 03-Nov-20 24 GC

PAS-110 Prepare and Submit Accident Prevention Plan 20 20 0% 30-Sep-20 27-Oct-20 56 GC

PAS-120 Prepare and Submit CQC Plan 59 59 0% 30-Sep-20 22-Dec-20 8 GC

PAS-130 Prepare and Submit Environmental Protection Plan 15 15 0% 30-Sep-20 20-Oct-20 52 GC

PAS-140 Prepare and Submit Waste Management Plan 15 15 0% 30-Sep-20 20-Oct-20 34 GC

PAS-150 Prepare and Submit Baseline Construction Schedule 65 65 0% 30-Sep-20 31-Dec-20 2 GC

PAS-160 Prepare and Submit SWPP Plan 50 50 0% 30-Sep-20 09-Dec-20 17 GC

PAS-170 Prepare and Submit Construction Site Plan 15 15 0% 30-Sep-20 20-Oct-20 34 GC

PAS-180 Prepare and Submit Temp Power Plan 25 25 0% 30-Sep-20 03-Nov-20 16 GC

PAS-270 Prepare and Submit Utility Coordination \ Location Report 53 53 0% 30-Sep-20 14-Dec-20 14 GC

PAS-560 Review/Approve Commissioning Firm 21 21 0% 06-Oct-20 27-Oct-20 566 OWN

PAS-210 Review/Approve Environmental Protection Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN

PAS-220 Review/Approve Waste Management Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN

PAS-250 Review/Approve Construction Site Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN

PAS-190 Review/Approve Accident Prevention Plan 5 5 0% 28-Oct-20 03-Nov-20 56 OWN

PAS-260 Review/Approve Temp Power Plan 21 21 0% 03-Nov-20 24-Nov-20 23 OWN

PAS-570 Review/Approve T&B Firm 21 21 0% 03-Nov-20 24-Nov-20 463 OWN

PAS-105 Review/Approve Bonds 6 6 0% 04-Nov-20 11-Nov-20 24 OWN

PAS-580 Prepare and SubmitCX Design Review Report per Section 01 91 00.15 5 5 0% 04-Nov-20 10-Nov-20 224 GC

PAS-590 Review/Approve - Site Utility Repair Plan 5 5 0% 04-Nov-20 10-Nov-20 51 OWN

PAS-108 Review/Approve Insurance 7 7 0% 04-Nov-20 12-Nov-20 24 OWN

PAS-240 Review/Approve SWPP Plan 21 21 0% 09-Dec-20 30-Dec-20 27 OWN

PAS-280 Review/Approve Utility Coordination \ Location Report 21 21 0% 14-Dec-20 04-Jan-21 22 OWN

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Notice to Proceed, 30-Sep-20

Contract Award, 30-Sep-20*

FF&E Installation Complete, Phase 1 Substantial Completion, Commissioning Complete, HVAC Testing Complete, Customer Move Complete, Phase 2 Substantial Completion, Phase 3 Substantial Completion, Permit - SWPPP Notice of Intent

Permit - APCD Notice

Permit - SWPPP Notice of Termination

Prepare and Submit Commissioning Firm

Prepare and Submit T&B Firm

Prepare and Submit - Site Utility Repair Plan

Prepare and Submit Bond and Insurance

Prepare and Submit Accident Prevention Plan

Prepare and Submit CQC Plan

Prepare and Submit Environmental Protection Plan

Prepare and Submit Waste Management Plan

Prepare and Submit Baseline Construction Schedule

Prepare and Submit SWPP Plan

Prepare and Submit Construction Site Plan

Prepare and Submit Temp Power Plan

Prepare and Submit Utility Coordination \ Location Report

Review/Approve Commissioning Firm

Review/Approve Environmental Protection Plan

Review/Approve Waste Management Plan

Review/Approve Construction Site Plan

Review/Approve Accident Prevention Plan

Review/Approve Temp Power Plan

Review/Approve T&B Firm

Review/Approve Bonds

Prepare and SubmitCX Design Review Report per Section 01 91 00.15

Review/Approve - Site Utility Repair Plan

Review/Approve Insurance

Review/Approve SWPP Plan

Review/Approve Utility Coordination \ Location Report

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Print Date: 25-Feb-21 08:54

Actual Level of Effort Actual Work Remaining Work C... Page 1 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

PAS-200 Review/Approve CQC Plan 21 21 0% 22-Dec-20 12-Jan-21 14 OWN

PAS-230 Review/Approve Baseline Construction Schedule 21 21 0% 31-Dec-20 21-Jan-21 5 OWN

PAS-600 Prepare and Submit Utility Service Connection Application Water / Telecom 1 1 0% 15-Mar-21 15-Mar-21 99 ELE

Submittals, Review and ProcurementSubmittals, Review and Procurement 225 225 30-Sep-20 19-Aug-21 238

Division 1Division 1 35 35 30-Sep-20 17-Nov-20 379

019100 Commssioning019100 Commssioning 35 35 30-Sep-20 17-Nov-20 379

BC-1060 Submit Utility Service Connection Application 15 15 0% 30-Sep-20 20-Oct-20 379 PWFEAD

BC-1085 Submittal Review/Approve - Utility Service Connection Application 20 20 0% 21-Oct-20 17-Nov-20 379 OWN

Division 2 - Existing ConditionsDivision 2 - Existing Conditions 25 25 24-Dec-20 01-Feb-21 348

028100 Transportation and Disposal of Hazardous Materials028100 Transportation and Disposal of Hazardous Materials 25 25 24-Dec-20 01-Feb-21 348

SP-1510 Submittal Prep - 028100 Transportation and Disposal of Hazardous Materials 5 5 0% 24-Dec-20 31-Dec-20 348 GC

SR-2230 Submittal Review/Approve - 028100 Transportation and Disposal of Hazardous Materials20 20 0% 04-Jan-21 01-Feb-21 348 OWN

028200 Asbestos Remediation028200 Asbestos Remediation 20 20 24-Dec-20 25-Jan-21 353

SP-1520 Submittal Prep - 028200 Asbestos Remediation 5 5 0% 24-Dec-20 31-Dec-20 353 GC

SR-2240 Submittal Review/Approve - 028200 Asbestos Remediation 15 15 0% 04-Jan-21 25-Jan-21 353 OWN

028300 Lead Remediation028300 Lead Remediation 20 20 24-Dec-20 25-Jan-21 353

SP-1530 Submittal Prep - 028300 Lead Remediation 5 5 0% 24-Dec-20 31-Dec-20 353 GC

SR-2250 Submittal Review/Approve - 028300 Lead Remediation 15 15 0% 04-Jan-21 25-Jan-21 353 OWN

Division 3 - ConcreteDivision 3 - Concrete 45 45 24-Dec-20 02-Mar-21 195

033000 CIP Rebar033000 CIP Rebar 45 45 24-Dec-20 02-Mar-21 195

SP-3420 Submittal Prep - 033000 CIP Rebar 10 10 0% 24-Dec-20 08-Jan-21 195 REIN

SR-1210 Submittal Review/Approve - 033000 CIP Rebar 15 15 0% 11-Jan-21 01-Feb-21 195 OWN

PR-1090 Procure/Deliver - 033000 CIP Rebar 20 20 0% 02-Feb-21 02-Mar-21 195 REIN

Division 4 - MasonryDivision 4 - Masonry 65 65 24-Dec-20 30-Mar-21 183

042000 Unit Masonry042000 Unit Masonry 65 65 24-Dec-20 30-Mar-21 183

SP-1550 Submittal Prep - 042000 Unit Masonry 5 5 0% 24-Dec-20 31-Dec-20 183 MAS

SR-2270 Submittal Review/Approve - 042000 Unit Masonry 15 15 0% 04-Jan-21 25-Jan-21 183 OWN

