DRAFT GC_Schedule.pdf
PDF 12 MB Posted
- Attached to
- ACC Replacement 21 Area Initial Outfitting Project Federal contract opportunity
- Solicitation number
- W9127S21Q6003
About this file
This document provides details on an upcoming federal contract opportunity for an initial outfitting project at Camp Pendleton, California. The U.S. Army Corps of Engineers Little Rock District intends to issue a Request for Quote for the ACC Replacement 21 Area Initial Outfitting Project with an estimated value between $5-10 million. The simplified acquisition procedures of FAR Part 13 and commercial items procedures of FAR Part 12 will apply to this requirement, which will be set aside solely for Service-Disabled Veteran-Owned Small Businesses. Interested parties can submit questions through ProjNet until July 18, 2021, and quotes are due on July 23, 2021. This Special Notice provides advance notice of the forthcoming solicitation and anticipated requirement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DRAFT Copy of 6.7 PRICE SCHEDULE_PN89906 CP 21 Area.xlsx | XLSX spreadsheet | |
| DRAFT 6.4.2 Drawings (FFE)_PN89906 CP 21 AREA_BINDING 03_FINAL SET_Sign1.pdf | ||
| DRAFT SOW V2 PN89906 CP 21 Area IOT Standalone Requirements Document.pdf | ||
| DRAFT 6.7.1 DOR SPECS_PN89906_E2.2_EQ_Cutbook_M0005-X6610 (3).pdf | ||
| DRAFT Room by Room.pdf | ||
| DRAFT 6.4.1 Design-Construction Drawings_PN89906 CP 21 AREA_BINDING 02_FINAL SET_Sign1.pdf | ||
| DRAFT Program for Design.pdf | ||
| DRAFT 6.7.1 DOR SPECS_PN89906_E2.1_EQ_Cutbook_A1000-L8520.pdf | ||
| DRAFT 6.5.3 Program For Design_PN89906 CP 21 Area.pdf | ||
| DRAFT 6.5.1 Project Room Contents (FFE)_PN89906 CP 21 Area.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
www.soltekpacific.com 2424 Congress Street San Diego CA 92110 P 619.296.6247 | F 619.296.7109 Contractor License #886641 EOE
Ltr 1099-23 February 26, 2021
FEAD Camp Pendleton Building 22101, MCB, Camp Pendleton Camp Pendleton, California 92055-5229 Attention: LT JG Acosta Construction Manager
Reference: P-9906 Area 21 Ambulatory Care Center Replacement
Contract N62473-I8-D-5885, Task Order N62473-20-F-5350
Subject: Revised CPM Baseline Schedule
Dear LT JG Acosta, Attached for your review is our revised cost loaded Construction Baseline Schedule with a data date of 9-30-20 and a run date of 2-25-21. In this schedule we have incorporated the Government’s following review comments
Dated January 22, 2021 & February 17, 2120
As well as the mutually agreed up item during our meetings of
February 04, 2021 & February 23, 2021
To assist with the Government’s review of our schedule, we have provided the following:
32 Page Time Scale Logic Diagram ( 1.10.4.A ) 32 Page Previous Month Comparison ( 1.10.4.B ) 01 XER File ( 1.10.4.C ) 08 Page Schedule Leveling Log Report ( 1.10.4.D ) 02 Page Baseline Schedule Narrative ( 1.10.4.E ) 33 Page Complete Schedule with Cost Plot ( 1.10.4.F ) 01 Page Schedule Variance Control (Cash Curve ) Report ( 1.10.4.G )
03 Page Longest Path Plot without WBS ( 1.10.4.H ) 04 Page Baseline Check List ( 1.10.4.I ) 02 Page Summary of Screen Shots ( 1.10.4.J )
We look forward to meeting with you to discuss and come to a mutual understanding of any of the remaining Gov’t review comments that need to be incorporated into our revised Baseline Schedule.
Should you have any questions, comments or concerns about the information provided above or attached, I can be reached via my e-mail ( dcarlin@soltekpacific.com ) or my cell phone at 619-987-1925 and you can also reach out to Oscar Lucio ( olucio@soltekpacific.com ) or Oscar’s cell phone at 619-807-8244.