PR-3150 Procure/Deliver - 042000 Unit Masonry 45 45 0% 26-Jan-21 30-Mar-21 183 MAS

Division 5 - MetalsDivision 5 - Metals 105 105 24-Dec-20 25-May-21 55

051200 Structural Steel051200 Structural Steel 105 105 24-Dec-20 25-May-21 38

SP-1570 Submittal Prep - 051200 Structural Steel 30 30 0% 24-Dec-20 08-Feb-21 38 GC

SR-2290 Submittal Review/Approve - 051200 Structural Steel 15 15 0% 09-Feb-21 02-Mar-21 38 OWN

PR-3170 Procure/Deliver - 051200 Structural Steel 60 60 0% 03-Mar-21 25-May-21 38 GC

052100 Steel Joist Framing052100 Steel Joist Framing 105 105 24-Dec-20 25-May-21 33

SP-1580 Submittal Prep - 052100 Steel Joist Framing 30 30 0% 24-Dec-20 08-Feb-21 33 GC

SR-2300 Submittal Review/Approve - 052100 Steel Joist Framing 15 15 0% 09-Feb-21 02-Mar-21 33 OWN

PR-3180 Procure/Deliver - 052100 Steel Joist Framing 60 60 0% 03-Mar-21 25-May-21 33 GC

053000 Steel Decks053000 Steel Decks 85 85 24-Dec-20 27-Apr-21 75

SP-1590 Submittal Prep - 053000 Steel Decks 10 10 0% 24-Dec-20 08-Jan-21 75 DECK

SR-2310 Submittal Review/Approve - 053000 Steel Decks 15 15 0% 11-Jan-21 01-Feb-21 75 OWN

PR-3190 Procure/Deliver - 053000 Steel Decks 60 60 0% 02-Feb-21 27-Apr-21 75 DECK

054000 Cold-Formed Metal Framing054000 Cold-Formed Metal Framing 45 45 24-Dec-20 02-Mar-21 93

SP-1600 Submittal Prep - 054000 Cold-Formed Metal Framing 15 15 0% 24-Dec-20 15-Jan-21 93 GC

SR-2320 Submittal Review/Approve - 054000 Cold-Formed Metal Framing 15 15 0% 19-Jan-21 08-Feb-21 93 OWN

PR-3200 Procure/Deliver - 054000 Cold-Formed Metal Framing 15 15 0% 09-Feb-21 02-Mar-21 93 GC

055013 Misc Metal Fabrication055013 Misc Metal Fabrication 45 45 24-Dec-20 02-Mar-21 86

SP-1620 Submittal Prep - 055013 Misc Metal Fabrication 30 30 0% 24-Dec-20 08-Feb-21 86 GC

SR-2340 Submittal Review/Approve - 055013 Misc Metal Fabrication 15 15 0% 09-Feb-21 02-Mar-21 86 OWN

Division 6 - Wood Plastics and CompositesDivision 6 - Wood Plastics and Composites 30 30 24-Dec-20 08-Feb-21 294

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Review/Approve CQC Plan

Review/Approve Baseline Construction Schedule

Prepare and Submit Utility Service Connection Application Water / Telecom

Submit Utility Service Connection Application

Submittal Review/Approve - Utility Service Connection Application

Submittal Prep - 028100 Transportation and Disposal of Hazardous Materials

Submittal Review/Approve - 028100 Transportation and Disposal of Hazardous Materials

Submittal Prep - 028200 Asbestos Remediation

Submittal Review/Approve - 028200 Asbestos Remediation

Submittal Prep - 028300 Lead Remediation

Submittal Review/Approve - 028300 Lead Remediation

Submittal Prep - 033000 CIP Rebar

Submittal Review/Approve - 033000 CIP Rebar

Procure/Deliver - 033000 CIP Rebar

Submittal Prep - 042000 Unit Masonry

Submittal Review/Approve - 042000 Unit Masonry

Procure/Deliver - 042000 Unit Masonry

Submittal Prep - 051200 Structural Steel

Submittal Review/Approve - 051200 Structural Steel

Procure/Deliver - 051200 Structural Steel

Submittal Prep - 052100 Steel Joist Framing

Submittal Review/Approve - 052100 Steel Joist Framing

Procure/Deliver - 052100 Steel Joist Framing

Submittal Prep - 053000 Steel Decks

Submittal Review/Approve - 053000 Steel Decks

Procure/Deliver - 053000 Steel Decks

Submittal Prep - 054000 Cold-Formed Metal Framing

Submittal Review/Approve - 054000 Cold-Formed Metal Framing

Procure/Deliver - 054000 Cold-Formed Metal Framing

Submittal Prep - 055013 Misc Metal Fabrication

Submittal Review/Approve - 055013 Misc Metal Fabrication

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 2 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

061000 Rough Carpentry061000 Rough Carpentry 15 15 24-Dec-20 15-Jan-21 176

SR-2350 Submittal Review/Approve - 061000 Rough Carpentry 15 15 0% 24-Dec-20 15-Jan-21 176 OWN

062000 Finish Carpentry062000 Finish Carpentry 30 30 24-Dec-20 08-Feb-21 292

SP-1640 Submittal Prep - 062000 Finish Carpentry 15 15 0% 24-Dec-20 15-Jan-21 292 GC

SR-2360 Submittal Review/Approve - 062000 Finish Carpentry 15 15 0% 19-Jan-21 08-Feb-21 292 OWN

066116 Solid Surfacing Fabrications066116 Solid Surfacing Fabrications 30 30 24-Dec-20 08-Feb-21 277

SP-1650 Submittal Prep - 066116 Solid Surfacing Fabrications 15 15 0% 24-Dec-20 15-Jan-21 277 CW

SR-2370 Submittal Review/Approve - 066116 Solid Surfacing Fabrications 15 15 0% 19-Jan-21 08-Feb-21 277 OWN

066413 Translucent Resin Panel Restrictions066413 Translucent Resin Panel Restrictions 30 30 24-Dec-20 08-Feb-21 294

SP-1660 Submittal Prep - 066413 Translucent Resin Panel Restrictions 15 15 0% 24-Dec-20 15-Jan-21 294 CW

SR-2380 Submittal Review/Approve - 066413 Translucent Resin Panel Restrictions 15 15 0% 19-Jan-21 08-Feb-21 294 OWN

Division 7 - Thermal and Moisture ProtectionDivision 7 - Thermal and Moisture Protection 135 135 24-Dec-20 08-Jul-21 105

070523 Pressure Testing an Air Barrier System for Air Tightness070523 Pressure Testing an Air Barrier System for Air Tightness 25 25 24-Dec-20 01-Feb-21 159

SP-1670 Submittal Prep - 070523 Pressure Testing an Air Barrier System for Air Tightness10 10 0% 24-Dec-20 08-Jan-21 159 GC

SR-2390 Submittal Review/Approve - 070523 Pressure Testing an Air Barrier System for Air Tightness15 15 0% 11-Jan-21 01-Feb-21 159 OWN

072113 Board and Block Insulation072113 Board and Block Insulation 40 40 24-Dec-20 23-Feb-21 150

SP-1680 Submittal Prep - 072113 Board and Block Insulation 5 5 0% 24-Dec-20 31-Dec-20 150 INSUL

SR-2400 Submittal Review/Approve - 072113 Board and Block Insulation 15 15 0% 04-Jan-21 25-Jan-21 150 OWN

PR-3280 Procure/Deliver - 072113 Board and Block Insulation 20 20 0% 26-Jan-21 23-Feb-21 150 INSUL

072116 Mineral Fiber Blanket Insulation072116 Mineral Fiber Blanket Insulation 65 65 24-Dec-20 30-Mar-21 126

SP-1690 Submittal Prep - 072116 Mineral Fiber Blanket Insulation 5 5 0% 24-Dec-20 31-Dec-20 126 INSUL

SR-2410 Submittal Review/Approve - 072116 Mineral Fiber Blanket Insulation 15 15 0% 04-Jan-21 25-Jan-21 126 OWN

PR-3290 Procure/Deliver - 072116 Mineral Fiber Blanket Insulation 45 45 0% 26-Jan-21 30-Mar-21 126 INSUL

072129 Sprayed Acoustic Insulation072129 Sprayed Acoustic Insulation 34 34 24-Dec-20 12-Feb-21 157

SP-1700 Submittal Prep - 072129 Sprayed Acoustic Insulation 5 5 0% 24-Dec-20 31-Dec-20 157 INSUL

SR-2420 Submittal Review/Approve - 072129 Sprayed Acoustic Insulation 15 15 0% 04-Jan-21 25-Jan-21 157 OWN

PR-3300 Procure/Deliver - 072129 Sprayed Acoustic Insulation 14 14 0% 26-Jan-21 12-Feb-21 157 INSUL

072719.01 Self-Adhering Air Barriers072719.01 Self-Adhering Air Barriers 40 40 17-Mar-21 11-May-21 99

SP-1710 Submittal Prep - 072719.01 Self-Adhering Barriers 10 10 0% 17-Mar-21 30-Mar-21 99 GC

SR-2430 Submittal Review/Approve - 072719.01 Self-Adhering Barriers 15 15 0% 31-Mar-21 20-Apr-21 99 OWN

PR-3310 Procure/Deliver - 072719.01 Self-Adhering Barriers 15 15 0% 21-Apr-21 11-May-21 99 GC

074113 Metal Roof Panels074113 Metal Roof Panels 80 80 24-Dec-20 20-Apr-21 160

SP-1720 Submittal Prep - 074113 Metal Roof Panels 20 20 0% 24-Dec-20 25-Jan-21 160 GC

SR-2440 Submittal Review/Approve - 074113 Metal Roof Panels 15 15 0% 26-Jan-21 16-Feb-21 160 OWN

PR-3320 Procure/Deliver - 074113 Metal Roof Panels 45 45 0% 17-Feb-21 20-Apr-21 160 GC

074213 Metal Wall Panels074213 Metal Wall Panels 80 80 24-Dec-20 20-Apr-21 139

SP-1730 Submittal Prep - 074213 Metal Wall Panels 20 20 0% 24-Dec-20 25-Jan-21 139 GC

SR-2450 Submittal Review/Approve - 074213 Metal Wall Panels 15 15 0% 26-Jan-21 16-Feb-21 139 OWN

PR-3330 Procure/Deliver - 074213 Metal Wall Panels 45 45 0% 17-Feb-21 20-Apr-21 139 GC

076000 Flashing and Sheet Metals076000 Flashing and Sheet Metals 80 80 17-Mar-21 08-Jul-21 105

SP-1740 Submittal Prep - 076000 Flashing and Sheet Metals 20 20 0% 17-Mar-21 13-Apr-21 105 GC

SR-2460 Submittal Review/Approve - 076000 Flashing and Sheet Metals 15 15 0% 14-Apr-21 04-May-21 105 OWN

PR-3340 Procure/Deliver - 076000 Flashing and Sheet Metals 45 45 0% 05-May-21 08-Jul-21 105 GC

078400 Firestopping078400 Firestopping 20 20 24-Dec-20 25-Jan-21 174

SP-1750 Submittal Prep - 078400 Firestopping 5 5 0% 24-Dec-20 31-Dec-20 174 GC

SR-2470 Submittal Review/Approve - 078400 Firestopping 15 15 0% 04-Jan-21 25-Jan-21 174 OWN

079200 Joint Sealants079200 Joint Sealants 25 25 24-Dec-20 01-Feb-21 168

SP-1760 Submittal Prep - 079200 Joint Sealants 10 10 0% 24-Dec-20 08-Jan-21 168 GC

SR-2480 Submittal Review/Approve - 079200 Joint Sealants 15 15 0% 11-Jan-21 01-Feb-21 168 OWN

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Submittal Review/Approve - 061000 Rough Carpentry

Submittal Prep - 062000 Finish Carpentry

Submittal Review/Approve - 062000 Finish Carpentry

Submittal Prep - 066116 Solid Surfacing Fabrications

Submittal Review/Approve - 066116 Solid Surfacing Fabrications

Submittal Prep - 066413 Translucent Resin Panel Restrictions

Submittal Review/Approve - 066413 Translucent Resin Panel Restrictions

Submittal Prep - 070523 Pressure Testing an Air Barrier System for Air Tightness

Submittal Review/Approve - 070523 Pressure Testing an Air Barrier System for Air Tightness

Submittal Prep - 072113 Board and Block Insulation

Submittal Review/Approve - 072113 Board and Block Insulation

Procure/Deliver - 072113 Board and Block Insulation

Submittal Prep - 072116 Mineral Fiber Blanket Insulation

Submittal Review/Approve - 072116 Mineral Fiber Blanket Insulation

Procure/Deliver - 072116 Mineral Fiber Blanket Insulation

Submittal Prep - 072129 Sprayed Acoustic Insulation

Submittal Review/Approve - 072129 Sprayed Acoustic Insulation

Procure/Deliver - 072129 Sprayed Acoustic Insulation

Submittal Prep - 072719.01 Self-Adhering Barriers

Submittal Review/Approve - 072719.01 Self-Adhering Barriers

Procure/Deliver - 072719.01 Self-Adhering Barriers

Submittal Prep - 074113 Metal Roof Panels

Submittal Review/Approve - 074113 Metal Roof Panels

Procure/Deliver - 074113 Metal Roof Panels

Submittal Prep - 074213 Metal Wall Panels

Submittal Review/Approve - 074213 Metal Wall Panels

Procure/Deliver - 074213 Metal Wall Panels

Submittal Prep - 076000 Flashing and Sheet Metals

Submittal Review/Approve - 076000 Flashing and Sheet Metals

Procure/Deliver - 076000 Flashing and Sheet Metals

Submittal Prep - 078400 Firestopping

Submittal Review/Approve - 078400 Firestopping

Submittal Prep - 079200 Joint Sealants

Submittal Review/Approve - 079200 Joint Sealants

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 3 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

Division 8 - OpeningsDivision 8 - Openings 140 140 24-Dec-20 15-Jul-21 206

081113 Steel Doors and Frames081113 Steel Doors and Frames 60 60 24-Dec-20 23-Mar-21 286

SP-1770 Submittal Prep - 081113 Steel Doors and Frames 5 5 0% 24-Dec-20 31-Dec-20 286 GC

SR-2490 Submittal Review/Approve - 081113 Steel Doors and Frames 15 15 0% 04-Jan-21 25-Jan-21 286 OWN

PR-3370 Procure/Deliver - 081113 Steel Doors and Frames 40 40 0% 26-Jan-21 23-Mar-21 286 DO