Sincerely, . cc. Michelle Barlow, Dave Carlin Daniel Ramos, Jim Vieira
Don Rote Job Site File Oscar Lucio Project Manager mailto:dcarlin@soltekpacific.com mailto:mrogan@soltekpacific.com
Activity ID Activity Name Original Duration
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post CommentsP-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments542 542 30-Sep-20 27-Oct-22 1
Project MilestonesProject Milestones 542 542 30-Sep-20 27-Oct-22 1
Management MilestonesManagement Milestones 542 542 30-Sep-20 27-Oct-22 1
MS-110 Notice to Proceed 0 0 0% 30-Sep-20 14 OWN
MS-100 Contract Award 0 0 0% 30-Sep-20* 0 OWN
MS-190 FF&E Installation Complete 0 0 0% 02-Mar-22 66 GC
MS-130 Phase 1 Substantial Completion 0 0 0% 04-Apr-22 10 GC
MS-170 Commissioning Complete 0 0 0% 12-Apr-22 37 GC
MS-180 HVAC Testing Complete 0 0 0% 11-May-22 16 GC
MS-200 Customer Move Complete 0 0 0% 27-May-22 4 GC
MS-150 Phase 2 Substantial Completion 0 0 0% 15-Sep-22 29 GC
MS-160 Phase 3 Substantial Completion 0 0 0% 27-Sep-22 21 GC
MS-120 Projected Completion 0 0 0% 27-Oct-22 1 OWN
MS-140 Contract Completion Date (CCD 10-30-22) 0 0 0% 27-Oct-22* 2 OWN
PermitsPermits 436 436 24-Dec-20 19-Sep-22 27
PER-1000 Permit - SWPPP Notice of Intent 10 10 0% 24-Dec-20 08-Jan-21 29 GC
PER-1020 Permit - APCD Notice 10 10 0% 05-Apr-22 18-Apr-22 34 GC
PER-1010 Permit - SWPPP Notice of Termination 10 10 0% 06-Sep-22 19-Sep-22 27 GC
Pre-Construction PhasePre-Construction Phase 232 232 30-Sep-20 19-Aug-21 248
Submittals, Review and Procurement (General)Submittals, Review and Procurement (General) 119 119 30-Sep-20 15-Mar-21 305
PAS-530 Prepare and Submit Commissioning Firm 5 5 0% 30-Sep-20 06-Oct-20 389 GC
PAS-540 Prepare and Submit T&B Firm 25 25 0% 30-Sep-20 03-Nov-20 209 GC
PAS-550 Prepare and Submit - Site Utility Repair Plan 25 25 0% 30-Sep-20 03-Nov-20 51 GC
PAS-100 Prepare and Submit Bond and Insurance 25 25 0% 30-Sep-20 03-Nov-20 24 GC
PAS-110 Prepare and Submit Accident Prevention Plan 20 20 0% 30-Sep-20 27-Oct-20 56 GC
PAS-120 Prepare and Submit CQC Plan 59 59 0% 30-Sep-20 22-Dec-20 8 GC
PAS-130 Prepare and Submit Environmental Protection Plan 15 15 0% 30-Sep-20 20-Oct-20 52 GC
PAS-140 Prepare and Submit Waste Management Plan 15 15 0% 30-Sep-20 20-Oct-20 34 GC
PAS-150 Prepare and Submit Baseline Construction Schedule 65 65 0% 30-Sep-20 31-Dec-20 2 GC
PAS-160 Prepare and Submit SWPP Plan 50 50 0% 30-Sep-20 09-Dec-20 17 GC
PAS-170 Prepare and Submit Construction Site Plan 15 15 0% 30-Sep-20 20-Oct-20 34 GC
PAS-180 Prepare and Submit Temp Power Plan 25 25 0% 30-Sep-20 03-Nov-20 16 GC
PAS-270 Prepare and Submit Utility Coordination \ Location Report 53 53 0% 30-Sep-20 14-Dec-20 14 GC
PAS-560 Review/Approve Commissioning Firm 21 21 0% 06-Oct-20 27-Oct-20 566 OWN
PAS-210 Review/Approve Environmental Protection Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN
PAS-220 Review/Approve Waste Management Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN
PAS-250 Review/Approve Construction Site Plan 21 21 0% 20-Oct-20 10-Nov-20 77 OWN
PAS-190 Review/Approve Accident Prevention Plan 5 5 0% 28-Oct-20 03-Nov-20 56 OWN
PAS-260 Review/Approve Temp Power Plan 21 21 0% 03-Nov-20 24-Nov-20 23 OWN
PAS-570 Review/Approve T&B Firm 21 21 0% 03-Nov-20 24-Nov-20 463 OWN
PAS-105 Review/Approve Bonds 6 6 0% 04-Nov-20 11-Nov-20 24 OWN
PAS-580 Prepare and SubmitCX Design Review Report per Section 01 91 00.15 5 5 0% 04-Nov-20 10-Nov-20 224 GC
PAS-590 Review/Approve - Site Utility Repair Plan 5 5 0% 04-Nov-20 10-Nov-20 51 OWN
PAS-108 Review/Approve Insurance 7 7 0% 04-Nov-20 12-Nov-20 24 OWN
PAS-240 Review/Approve SWPP Plan 21 21 0% 09-Dec-20 30-Dec-20 27 OWN
PAS-280 Review/Approve Utility Coordination \ Location Report 21 21 0% 14-Dec-20 04-Jan-21 22 OWN
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Notice to Proceed, 30-Sep-20
Contract Award, 30-Sep-20*
FF&E Installation Complete, Phase 1 Substantial Completion, Commissioning Complete, HVAC Testing Complete, Customer Move Complete, Phase 2 Substantial Completion, Phase 3 Substantial Completion, Permit - SWPPP Notice of Intent
Permit - APCD Notice
Permit - SWPPP Notice of Termination
Prepare and Submit Commissioning Firm
Prepare and Submit T&B Firm