081116 Aluminum Doors and Frames081116 Aluminum Doors and Frames 60 60 24-Dec-20 23-Mar-21 286

SP-1780 Submittal Prep - 081116 Aluminum Doors and Frames 5 5 0% 24-Dec-20 31-Dec-20 286 GC

SR-2500 Submittal Review/Approve - 081116 Aluminum Doors and Frames 15 15 0% 04-Jan-21 25-Jan-21 286 OWN

PR-3380 Procure/Deliver - 081116 Aluminum Doors and Frames 40 40 0% 26-Jan-21 23-Mar-21 286 GC

081400 Wood Doors081400 Wood Doors 60 60 24-Dec-20 23-Mar-21 259

SP-1790 Submittal Prep - 081400 Wood Doors 5 5 0% 24-Dec-20 31-Dec-20 259 GC

SR-2510 Submittal Review/Approve - 081400 Wood Doors 15 15 0% 04-Jan-21 25-Jan-21 259 OWN

PR-3390 Procure/Deliver - 081400 Wood Doors 40 40 0% 26-Jan-21 23-Mar-21 259 DO

083100 Access Doors and Frames083100 Access Doors and Frames 30 30 24-Dec-20 08-Feb-21 289

SP-1800 Submittal Prep - 083100 Access Doors and Frames 15 15 0% 24-Dec-20 15-Jan-21 289 GC

SR-2520 Submittal Review/Approve - 083100 Access Doors and Frames 15 15 0% 19-Jan-21 08-Feb-21 289 OWN

083313 Coiling Counter Doors083313 Coiling Counter Doors 60 60 24-Dec-20 23-Mar-21 250

SP-1810 Submittal Prep - 083313 Coiling Counter Doors 5 5 0% 24-Dec-20 31-Dec-20 250 GC

SR-2530 Submittal Review/Approve - 083313 Coiling Counter Doors 15 15 0% 04-Jan-21 25-Jan-21 250 OWN

PR-3410 Procure/Deliver - 083313 Coiling Counter Doors 40 40 0% 26-Jan-21 23-Mar-21 250 GC

084400 Curtain Wall and Glaze Assemblies084400 Curtain Wall and Glaze Assemblies 115 115 24-Dec-20 09-Jun-21 182

SP-1820 Submittal Prep - 084400 Curtain Wall and Glaze Assemblies 30 30 0% 24-Dec-20 08-Feb-21 182 GC

SR-2540 Submittal Review/Approve - 084400 Curtain Wall and Glaze Assemblies 15 15 0% 09-Feb-21 02-Mar-21 182 OWN

PR-3420 Procure/Deliver - 084400 Curtain Wall and Glaze Assemblies 70 70 0% 03-Mar-21 09-Jun-21 182 GC

085680 Aluminum Sliding Service Windows085680 Aluminum Sliding Service Windows 50 50 24-Dec-20 09-Mar-21 256

SP-1830 Submittal Prep - 085680 Aluminum Sliding Service Windows 5 5 0% 24-Dec-20 31-Dec-20 256 GC

SR-2550 Submittal Review/Approve - 085680 Aluminum Sliding Service Windows 15 15 0% 04-Jan-21 25-Jan-21 256 OWN

PR-3430 Procure/Deliver - 085680 Aluminum Sliding Service Windows 30 30 0% 26-Jan-21 09-Mar-21 256 GC

086045 Skylights086045 Skylights 80 80 24-Dec-20 20-Apr-21 101

SP-1840 Submittal Prep - 086045 Skylights 20 20 0% 24-Dec-20 25-Jan-21 101 GC

SR-2560 Submittal Review/Approve - 086045 Skylights 15 15 0% 26-Jan-21 16-Feb-21 101 OWN

PR-3440 Procure/Deliver - 086045 Skylights 45 45 0% 17-Feb-21 20-Apr-21 101 GC

087100 Door Hardware087100 Door Hardware 140 140 24-Dec-20 15-Jul-21 181

SP-1850 Submittal Prep - 087100 Door Hardware 5 5 0% 24-Dec-20 31-Dec-20 181 GC

SR-2570 Submittal Review/Approve - 087100 Door Hardware 15 15 0% 04-Jan-21 25-Jan-21 181 OWN

PR-3450 Procure/Deliver - 087100 Door Hardware 120 120 0% 26-Jan-21 15-Jul-21 181 DO

088100 Glazing088100 Glazing 115 115 24-Dec-20 09-Jun-21 185

SP-1860 Submittal Prep - 088100 Glazing 30 30 0% 24-Dec-20 08-Feb-21 185 GC

SR-2580 Submittal Review/Approve - 088100 Glazing 15 15 0% 09-Feb-21 02-Mar-21 185 OWN

PR-3460 Procure/Deliver - 088100 Glazing 70 70 0% 03-Mar-21 09-Jun-21 185 GC

089100 Metal Wall Louvers089100 Metal Wall Louvers 80 80 24-Dec-20 20-Apr-21 219

SP-1870 Submittal Prep - 089100 Metal Wall Louvers 20 20 0% 24-Dec-20 25-Jan-21 219 MECH

SR-2590 Submittal Review/Approve - 089100 Metal Wall Louvers 15 15 0% 26-Jan-21 16-Feb-21 219 OWN

PR-3470 Procure/Deliver - 089100 Metal Wall Louvers 45 45 0% 17-Feb-21 20-Apr-21 219 MECH

Division 9 - FinishesDivision 9 - Finishes 80 80 24-Dec-20 20-Apr-21 235

092200 Supports of Gypsum Boards092200 Supports of Gypsum Boards 15 15 24-Dec-20 15-Jan-21 171

SR-2600 Submittal Review/Approve - 092200 Supports of Gypsum Boards 15 15 0% 24-Dec-20 15-Jan-21 171 OWN

092900 Gypsum Board092900 Gypsum Board 40 40 24-Dec-20 23-Feb-21 146

SP-1890 Submittal Prep - 092900 Gypsum Board 10 10 0% 24-Dec-20 08-Jan-21 146 GC

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Submittal Prep - 081113 Steel Doors and Frames

Submittal Review/Approve - 081113 Steel Doors and Frames

Procure/Deliver - 081113 Steel Doors and Frames

Submittal Prep - 081116 Aluminum Doors and Frames

Submittal Review/Approve - 081116 Aluminum Doors and Frames

Procure/Deliver - 081116 Aluminum Doors and Frames

Submittal Prep - 081400 Wood Doors

Submittal Review/Approve - 081400 Wood Doors

Procure/Deliver - 081400 Wood Doors

Submittal Prep - 083100 Access Doors and Frames

Submittal Review/Approve - 083100 Access Doors and Frames

Submittal Prep - 083313 Coiling Counter Doors

Submittal Review/Approve - 083313 Coiling Counter Doors

Procure/Deliver - 083313 Coiling Counter Doors

Submittal Prep - 084400 Curtain Wall and Glaze Assemblies

Submittal Review/Approve - 084400 Curtain Wall and Glaze Assemblies

Procure/Deliver - 084400 Curtain Wall and Glaze Assemblies

Submittal Prep - 085680 Aluminum Sliding Service Windows

Submittal Review/Approve - 085680 Aluminum Sliding Service Windows

Procure/Deliver - 085680 Aluminum Sliding Service Windows

Submittal Prep - 086045 Skylights

Submittal Review/Approve - 086045 Skylights

Procure/Deliver - 086045 Skylights

Submittal Prep - 087100 Door Hardware

Submittal Review/Approve - 087100 Door Hardware

Procure/Deliver - 087100 Door Hardware

Submittal Prep - 088100 Glazing

Submittal Review/Approve - 088100 Glazing

Procure/Deliver - 088100 Glazing

Submittal Prep - 089100 Metal Wall Louvers

Submittal Review/Approve - 089100 Metal Wall Louvers

Procure/Deliver - 089100 Metal Wall Louvers

Submittal Review/Approve - 092200 Supports of Gypsum Boards

Submittal Prep - 092900 Gypsum Board

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 4 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

SR-2610 Submittal Review/Approve - 092900 Gypsum Board 15 15 0% 11-Jan-21 01-Feb-21 146 OWN

PR-3490 Procure/Deliver - 092900 Gypsum Board 15 15 0% 02-Feb-21 23-Feb-21 146 GC

093010 Tiling093010 Tiling 50 50 24-Dec-20 09-Mar-21 261

SP-1900 Submittal Prep - 093010 Tiling 5 5 0% 24-Dec-20 31-Dec-20 261 FL

SR-2620 Submittal Review/Approve - 093010 Tiling 15 15 0% 04-Jan-21 25-Jan-21 261 OWN

PR-3500 Procure/Deliver - 093010 Tiling 30 30 0% 26-Jan-21 09-Mar-21 261 FL

095100 Acoustical Ceilings095100 Acoustical Ceilings 45 45 24-Dec-20 02-Mar-21 223

SP-1910 Submittal Prep - 095100 Acoustical Ceilings 15 15 0% 24-Dec-20 15-Jan-21 223 GC

SR-2630 Submittal Review/Approve - 095100 Acoustical Ceilings 15 15 0% 19-Jan-21 08-Feb-21 223 OWN

PR-3510 Procure/Deliver - 095100 Acoustical Ceilings 15 15 0% 09-Feb-21 02-Mar-21 223 GC

095423 Linear Metal Ceilings095423 Linear Metal Ceilings 45 45 24-Dec-20 02-Mar-21 270

SP-1920 Submittal Prep - 095423 Linear Metal Ceilings 15 15 0% 24-Dec-20 15-Jan-21 270 GC

SR-2640 Submittal Review/Approve - 095423 Linear Metal Ceilings 15 15 0% 19-Jan-21 08-Feb-21 270 OWN

PR-3520 Procure/Deliver - 095423 Linear Metal Ceilings 15 15 0% 09-Feb-21 02-Mar-21 270 GC

096500 Resilient Flooring096500 Resilient Flooring 50 50 24-Dec-20 09-Mar-21 226

SP-1930 Submittal Prep - 096500 Resilient Flooring 5 5 0% 24-Dec-20 31-Dec-20 226 FL

SR-2650 Submittal Review/Approve - 096500 Resilient Flooring 15 15 0% 04-Jan-21 25-Jan-21 226 OWN

PR-3530 Procure/Deliver - 096500 Resilient Flooring 30 30 0% 26-Jan-21 09-Mar-21 226 FL

096800 Carpeting096800 Carpeting 80 80 24-Dec-20 20-Apr-21 219

SP-1940 Submittal Prep - 096800 Carpeting 5 5 0% 24-Dec-20 31-Dec-20 219 FL

SR-2660 Submittal Review/Approve - 096800 Carpeting 15 15 0% 04-Jan-21 25-Jan-21 219 OWN

PR-3540 Procure/Deliver - 096800 Carpeting 60 60 0% 26-Jan-21 20-Apr-21 219 FL

097710 Modular Panel Systems097710 Modular Panel Systems 20 20 24-Dec-20 25-Jan-21 276

SP-1950 Submittal Prep - 097710 Modular Panel Systems 5 5 0% 24-Dec-20 31-Dec-20 276 GC

SR-2670 Submittal Review/Approve - 097710 Modular Panel Systems 15 15 0% 04-Jan-21 25-Jan-21 276 OWN

099000 Paints and Coatings099000 Paints and Coatings 30 30 24-Dec-20 08-Feb-21 244

SP-1960 Submittal Prep - 099000 Paints and Coatings 5 5 0% 24-Dec-20 31-Dec-20 244 GC

SR-2680 Submittal Review/Approve - 099000 Paints and Coatings 15 15 0% 04-Jan-21 25-Jan-21 244 OWN

PR-3560 Procure/Deliver - 099000 Paints and Coatings 10 10 0% 26-Jan-21 08-Feb-21 244 GC

Division 10 - SpecialtiesDivision 10 - Specialties 75 75 24-Dec-20 13-Apr-21 273

101100 Visual Display Units101100 Visual Display Units 75 75 24-Dec-20 13-Apr-21 218

SP-1970 Submittal Prep - 101100 Visual Display Units 15 15 0% 24-Dec-20 15-Jan-21 218 SIGN

SR-2690 Submittal Review/Approve - 101100 Visual Display Units 15 15 0% 19-Jan-21 08-Feb-21 218 OWN

PR-3570 Procure/Deliver - 101100 Visual Display Units 45 45 0% 09-Feb-21 13-Apr-21 218 SIGN

101400.10 Exterior Signage101400.10 Exterior Signage 75 75 24-Dec-20 13-Apr-21 273

SP-1980 Submittal Prep - 101400.10 Exterior Signage 15 15 0% 24-Dec-20 15-Jan-21 273 SIGN

SR-2700 Submittal Review/Approve - 101400.10 Exterior Signage 15 15 0% 19-Jan-21 08-Feb-21 273 OWN

PR-3580 Procure/Deliver - 101400.10 Exterior Signage 45 45 0% 09-Feb-21 13-Apr-21 273 SIGN

101400.20 Interior Signage101400.20 Interior Signage 75 75 24-Dec-20 13-Apr-21 241

SP-1990 Submittal Prep - 101400.20 Interior Signage 15 15 0% 24-Dec-20 15-Jan-21 241 SIGN

SR-2710 Submittal Review/Approve - 101400.20 Interior Signage 15 15 0% 19-Jan-21 08-Feb-21 241 OWN

PR-3590 Procure/Deliver - 101400.20 Interior Signage 45 45 0% 09-Feb-21 13-Apr-21 241 SIGN

Division 11 - EquipmentDivision 11 - Equipment 95 95 24-Dec-20 11-May-21 224

114600 Food Dispensing Equipment114600 Food Dispensing Equipment 20 20 24-Dec-20 25-Jan-21 280

SP-2080 Submittal Prep - 114600 Food Dispensing Equipment 5 5 0% 24-Dec-20 31-Dec-20 280 GC

SR-2800 Submittal Review/Approve - 114600 Food Dispensing Equipment 15 15 0% 04-Jan-21 25-Jan-21 280 OWN

114700 Ice Machines114700 Ice Machines 65 65 24-Dec-20 30-Mar-21 235

SP-2090 Submittal Prep - 114700 Ice Machines 5 5 0% 24-Dec-20 31-Dec-20 235 GC

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Submittal Review/Approve - 092900 Gypsum Board