Prepare and Submit - Site Utility Repair Plan
Prepare and Submit Bond and Insurance
Prepare and Submit Accident Prevention Plan
Prepare and Submit CQC Plan
Prepare and Submit Environmental Protection Plan
Prepare and Submit Waste Management Plan
Prepare and Submit Baseline Construction Schedule
Prepare and Submit SWPP Plan
Prepare and Submit Construction Site Plan
Prepare and Submit Temp Power Plan
Prepare and Submit Utility Coordination \ Location Report
Review/Approve Commissioning Firm
Review/Approve Environmental Protection Plan
Review/Approve Waste Management Plan
Review/Approve Construction Site Plan
Review/Approve Accident Prevention Plan
Review/Approve Temp Power Plan
Review/Approve T&B Firm
Review/Approve Bonds
Prepare and SubmitCX Design Review Report per Section 01 91 00.15
Review/Approve - Site Utility Repair Plan
Review/Approve Insurance
Review/Approve SWPP Plan
Review/Approve Utility Coordination \ Location Report
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Print Date: 25-Feb-21 08:54
Actual Level of Effort Actual Work Remaining Work C... Page 1 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
PAS-200 Review/Approve CQC Plan 21 21 0% 22-Dec-20 12-Jan-21 14 OWN
PAS-230 Review/Approve Baseline Construction Schedule 21 21 0% 31-Dec-20 21-Jan-21 5 OWN
PAS-600 Prepare and Submit Utility Service Connection Application Water / Telecom 1 1 0% 15-Mar-21 15-Mar-21 99 ELE
Submittals, Review and ProcurementSubmittals, Review and Procurement 225 225 30-Sep-20 19-Aug-21 238
Division 1Division 1 35 35 30-Sep-20 17-Nov-20 379
019100 Commssioning019100 Commssioning 35 35 30-Sep-20 17-Nov-20 379
BC-1060 Submit Utility Service Connection Application 15 15 0% 30-Sep-20 20-Oct-20 379 PWFEAD
BC-1085 Submittal Review/Approve - Utility Service Connection Application 20 20 0% 21-Oct-20 17-Nov-20 379 OWN
Division 2 - Existing ConditionsDivision 2 - Existing Conditions 25 25 24-Dec-20 01-Feb-21 348
028100 Transportation and Disposal of Hazardous Materials028100 Transportation and Disposal of Hazardous Materials 25 25 24-Dec-20 01-Feb-21 348
SP-1510 Submittal Prep - 028100 Transportation and Disposal of Hazardous Materials 5 5 0% 24-Dec-20 31-Dec-20 348 GC
SR-2230 Submittal Review/Approve - 028100 Transportation and Disposal of Hazardous Materials20 20 0% 04-Jan-21 01-Feb-21 348 OWN
028200 Asbestos Remediation028200 Asbestos Remediation 20 20 24-Dec-20 25-Jan-21 353
SP-1520 Submittal Prep - 028200 Asbestos Remediation 5 5 0% 24-Dec-20 31-Dec-20 353 GC
SR-2240 Submittal Review/Approve - 028200 Asbestos Remediation 15 15 0% 04-Jan-21 25-Jan-21 353 OWN
028300 Lead Remediation028300 Lead Remediation 20 20 24-Dec-20 25-Jan-21 353
SP-1530 Submittal Prep - 028300 Lead Remediation 5 5 0% 24-Dec-20 31-Dec-20 353 GC
SR-2250 Submittal Review/Approve - 028300 Lead Remediation 15 15 0% 04-Jan-21 25-Jan-21 353 OWN
Division 3 - ConcreteDivision 3 - Concrete 45 45 24-Dec-20 02-Mar-21 195
033000 CIP Rebar033000 CIP Rebar 45 45 24-Dec-20 02-Mar-21 195
SP-3420 Submittal Prep - 033000 CIP Rebar 10 10 0% 24-Dec-20 08-Jan-21 195 REIN
SR-1210 Submittal Review/Approve - 033000 CIP Rebar 15 15 0% 11-Jan-21 01-Feb-21 195 OWN
PR-1090 Procure/Deliver - 033000 CIP Rebar 20 20 0% 02-Feb-21 02-Mar-21 195 REIN
Division 4 - MasonryDivision 4 - Masonry 65 65 24-Dec-20 30-Mar-21 183
042000 Unit Masonry042000 Unit Masonry 65 65 24-Dec-20 30-Mar-21 183
SP-1550 Submittal Prep - 042000 Unit Masonry 5 5 0% 24-Dec-20 31-Dec-20 183 MAS
SR-2270 Submittal Review/Approve - 042000 Unit Masonry 15 15 0% 04-Jan-21 25-Jan-21 183 OWN
PR-3150 Procure/Deliver - 042000 Unit Masonry 45 45 0% 26-Jan-21 30-Mar-21 183 MAS
Division 5 - MetalsDivision 5 - Metals 105 105 24-Dec-20 25-May-21 55
051200 Structural Steel051200 Structural Steel 105 105 24-Dec-20 25-May-21 38
SP-1570 Submittal Prep - 051200 Structural Steel 30 30 0% 24-Dec-20 08-Feb-21 38 GC
SR-2290 Submittal Review/Approve - 051200 Structural Steel 15 15 0% 09-Feb-21 02-Mar-21 38 OWN
PR-3170 Procure/Deliver - 051200 Structural Steel 60 60 0% 03-Mar-21 25-May-21 38 GC
052100 Steel Joist Framing052100 Steel Joist Framing 105 105 24-Dec-20 25-May-21 33
SP-1580 Submittal Prep - 052100 Steel Joist Framing 30 30 0% 24-Dec-20 08-Feb-21 33 GC
SR-2300 Submittal Review/Approve - 052100 Steel Joist Framing 15 15 0% 09-Feb-21 02-Mar-21 33 OWN