Procure/Deliver - 092900 Gypsum Board

Submittal Prep - 093010 Tiling

Submittal Review/Approve - 093010 Tiling

Procure/Deliver - 093010 Tiling

Submittal Prep - 095100 Acoustical Ceilings

Submittal Review/Approve - 095100 Acoustical Ceilings

Procure/Deliver - 095100 Acoustical Ceilings

Submittal Prep - 095423 Linear Metal Ceilings

Submittal Review/Approve - 095423 Linear Metal Ceilings

Procure/Deliver - 095423 Linear Metal Ceilings

Submittal Prep - 096500 Resilient Flooring

Submittal Review/Approve - 096500 Resilient Flooring

Procure/Deliver - 096500 Resilient Flooring

Submittal Prep - 096800 Carpeting

Submittal Review/Approve - 096800 Carpeting

Procure/Deliver - 096800 Carpeting

Submittal Prep - 097710 Modular Panel Systems

Submittal Review/Approve - 097710 Modular Panel Systems

Submittal Prep - 099000 Paints and Coatings

Submittal Review/Approve - 099000 Paints and Coatings

Procure/Deliver - 099000 Paints and Coatings

Submittal Prep - 101100 Visual Display Units

Submittal Review/Approve - 101100 Visual Display Units

Procure/Deliver - 101100 Visual Display Units

Submittal Prep - 101400.10 Exterior Signage

Submittal Review/Approve - 101400.10 Exterior Signage

Procure/Deliver - 101400.10 Exterior Signage

Submittal Prep - 101400.20 Interior Signage

Submittal Review/Approve - 101400.20 Interior Signage

Procure/Deliver - 101400.20 Interior Signage

Submittal Prep - 114600 Food Dispensing Equipment

Submittal Review/Approve - 114600 Food Dispensing Equipment

Submittal Prep - 114700 Ice Machines

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 5 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

SR-2810 Submittal Review/Approve - 114700 Ice Machines 15 15 0% 04-Jan-21 25-Jan-21 235 OWN

PR-3690 Procure/Deliver - 114700 Ice Machines 45 45 0% 26-Jan-21 30-Mar-21 235 GC

115300 Labratory Equipment and Fumehoods115300 Labratory Equipment and Fumehoods 95 95 24-Dec-20 11-May-21 224

SP-2100 Submittal Prep - 115300 Laboratory Equipment and Fumehoods 20 20 0% 24-Dec-20 25-Jan-21 224 GC

SR-2820 Submittal Review/Approve - 115300 Laboratory Equipment and Fumehoods 15 15 0% 26-Jan-21 16-Feb-21 224 OWN

PR-3700 Procure/Deliver - 115300 Laboratory Equipment and Fumehoods 60 60 0% 17-Feb-21 11-May-21 224 GC

117000 General Requirements for Medical and Dental Equipment117000 General Requirements for Medical and Dental Equipment 15 15 24-Dec-20 15-Jan-21 285

SR-2830 Submittal Review/Approve - 117000 General Requirements for Medical and Dental Equipment15 15 0% 24-Dec-20 15-Jan-21 285 OWN

117100 Warming Cabinets Sterilizers and Associated Equipment117100 Warming Cabinets Sterilizers and Associated Equipment 95 95 24-Dec-20 11-May-21 212

SP-2120 Submittal Prep - 117100 Warming Cabinets Sterilizers and Associated Equipment20 20 0% 24-Dec-20 25-Jan-21 212 GC

SR-2840 Submittal Review/Approve - 117100 Warming Cabinets Sterilizers and Associated Equipment15 15 0% 26-Jan-21 16-Feb-21 212 OWN

PR-3720 Procure/Deliver - 117100 Warming Cabinets Sterilizers and Associated Equipment60 60 0% 17-Feb-21 11-May-21 212 GC

117213 Medical Equipment Misc117213 Medical Equipment Misc 15 15 24-Dec-20 15-Jan-21 304

SR-2850 Submittal Review/Approve - 117213 Medical Equipment Misc 15 15 0% 24-Dec-20 15-Jan-21 304 OWN

117400 Dental Equipment117400 Dental Equipment 35 35 24-Dec-20 16-Feb-21 265

SP-2140 Submittal Prep - 117400 Dental Equipment 20 20 0% 24-Dec-20 25-Jan-21 265 GC

SR-2860 Submittal Review/Approve - 117400 Dental Equipment 15 15 0% 26-Jan-21 16-Feb-21 265 OWN

Division 12 - FurnishingsDivision 12 - Furnishings 110 110 24-Dec-20 02-Jun-21 197

123570 Healthcare Casework123570 Healthcare Casework 110 110 24-Dec-20 02-Jun-21 197

SP-2150 Submittal Prep - 123570 Healthcare Casework 25 25 0% 24-Dec-20 01-Feb-21 197 GC

SR-2870 Submittal Review/Approve - 123570 Healthcare Casework 15 15 0% 02-Feb-21 23-Feb-21 197 OWN

PR-3750 Procure/Deliver - 123570 Healthcare Casework 70 70 0% 24-Feb-21 02-Jun-21 197 GC

123600 Countertops123600 Countertops 40 40 24-Dec-20 23-Feb-21 267

SP-2160 Submittal Prep - 123600 Countertops 25 25 0% 24-Dec-20 01-Feb-21 267 GC

SR-2880 Submittal Review/Approve - 123600 Countertops 15 15 0% 02-Feb-21 23-Feb-21 267 OWN

Division 13 - Special ConstructionDivision 13 - Special Construction 70 70 24-Dec-20 06-Apr-21 169

132148 Prefrabricated Audiometric Rooms132148 Prefrabricated Audiometric Rooms 70 70 24-Dec-20 06-Apr-21 161

SP-2180 Submittal Prep - 132148 Prefabricated Audiometric Rooms 5 5 0% 24-Dec-20 31-Dec-20 161 GC

SR-2900 Submittal Review/Approve - 132148 Prefabricated Audiometric Rooms 15 15 0% 04-Jan-21 25-Jan-21 161 OWN

PR-3780 Procure/Deliver - 132148 Prefabricated Audiometric Rooms 50 50 0% 26-Jan-21 06-Apr-21 161 GC

134910 X-Ray Shielding134910 X-Ray Shielding 30 30 24-Dec-20 08-Feb-21 209

SP-2190 Submittal Prep - 134910 X-Ray Shielding 15 15 0% 24-Dec-20 15-Jan-21 209 GC

SR-2910 Submittal Review/Approve - 134910 X-Ray Shielding 15 15 0% 19-Jan-21 08-Feb-21 209 OWN

Division 21 - Fire SuppressionDivision 21 - Fire Suppression 140 140 24-Dec-20 15-Jul-21 114

211313.0020 Wet Pipe Sprinkler System Fire Protection211313.0020 Wet Pipe Sprinkler System Fire Protection 140 140 24-Dec-20 15-Jul-21 114

SP-2210 Submittal Prep - 211313.0020 Wet Piping Sprinkler System Fire Protection 20 20 0% 24-Dec-20 25-Jan-21 114 GC

SR-2930 Submittal Review/Approve - 211313.0020 Wet Piping Sprinkler System Fire Protection30 30 0% 26-Jan-21 09-Mar-21 114 OWN

PR-3810 Procure/Deliver - 211313.0020 Wet Piping Sprinkler System Fire Protection 90 90 0% 10-Mar-21 15-Jul-21 114 GC

Division 22 - PlumbingDivision 22 - Plumbing 105 105 24-Dec-20 25-May-21 159

220070 Plumbing Healthcare Facilities220070 Plumbing Healthcare Facilities 105 105 24-Dec-20 25-May-21 137

SP-2220 Submittal Prep - 220070 Plumbing Healthcare Facilities 10 10 0% 24-Dec-20 08-Jan-21 137 PL

SR-2940 Submittal Review/Approve - 220070 Plumbing Healthcare Facilities 15 15 0% 11-Jan-21 01-Feb-21 137 OWN

PR-3820 Procure/Deliver - 220070 Plumbing Healthcare Facilities 80 80 0% 02-Feb-21 25-May-21 137 PL

220548.0020 Mechanical Sounds Vibration and Seismic Control220548.0020 Mechanical Sounds Vibration and Seismic Control 15 15 24-Dec-20 15-Jan-21 217