PR-3180 Procure/Deliver - 052100 Steel Joist Framing 60 60 0% 03-Mar-21 25-May-21 33 GC
053000 Steel Decks053000 Steel Decks 85 85 24-Dec-20 27-Apr-21 75
SP-1590 Submittal Prep - 053000 Steel Decks 10 10 0% 24-Dec-20 08-Jan-21 75 DECK
SR-2310 Submittal Review/Approve - 053000 Steel Decks 15 15 0% 11-Jan-21 01-Feb-21 75 OWN
PR-3190 Procure/Deliver - 053000 Steel Decks 60 60 0% 02-Feb-21 27-Apr-21 75 DECK
054000 Cold-Formed Metal Framing054000 Cold-Formed Metal Framing 45 45 24-Dec-20 02-Mar-21 93
SP-1600 Submittal Prep - 054000 Cold-Formed Metal Framing 15 15 0% 24-Dec-20 15-Jan-21 93 GC
SR-2320 Submittal Review/Approve - 054000 Cold-Formed Metal Framing 15 15 0% 19-Jan-21 08-Feb-21 93 OWN
PR-3200 Procure/Deliver - 054000 Cold-Formed Metal Framing 15 15 0% 09-Feb-21 02-Mar-21 93 GC
055013 Misc Metal Fabrication055013 Misc Metal Fabrication 45 45 24-Dec-20 02-Mar-21 86
SP-1620 Submittal Prep - 055013 Misc Metal Fabrication 30 30 0% 24-Dec-20 08-Feb-21 86 GC
SR-2340 Submittal Review/Approve - 055013 Misc Metal Fabrication 15 15 0% 09-Feb-21 02-Mar-21 86 OWN
Division 6 - Wood Plastics and CompositesDivision 6 - Wood Plastics and Composites 30 30 24-Dec-20 08-Feb-21 294
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Review/Approve CQC Plan
Review/Approve Baseline Construction Schedule
Prepare and Submit Utility Service Connection Application Water / Telecom
Submit Utility Service Connection Application
Submittal Review/Approve - Utility Service Connection Application
Submittal Prep - 028100 Transportation and Disposal of Hazardous Materials
Submittal Review/Approve - 028100 Transportation and Disposal of Hazardous Materials
Submittal Prep - 028200 Asbestos Remediation
Submittal Review/Approve - 028200 Asbestos Remediation
Submittal Prep - 028300 Lead Remediation
Submittal Review/Approve - 028300 Lead Remediation
Submittal Prep - 033000 CIP Rebar
Submittal Review/Approve - 033000 CIP Rebar
Procure/Deliver - 033000 CIP Rebar
Submittal Prep - 042000 Unit Masonry
Submittal Review/Approve - 042000 Unit Masonry
Procure/Deliver - 042000 Unit Masonry
Submittal Prep - 051200 Structural Steel
Submittal Review/Approve - 051200 Structural Steel
Procure/Deliver - 051200 Structural Steel
Submittal Prep - 052100 Steel Joist Framing
Submittal Review/Approve - 052100 Steel Joist Framing
Procure/Deliver - 052100 Steel Joist Framing
Submittal Prep - 053000 Steel Decks
Submittal Review/Approve - 053000 Steel Decks
Procure/Deliver - 053000 Steel Decks
Submittal Prep - 054000 Cold-Formed Metal Framing
Submittal Review/Approve - 054000 Cold-Formed Metal Framing
Procure/Deliver - 054000 Cold-Formed Metal Framing
Submittal Prep - 055013 Misc Metal Fabrication
Submittal Review/Approve - 055013 Misc Metal Fabrication
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 2 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
061000 Rough Carpentry061000 Rough Carpentry 15 15 24-Dec-20 15-Jan-21 176
SR-2350 Submittal Review/Approve - 061000 Rough Carpentry 15 15 0% 24-Dec-20 15-Jan-21 176 OWN
062000 Finish Carpentry062000 Finish Carpentry 30 30 24-Dec-20 08-Feb-21 292
SP-1640 Submittal Prep - 062000 Finish Carpentry 15 15 0% 24-Dec-20 15-Jan-21 292 GC
SR-2360 Submittal Review/Approve - 062000 Finish Carpentry 15 15 0% 19-Jan-21 08-Feb-21 292 OWN
066116 Solid Surfacing Fabrications066116 Solid Surfacing Fabrications 30 30 24-Dec-20 08-Feb-21 277
SP-1650 Submittal Prep - 066116 Solid Surfacing Fabrications 15 15 0% 24-Dec-20 15-Jan-21 277 CW
SR-2370 Submittal Review/Approve - 066116 Solid Surfacing Fabrications 15 15 0% 19-Jan-21 08-Feb-21 277 OWN
066413 Translucent Resin Panel Restrictions066413 Translucent Resin Panel Restrictions 30 30 24-Dec-20 08-Feb-21 294
SP-1660 Submittal Prep - 066413 Translucent Resin Panel Restrictions 15 15 0% 24-Dec-20 15-Jan-21 294 CW
SR-2380 Submittal Review/Approve - 066413 Translucent Resin Panel Restrictions 15 15 0% 19-Jan-21 08-Feb-21 294 OWN
Division 7 - Thermal and Moisture ProtectionDivision 7 - Thermal and Moisture Protection 135 135 24-Dec-20 08-Jul-21 105
070523 Pressure Testing an Air Barrier System for Air Tightness070523 Pressure Testing an Air Barrier System for Air Tightness 25 25 24-Dec-20 01-Feb-21 159
SP-1670 Submittal Prep - 070523 Pressure Testing an Air Barrier System for Air Tightness10 10 0% 24-Dec-20 08-Jan-21 159 GC
SR-2390 Submittal Review/Approve - 070523 Pressure Testing an Air Barrier System for Air Tightness15 15 0% 11-Jan-21 01-Feb-21 159 OWN
072113 Board and Block Insulation072113 Board and Block Insulation 40 40 24-Dec-20 23-Feb-21 150
SP-1680 Submittal Prep - 072113 Board and Block Insulation 5 5 0% 24-Dec-20 31-Dec-20 150 INSUL
SR-2400 Submittal Review/Approve - 072113 Board and Block Insulation 15 15 0% 04-Jan-21 25-Jan-21 150 OWN
PR-3280 Procure/Deliver - 072113 Board and Block Insulation 20 20 0% 26-Jan-21 23-Feb-21 150 INSUL
072116 Mineral Fiber Blanket Insulation072116 Mineral Fiber Blanket Insulation 65 65 24-Dec-20 30-Mar-21 126
SP-1690 Submittal Prep - 072116 Mineral Fiber Blanket Insulation 5 5 0% 24-Dec-20 31-Dec-20 126 INSUL
SR-2410 Submittal Review/Approve - 072116 Mineral Fiber Blanket Insulation 15 15 0% 04-Jan-21 25-Jan-21 126 OWN
PR-3290 Procure/Deliver - 072116 Mineral Fiber Blanket Insulation 45 45 0% 26-Jan-21 30-Mar-21 126 INSUL
072129 Sprayed Acoustic Insulation072129 Sprayed Acoustic Insulation 34 34 24-Dec-20 12-Feb-21 157
SP-1700 Submittal Prep - 072129 Sprayed Acoustic Insulation 5 5 0% 24-Dec-20 31-Dec-20 157 INSUL
SR-2420 Submittal Review/Approve - 072129 Sprayed Acoustic Insulation 15 15 0% 04-Jan-21 25-Jan-21 157 OWN
PR-3300 Procure/Deliver - 072129 Sprayed Acoustic Insulation 14 14 0% 26-Jan-21 12-Feb-21 157 INSUL
072719.01 Self-Adhering Air Barriers072719.01 Self-Adhering Air Barriers 40 40 17-Mar-21 11-May-21 99
SP-1710 Submittal Prep - 072719.01 Self-Adhering Barriers 10 10 0% 17-Mar-21 30-Mar-21 99 GC
SR-2430 Submittal Review/Approve - 072719.01 Self-Adhering Barriers 15 15 0% 31-Mar-21 20-Apr-21 99 OWN
PR-3310 Procure/Deliver - 072719.01 Self-Adhering Barriers 15 15 0% 21-Apr-21 11-May-21 99 GC
074113 Metal Roof Panels074113 Metal Roof Panels 80 80 24-Dec-20 20-Apr-21 160
SP-1720 Submittal Prep - 074113 Metal Roof Panels 20 20 0% 24-Dec-20 25-Jan-21 160 GC
SR-2440 Submittal Review/Approve - 074113 Metal Roof Panels 15 15 0% 26-Jan-21 16-Feb-21 160 OWN
PR-3320 Procure/Deliver - 074113 Metal Roof Panels 45 45 0% 17-Feb-21 20-Apr-21 160 GC
074213 Metal Wall Panels074213 Metal Wall Panels 80 80 24-Dec-20 20-Apr-21 139
SP-1730 Submittal Prep - 074213 Metal Wall Panels 20 20 0% 24-Dec-20 25-Jan-21 139 GC
SR-2450 Submittal Review/Approve - 074213 Metal Wall Panels 15 15 0% 26-Jan-21 16-Feb-21 139 OWN
PR-3330 Procure/Deliver - 074213 Metal Wall Panels 45 45 0% 17-Feb-21 20-Apr-21 139 GC
076000 Flashing and Sheet Metals076000 Flashing and Sheet Metals 80 80 17-Mar-21 08-Jul-21 105
SP-1740 Submittal Prep - 076000 Flashing and Sheet Metals 20 20 0% 17-Mar-21 13-Apr-21 105 GC
SR-2460 Submittal Review/Approve - 076000 Flashing and Sheet Metals 15 15 0% 14-Apr-21 04-May-21 105 OWN
PR-3340 Procure/Deliver - 076000 Flashing and Sheet Metals 45 45 0% 05-May-21 08-Jul-21 105 GC
078400 Firestopping078400 Firestopping 20 20 24-Dec-20 25-Jan-21 174
SP-1750 Submittal Prep - 078400 Firestopping 5 5 0% 24-Dec-20 31-Dec-20 174 GC
SR-2470 Submittal Review/Approve - 078400 Firestopping 15 15 0% 04-Jan-21 25-Jan-21 174 OWN
079200 Joint Sealants079200 Joint Sealants 25 25 24-Dec-20 01-Feb-21 168
SP-1760 Submittal Prep - 079200 Joint Sealants 10 10 0% 24-Dec-20 08-Jan-21 168 GC
SR-2480 Submittal Review/Approve - 079200 Joint Sealants 15 15 0% 11-Jan-21 01-Feb-21 168 OWN
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Submittal Review/Approve - 061000 Rough Carpentry
Submittal Prep - 062000 Finish Carpentry
Submittal Review/Approve - 062000 Finish Carpentry
Submittal Prep - 066116 Solid Surfacing Fabrications
Submittal Review/Approve - 066116 Solid Surfacing Fabrications
Submittal Prep - 066413 Translucent Resin Panel Restrictions
Submittal Review/Approve - 066413 Translucent Resin Panel Restrictions
Submittal Prep - 070523 Pressure Testing an Air Barrier System for Air Tightness
Submittal Review/Approve - 070523 Pressure Testing an Air Barrier System for Air Tightness
Submittal Prep - 072113 Board and Block Insulation
Submittal Review/Approve - 072113 Board and Block Insulation
Procure/Deliver - 072113 Board and Block Insulation