SR-2950 Submittal Review/Approve - 220548.0020 Mechanical Sounds Vibration and Seismic Control15 15 0% 24-Dec-20 15-Jan-21 217 OWN

223100 Water Softeners Cation-Exchange (Sodium Cycle)223100 Water Softeners Cation-Exchange (Sodium Cycle) 85 85 24-Dec-20 27-Apr-21 178

SP-2240 Submittal Prep - 223100 Water Softeners Cation-Exchange (Sodium Cycle) 10 10 0% 24-Dec-20 08-Jan-21 178 PL

SR-2960 Submittal Review/Approve - 223100 Water Softeners Cation-Exchange (Sodium Cycle)15 15 0% 11-Jan-21 01-Feb-21 178 OWN

PR-3840 Procure/Deliver - 223100 Water Softeners Cation-Exchange (Sodium Cycle) 60 60 0% 02-Feb-21 27-Apr-21 178 PL

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Submittal Review/Approve - 114700 Ice Machines

Procure/Deliver - 114700 Ice Machines

Submittal Prep - 115300 Laboratory Equipment and Fumehoods

Submittal Review/Approve - 115300 Laboratory Equipment and Fumehoods

Procure/Deliver - 115300 Laboratory Equipment and Fumehoods

Submittal Review/Approve - 117000 General Requirements for Medical and Dental Equipment

Submittal Prep - 117100 Warming Cabinets Sterilizers and Associated Equipment

Submittal Review/Approve - 117100 Warming Cabinets Sterilizers and Associated Equipment

Procure/Deliver - 117100 Warming Cabinets Sterilizers and Associated Equipment

Submittal Review/Approve - 117213 Medical Equipment Misc

Submittal Prep - 117400 Dental Equipment

Submittal Review/Approve - 117400 Dental Equipment

Submittal Prep - 123570 Healthcare Casework

Submittal Review/Approve - 123570 Healthcare Casework

Procure/Deliver - 123570 Healthcare Casework

Submittal Prep - 123600 Countertops

Submittal Review/Approve - 123600 Countertops

Submittal Prep - 132148 Prefabricated Audiometric Rooms

Submittal Review/Approve - 132148 Prefabricated Audiometric Rooms

Procure/Deliver - 132148 Prefabricated Audiometric Rooms

Submittal Prep - 134910 X-Ray Shielding

Submittal Review/Approve - 134910 X-Ray Shielding

Submittal Prep - 211313.0020 Wet Piping Sprinkler System Fire Protection

Submittal Review/Approve - 211313.0020 Wet Piping Sprinkler System Fire Protection

Procure/Deliver - 211313.0020 Wet Piping Sprinkler System Fire Protection

Submittal Prep - 220070 Plumbing Healthcare Facilities

Submittal Review/Approve - 220070 Plumbing Healthcare Facilities

Procure/Deliver - 220070 Plumbing Healthcare Facilities

Submittal Review/Approve - 220548.0020 Mechanical Sounds Vibration and Seismic Control

Submittal Prep - 223100 Water Softeners Cation-Exchange (Sodium Cycle)

Submittal Review/Approve - 223100 Water Softeners Cation-Exchange (Sodium Cycle)

Procure/Deliver - 223100 Water Softeners Cation-Exchange (Sodium Cycle)

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 6 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

226070 Gas and Vacuum Systems for Healthcare Facilities226070 Gas and Vacuum Systems for Healthcare Facilities 70 70 24-Dec-20 06-Apr-21 194

SP-2250 Submittal Prep - 226070 Gas and Vacuum Systems for Healthcare Facilities 10 10 0% 24-Dec-20 08-Jan-21 194 PL

SR-2970 Submittal Review/Approve - 226070 Gas and Vacuum Systems for Healthcare Facilities15 15 0% 11-Jan-21 01-Feb-21 194 OWN

PR-3850 Procure/Deliver - 226070 Gas and Vacuum Systems for Healthcare Facilities 45 45 0% 02-Feb-21 06-Apr-21 194 PL

Division 23 - HVACDivision 23 - HVAC 165 165 24-Dec-20 19-Aug-21 136

230000 Air Supply Distribution Ventilation and Exhaust Systems230000 Air Supply Distribution Ventilation and Exhaust Systems 140 140 24-Dec-20 15-Jul-21 24

SP-2260 Submittal Prep - 230000 Air Supply Distribution Ventilation and Exhaust Systems5 5 0% 24-Dec-20 31-Dec-20 24 MECH

SR-2980 Submittal Review/Approve - 230000 Air Supply Distribution Ventilation and Exhaust Systems15 15 0% 04-Jan-21 25-Jan-21 24 OWN

PR-3860 Procure/Deliver - 230000 Air Supply Distribution Ventilation and Exhaust Systems120 120 0% 26-Jan-21 15-Jul-21 24 MECH

230300.0020 Basic Mechanical Materials and Methods230300.0020 Basic Mechanical Materials and Methods 15 15 24-Dec-20 15-Jan-21 179

SR-2990 Submittal Review/Approve - 230300.0020 Basic Mechanical Materials and Methods15 15 0% 24-Dec-20 15-Jan-21 179 OWN

230593 Testing Adjusting and Balancing for HVAC230593 Testing Adjusting and Balancing for HVAC 20 20 24-Dec-20 25-Jan-21 260

SP-2280 Submittal Prep - 230593 Testing Adjust and Balancing for HVAC 5 5 0% 24-Dec-20 31-Dec-20 260 GC

SR-3000 Submittal Review/Approve - 230593 Testing Adjust and Balancing for HVAC 15 15 0% 04-Jan-21 25-Jan-21 260 OWN

230700 Thermal Insulation for Mechanical Systems230700 Thermal Insulation for Mechanical Systems 110 110 24-Dec-20 02-Jun-21 170

SP-2290 Submittal Prep - 230700 Thermal Insulation for Mechanical Systems 5 5 0% 24-Dec-20 31-Dec-20 170 MECH

SR-3010 Submittal Review/Approve - 230700 Thermal Insulation for Mechanical Systems15 15 0% 04-Jan-21 25-Jan-21 170 OWN

PR-3890 Procure/Deliver - 230700 Thermal Insulation for Mechanical Systems 90 90 0% 26-Jan-21 02-Jun-21 170 MECH

230900 Instrumentation and Control for HVAC230900 Instrumentation and Control for HVAC 145 145 24-Dec-20 22-Jul-21 56

SP-2300 Submittal Prep - 230900 Instrumentation and Control for HVAC 50 50 0% 24-Dec-20 09-Mar-21 56 MECH

SR-3020 Submittal Review/Approve - 230900 Instrumentation and Control for HVAC 15 15 0% 10-Mar-21 30-Mar-21 56 OWN

PR-3900 Procure/Deliver - 230900 Instrumentation and Control for HVAC 80 80 0% 31-Mar-21 22-Jul-21 56 MECH

230913 Instrumentation and Control Devices for HVAC230913 Instrumentation and Control Devices for HVAC 165 165 24-Dec-20 19-Aug-21 36

SP-2310 Submittal Prep - 230913 Instrumentation and Control Devices for HVAC 50 50 0% 24-Dec-20 09-Mar-21 36 MECH

SR-3030 Submittal Review/Approve - 230913 Instrumentation and Control Devices for HVAC15 15 0% 10-Mar-21 30-Mar-21 36 OWN

PR-3910 Procure/Deliver - 230913 Instrumentation and Control Devices for HVAC 100 100 0% 31-Mar-21 19-Aug-21 36 MECH

230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems 165 165 24-Dec-20 19-Aug-21 36

SP-2320 Submittal Prep - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems50 50 0% 24-Dec-20 09-Mar-21 36 MECH

SR-3040 Submittal Review/Approve - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems15 15 0% 10-Mar-21 30-Mar-21 36 OWN

PR-3920 Procure/Deliver - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems100 100 0% 31-Mar-21 19-Aug-21 36 MECH

230993 Sequences of Operation for HVAC Control230993 Sequences of Operation for HVAC Control 95 95 24-Dec-20 11-May-21 106

SP-2330 Submittal Prep - 230993 Sequences of Operation for HVAC Control 50 50 0% 24-Dec-20 09-Mar-21 106 MECH

SR-3050 Submittal Review/Approve - 230993 Sequences of Operation for HVAC Control15 15 0% 10-Mar-21 30-Mar-21 106 OWN

PR-3930 Procure/Deliver - 230993 Sequences of Operation for HVAC Control 30 30 0% 31-Mar-21 11-May-21 106 MECH

231125 Facility Gas Piping231125 Facility Gas Piping 35 35 24-Dec-20 16-Feb-21 229

SP-2340 Submittal Prep - 231125 Facility Gas Piping 10 10 0% 24-Dec-20 08-Jan-21 229 PL

SR-3060 Submittal Review/Approve - 231125 Facility Gas Piping 15 15 0% 11-Jan-21 01-Feb-21 229 OWN

PR-3940 Procure/Deliver - 231125 Facility Gas Piping 10 10 0% 02-Feb-21 16-Feb-21 229 PL

232113.0020 Low Temperatures Water (LTW) Heating System232113.0020 Low Temperatures Water (LTW) Heating System 35 35 24-Dec-20 16-Feb-21 225

SP-2350 Submittal Prep - 232113.0020 Low Temperatures Water (LTW) Heating System10 10 0% 24-Dec-20 08-Jan-21 225 MECH

SR-3070 Submittal Review/Approve - 232113.0020 Low Temperatures Water (LTW) Heating System15 15 0% 11-Jan-21 01-Feb-21 225 OWN

PR-3950 Procure/Deliver - 232113.0020 Low Temperatures Water (LTW) Heating System10 10 0% 02-Feb-21 16-Feb-21 225 MECH

232123 Hydronic Pumps232123 Hydronic Pumps 140 140 24-Dec-20 15-Jul-21 120

SP-2360 Submittal Prep - 232123 Hydronic Pumps 5 5 0% 24-Dec-20 31-Dec-20 120 MECH

SR-3080 Submittal Review/Approve - 232123 Hydronic Pumps 15 15 0% 04-Jan-21 25-Jan-21 120 OWN

PR-3960 Procure/Deliver - 232123 Hydronic Pumps 120 120 0% 26-Jan-21 15-Jul-21 120 MECH

232500 Chemical Treatment of Water for Mechanical Systems232500 Chemical Treatment of Water for Mechanical Systems 140 140 24-Dec-20 15-Jul-21 161

SP-2370 Submittal Prep - 232500 Chemical Treatment of Water for Mechanical Systems 5 5 0% 24-Dec-20 31-Dec-20 161 MECH

Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct

2021 2022

Submittal Prep - 226070 Gas and Vacuum Systems for Healthcare Facilities

Submittal Review/Approve - 226070 Gas and Vacuum Systems for Healthcare Facilities

Procure/Deliver - 226070 Gas and Vacuum Systems for Healthcare Facilities

Submittal Prep - 230000 Air Supply Distribution Ventilation and Exhaust Systems

Submittal Review/Approve - 230000 Air Supply Distribution Ventilation and Exhaust Systems

Procure/Deliver - 230000 Air Supply Distribution Ventilation and Exhaust Systems

Submittal Review/Approve - 230300.0020 Basic Mechanical Materials and Methods

Submittal Prep - 230593 Testing Adjust and Balancing for HVAC

Submittal Review/Approve - 230593 Testing Adjust and Balancing for HVAC

Submittal Prep - 230700 Thermal Insulation for Mechanical Systems

Submittal Review/Approve - 230700 Thermal Insulation for Mechanical Systems

Procure/Deliver - 230700 Thermal Insulation for Mechanical Systems

Submittal Prep - 230900 Instrumentation and Control for HVAC

Submittal Review/Approve - 230900 Instrumentation and Control for HVAC

Procure/Deliver - 230900 Instrumentation and Control for HVAC

Submittal Prep - 230913 Instrumentation and Control Devices for HVAC

Submittal Review/Approve - 230913 Instrumentation and Control Devices for HVAC

Procure/Deliver - 230913 Instrumentation and Control Devices for HVAC

Submittal Prep - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems

Submittal Review/Approve - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems

Procure/Deliver - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems

Submittal Prep - 230993 Sequences of Operation for HVAC Control

Submittal Review/Approve - 230993 Sequences of Operation for HVAC Control

Procure/Deliver - 230993 Sequences of Operation for HVAC Control

Submittal Prep - 231125 Facility Gas Piping

Submittal Review/Approve - 231125 Facility Gas Piping

Procure/Deliver - 231125 Facility Gas Piping

Submittal Prep - 232113.0020 Low Temperatures Water (LTW) Heating System

Submittal Review/Approve - 232113.0020 Low Temperatures Water (LTW) Heating System

Procure/Deliver - 232113.0020 Low Temperatures Water (LTW) Heating System

Submittal Prep - 232123 Hydronic Pumps

Submittal Review/Approve - 232123 Hydronic Pumps

Procure/Deliver - 232123 Hydronic Pumps

Submittal Prep - 232500 Chemical Treatment of Water for Mechanical Systems

P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments

P9066-1.10.4.A TSLD

Data Date: 30-Sep-20

Actual Level of Effort Actual Work Remaining Work C... Page 7 of 32 TASK filter: All Activities

Remaining Duration

Activity % Complete

Start Finish Total Float Responsibility

SR-3090 Submittal Review/Approve - 232500 Chemical Treatment of Water for Mechanical Systems15 15 0% 04-Jan-21 25-Jan-21 161 OWN

PR-3970 Procure/Deliver - 232500 Chemical Treatment of Water for Mechanical Systems120 120 0% 26-Jan-21 15-Jul-21 161 MECH

235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output) 110 110 24-Dec-20 02-Jun-21 150

SP-2380 Submittal Prep - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)5 5 0% 24-Dec-20 31-Dec-20 150 MECH

SR-3100 Submittal Review/Approve - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)15 15 0% 04-Jan-21 25-Jan-21 150 OWN

PR-3980 Procure/Deliver - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)90 90 0% 26-Jan-21 02-Jun-21 150 MECH

236410 Water Chillers Vapor Compression Type236410 Water Chillers Vapor Compression Type 110 110 24-Dec-20 02-Jun-21 152

SP-2390 Submittal Prep - 236410 Water Chillers Vapor Compression Type 5 5 0% 24-Dec-20 31-Dec-20 152 MECH

SR-3110 Submittal Review/Approve - 236410 Water Chillers Vapor Compression Type 15 15 0% 04-Jan-21 25-Jan-21 152 OWN

PR-3990 Procure/Deliver - 236410 Water Chillers Vapor Compression Type 90 90 0% 26-Jan-21 02-Jun-21 152 MECH

236426 Chilled Chilled-Hot and Condenser Water Piping Systems236426 Chilled Chilled-Hot and Condenser Water Piping…