Submittal Prep - 072116 Mineral Fiber Blanket Insulation
Submittal Review/Approve - 072116 Mineral Fiber Blanket Insulation
Procure/Deliver - 072116 Mineral Fiber Blanket Insulation
Submittal Prep - 072129 Sprayed Acoustic Insulation
Submittal Review/Approve - 072129 Sprayed Acoustic Insulation
Procure/Deliver - 072129 Sprayed Acoustic Insulation
Submittal Prep - 072719.01 Self-Adhering Barriers
Submittal Review/Approve - 072719.01 Self-Adhering Barriers
Procure/Deliver - 072719.01 Self-Adhering Barriers
Submittal Prep - 074113 Metal Roof Panels
Submittal Review/Approve - 074113 Metal Roof Panels
Procure/Deliver - 074113 Metal Roof Panels
Submittal Prep - 074213 Metal Wall Panels
Submittal Review/Approve - 074213 Metal Wall Panels
Procure/Deliver - 074213 Metal Wall Panels
Submittal Prep - 076000 Flashing and Sheet Metals
Submittal Review/Approve - 076000 Flashing and Sheet Metals
Procure/Deliver - 076000 Flashing and Sheet Metals
Submittal Prep - 078400 Firestopping
Submittal Review/Approve - 078400 Firestopping
Submittal Prep - 079200 Joint Sealants
Submittal Review/Approve - 079200 Joint Sealants
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 3 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
Division 8 - OpeningsDivision 8 - Openings 140 140 24-Dec-20 15-Jul-21 206
081113 Steel Doors and Frames081113 Steel Doors and Frames 60 60 24-Dec-20 23-Mar-21 286
SP-1770 Submittal Prep - 081113 Steel Doors and Frames 5 5 0% 24-Dec-20 31-Dec-20 286 GC
SR-2490 Submittal Review/Approve - 081113 Steel Doors and Frames 15 15 0% 04-Jan-21 25-Jan-21 286 OWN
PR-3370 Procure/Deliver - 081113 Steel Doors and Frames 40 40 0% 26-Jan-21 23-Mar-21 286 DO
081116 Aluminum Doors and Frames081116 Aluminum Doors and Frames 60 60 24-Dec-20 23-Mar-21 286
SP-1780 Submittal Prep - 081116 Aluminum Doors and Frames 5 5 0% 24-Dec-20 31-Dec-20 286 GC
SR-2500 Submittal Review/Approve - 081116 Aluminum Doors and Frames 15 15 0% 04-Jan-21 25-Jan-21 286 OWN
PR-3380 Procure/Deliver - 081116 Aluminum Doors and Frames 40 40 0% 26-Jan-21 23-Mar-21 286 GC
081400 Wood Doors081400 Wood Doors 60 60 24-Dec-20 23-Mar-21 259
SP-1790 Submittal Prep - 081400 Wood Doors 5 5 0% 24-Dec-20 31-Dec-20 259 GC
SR-2510 Submittal Review/Approve - 081400 Wood Doors 15 15 0% 04-Jan-21 25-Jan-21 259 OWN
PR-3390 Procure/Deliver - 081400 Wood Doors 40 40 0% 26-Jan-21 23-Mar-21 259 DO
083100 Access Doors and Frames083100 Access Doors and Frames 30 30 24-Dec-20 08-Feb-21 289
SP-1800 Submittal Prep - 083100 Access Doors and Frames 15 15 0% 24-Dec-20 15-Jan-21 289 GC
SR-2520 Submittal Review/Approve - 083100 Access Doors and Frames 15 15 0% 19-Jan-21 08-Feb-21 289 OWN
083313 Coiling Counter Doors083313 Coiling Counter Doors 60 60 24-Dec-20 23-Mar-21 250
SP-1810 Submittal Prep - 083313 Coiling Counter Doors 5 5 0% 24-Dec-20 31-Dec-20 250 GC
SR-2530 Submittal Review/Approve - 083313 Coiling Counter Doors 15 15 0% 04-Jan-21 25-Jan-21 250 OWN
PR-3410 Procure/Deliver - 083313 Coiling Counter Doors 40 40 0% 26-Jan-21 23-Mar-21 250 GC
084400 Curtain Wall and Glaze Assemblies084400 Curtain Wall and Glaze Assemblies 115 115 24-Dec-20 09-Jun-21 182
SP-1820 Submittal Prep - 084400 Curtain Wall and Glaze Assemblies 30 30 0% 24-Dec-20 08-Feb-21 182 GC
SR-2540 Submittal Review/Approve - 084400 Curtain Wall and Glaze Assemblies 15 15 0% 09-Feb-21 02-Mar-21 182 OWN
PR-3420 Procure/Deliver - 084400 Curtain Wall and Glaze Assemblies 70 70 0% 03-Mar-21 09-Jun-21 182 GC
085680 Aluminum Sliding Service Windows085680 Aluminum Sliding Service Windows 50 50 24-Dec-20 09-Mar-21 256
SP-1830 Submittal Prep - 085680 Aluminum Sliding Service Windows 5 5 0% 24-Dec-20 31-Dec-20 256 GC
SR-2550 Submittal Review/Approve - 085680 Aluminum Sliding Service Windows 15 15 0% 04-Jan-21 25-Jan-21 256 OWN
PR-3430 Procure/Deliver - 085680 Aluminum Sliding Service Windows 30 30 0% 26-Jan-21 09-Mar-21 256 GC
086045 Skylights086045 Skylights 80 80 24-Dec-20 20-Apr-21 101
SP-1840 Submittal Prep - 086045 Skylights 20 20 0% 24-Dec-20 25-Jan-21 101 GC
SR-2560 Submittal Review/Approve - 086045 Skylights 15 15 0% 26-Jan-21 16-Feb-21 101 OWN
PR-3440 Procure/Deliver - 086045 Skylights 45 45 0% 17-Feb-21 20-Apr-21 101 GC
087100 Door Hardware087100 Door Hardware 140 140 24-Dec-20 15-Jul-21 181
SP-1850 Submittal Prep - 087100 Door Hardware 5 5 0% 24-Dec-20 31-Dec-20 181 GC
SR-2570 Submittal Review/Approve - 087100 Door Hardware 15 15 0% 04-Jan-21 25-Jan-21 181 OWN
PR-3450 Procure/Deliver - 087100 Door Hardware 120 120 0% 26-Jan-21 15-Jul-21 181 DO
088100 Glazing088100 Glazing 115 115 24-Dec-20 09-Jun-21 185
SP-1860 Submittal Prep - 088100 Glazing 30 30 0% 24-Dec-20 08-Feb-21 185 GC
SR-2580 Submittal Review/Approve - 088100 Glazing 15 15 0% 09-Feb-21 02-Mar-21 185 OWN
PR-3460 Procure/Deliver - 088100 Glazing 70 70 0% 03-Mar-21 09-Jun-21 185 GC
089100 Metal Wall Louvers089100 Metal Wall Louvers 80 80 24-Dec-20 20-Apr-21 219
SP-1870 Submittal Prep - 089100 Metal Wall Louvers 20 20 0% 24-Dec-20 25-Jan-21 219 MECH
SR-2590 Submittal Review/Approve - 089100 Metal Wall Louvers 15 15 0% 26-Jan-21 16-Feb-21 219 OWN
PR-3470 Procure/Deliver - 089100 Metal Wall Louvers 45 45 0% 17-Feb-21 20-Apr-21 219 MECH
Division 9 - FinishesDivision 9 - Finishes 80 80 24-Dec-20 20-Apr-21 235
092200 Supports of Gypsum Boards092200 Supports of Gypsum Boards 15 15 24-Dec-20 15-Jan-21 171
SR-2600 Submittal Review/Approve - 092200 Supports of Gypsum Boards 15 15 0% 24-Dec-20 15-Jan-21 171 OWN
092900 Gypsum Board092900 Gypsum Board 40 40 24-Dec-20 23-Feb-21 146
SP-1890 Submittal Prep - 092900 Gypsum Board 10 10 0% 24-Dec-20 08-Jan-21 146 GC
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Submittal Prep - 081113 Steel Doors and Frames
Submittal Review/Approve - 081113 Steel Doors and Frames
Procure/Deliver - 081113 Steel Doors and Frames
Submittal Prep - 081116 Aluminum Doors and Frames
Submittal Review/Approve - 081116 Aluminum Doors and Frames
Procure/Deliver - 081116 Aluminum Doors and Frames
Submittal Prep - 081400 Wood Doors
Submittal Review/Approve - 081400 Wood Doors
Procure/Deliver - 081400 Wood Doors
Submittal Prep - 083100 Access Doors and Frames
Submittal Review/Approve - 083100 Access Doors and Frames
Submittal Prep - 083313 Coiling Counter Doors
Submittal Review/Approve - 083313 Coiling Counter Doors
Procure/Deliver - 083313 Coiling Counter Doors
Submittal Prep - 084400 Curtain Wall and Glaze Assemblies
Submittal Review/Approve - 084400 Curtain Wall and Glaze Assemblies
Procure/Deliver - 084400 Curtain Wall and Glaze Assemblies
Submittal Prep - 085680 Aluminum Sliding Service Windows
Submittal Review/Approve - 085680 Aluminum Sliding Service Windows
Procure/Deliver - 085680 Aluminum Sliding Service Windows
Submittal Prep - 086045 Skylights
Submittal Review/Approve - 086045 Skylights
Procure/Deliver - 086045 Skylights
Submittal Prep - 087100 Door Hardware
Submittal Review/Approve - 087100 Door Hardware
Procure/Deliver - 087100 Door Hardware
Submittal Prep - 088100 Glazing
Submittal Review/Approve - 088100 Glazing
Procure/Deliver - 088100 Glazing
Submittal Prep - 089100 Metal Wall Louvers
Submittal Review/Approve - 089100 Metal Wall Louvers
Procure/Deliver - 089100 Metal Wall Louvers
Submittal Review/Approve - 092200 Supports of Gypsum Boards
Submittal Prep - 092900 Gypsum Board
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 4 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
SR-2610 Submittal Review/Approve - 092900 Gypsum Board 15 15 0% 11-Jan-21 01-Feb-21 146 OWN
PR-3490 Procure/Deliver - 092900 Gypsum Board 15 15 0% 02-Feb-21 23-Feb-21 146 GC
093010 Tiling093010 Tiling 50 50 24-Dec-20 09-Mar-21 261
SP-1900 Submittal Prep - 093010 Tiling 5 5 0% 24-Dec-20 31-Dec-20 261 FL
SR-2620 Submittal Review/Approve - 093010 Tiling 15 15 0% 04-Jan-21 25-Jan-21 261 OWN
PR-3500 Procure/Deliver - 093010 Tiling 30 30 0% 26-Jan-21 09-Mar-21 261 FL
095100 Acoustical Ceilings095100 Acoustical Ceilings 45 45 24-Dec-20 02-Mar-21 223
SP-1910 Submittal Prep - 095100 Acoustical Ceilings 15 15 0% 24-Dec-20 15-Jan-21 223 GC
SR-2630 Submittal Review/Approve - 095100 Acoustical Ceilings 15 15 0% 19-Jan-21 08-Feb-21 223 OWN
PR-3510 Procure/Deliver - 095100 Acoustical Ceilings 15 15 0% 09-Feb-21 02-Mar-21 223 GC
095423 Linear Metal Ceilings095423 Linear Metal Ceilings 45 45 24-Dec-20 02-Mar-21 270
SP-1920 Submittal Prep - 095423 Linear Metal Ceilings 15 15 0% 24-Dec-20 15-Jan-21 270 GC
SR-2640 Submittal Review/Approve - 095423 Linear Metal Ceilings 15 15 0% 19-Jan-21 08-Feb-21 270 OWN
PR-3520 Procure/Deliver - 095423 Linear Metal Ceilings 15 15 0% 09-Feb-21 02-Mar-21 270 GC
096500 Resilient Flooring096500 Resilient Flooring 50 50 24-Dec-20 09-Mar-21 226
SP-1930 Submittal Prep - 096500 Resilient Flooring 5 5 0% 24-Dec-20 31-Dec-20 226 FL
SR-2650 Submittal Review/Approve - 096500 Resilient Flooring 15 15 0% 04-Jan-21 25-Jan-21 226 OWN
PR-3530 Procure/Deliver - 096500 Resilient Flooring 30 30 0% 26-Jan-21 09-Mar-21 226 FL
096800 Carpeting096800 Carpeting 80 80 24-Dec-20 20-Apr-21 219
SP-1940 Submittal Prep - 096800 Carpeting 5 5 0% 24-Dec-20 31-Dec-20 219 FL
SR-2660 Submittal Review/Approve - 096800 Carpeting 15 15 0% 04-Jan-21 25-Jan-21 219 OWN
PR-3540 Procure/Deliver - 096800 Carpeting 60 60 0% 26-Jan-21 20-Apr-21 219 FL
097710 Modular Panel Systems097710 Modular Panel Systems 20 20 24-Dec-20 25-Jan-21 276
SP-1950 Submittal Prep - 097710 Modular Panel Systems 5 5 0% 24-Dec-20 31-Dec-20 276 GC
SR-2670 Submittal Review/Approve - 097710 Modular Panel Systems 15 15 0% 04-Jan-21 25-Jan-21 276 OWN
099000 Paints and Coatings099000 Paints and Coatings 30 30 24-Dec-20 08-Feb-21 244
SP-1960 Submittal Prep - 099000 Paints and Coatings 5 5 0% 24-Dec-20 31-Dec-20 244 GC
SR-2680 Submittal Review/Approve - 099000 Paints and Coatings 15 15 0% 04-Jan-21 25-Jan-21 244 OWN
PR-3560 Procure/Deliver - 099000 Paints and Coatings 10 10 0% 26-Jan-21 08-Feb-21 244 GC
Division 10 - SpecialtiesDivision 10 - Specialties 75 75 24-Dec-20 13-Apr-21 273
101100 Visual Display Units101100 Visual Display Units 75 75 24-Dec-20 13-Apr-21 218
SP-1970 Submittal Prep - 101100 Visual Display Units 15 15 0% 24-Dec-20 15-Jan-21 218 SIGN
SR-2690 Submittal Review/Approve - 101100 Visual Display Units 15 15 0% 19-Jan-21 08-Feb-21 218 OWN
PR-3570 Procure/Deliver - 101100 Visual Display Units 45 45 0% 09-Feb-21 13-Apr-21 218 SIGN
101400.10 Exterior Signage101400.10 Exterior Signage 75 75 24-Dec-20 13-Apr-21 273
SP-1980 Submittal Prep - 101400.10 Exterior Signage 15 15 0% 24-Dec-20 15-Jan-21 273 SIGN
SR-2700 Submittal Review/Approve - 101400.10 Exterior Signage 15 15 0% 19-Jan-21 08-Feb-21 273 OWN
PR-3580 Procure/Deliver - 101400.10 Exterior Signage 45 45 0% 09-Feb-21 13-Apr-21 273 SIGN
101400.20 Interior Signage101400.20 Interior Signage 75 75 24-Dec-20 13-Apr-21 241
SP-1990 Submittal Prep - 101400.20 Interior Signage 15 15 0% 24-Dec-20 15-Jan-21 241 SIGN
SR-2710 Submittal Review/Approve - 101400.20 Interior Signage 15 15 0% 19-Jan-21 08-Feb-21 241 OWN
PR-3590 Procure/Deliver - 101400.20 Interior Signage 45 45 0% 09-Feb-21 13-Apr-21 241 SIGN
Division 11 - EquipmentDivision 11 - Equipment 95 95 24-Dec-20 11-May-21 224
114600 Food Dispensing Equipment114600 Food Dispensing Equipment 20 20 24-Dec-20 25-Jan-21 280
SP-2080 Submittal Prep - 114600 Food Dispensing Equipment 5 5 0% 24-Dec-20 31-Dec-20 280 GC
SR-2800 Submittal Review/Approve - 114600 Food Dispensing Equipment 15 15 0% 04-Jan-21 25-Jan-21 280 OWN
114700 Ice Machines114700 Ice Machines 65 65 24-Dec-20 30-Mar-21 235
SP-2090 Submittal Prep - 114700 Ice Machines 5 5 0% 24-Dec-20 31-Dec-20 235 GC
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Submittal Review/Approve - 092900 Gypsum Board
Procure/Deliver - 092900 Gypsum Board
Submittal Prep - 093010 Tiling
Submittal Review/Approve - 093010 Tiling
Procure/Deliver - 093010 Tiling
Submittal Prep - 095100 Acoustical Ceilings
Submittal Review/Approve - 095100 Acoustical Ceilings
Procure/Deliver - 095100 Acoustical Ceilings
Submittal Prep - 095423 Linear Metal Ceilings
Submittal Review/Approve - 095423 Linear Metal Ceilings
Procure/Deliver - 095423 Linear Metal Ceilings
Submittal Prep - 096500 Resilient Flooring
Submittal Review/Approve - 096500 Resilient Flooring
Procure/Deliver - 096500 Resilient Flooring
Submittal Prep - 096800 Carpeting
Submittal Review/Approve - 096800 Carpeting
Procure/Deliver - 096800 Carpeting
Submittal Prep - 097710 Modular Panel Systems
Submittal Review/Approve - 097710 Modular Panel Systems
Submittal Prep - 099000 Paints and Coatings
Submittal Review/Approve - 099000 Paints and Coatings
Procure/Deliver - 099000 Paints and Coatings
Submittal Prep - 101100 Visual Display Units
Submittal Review/Approve - 101100 Visual Display Units
Procure/Deliver - 101100 Visual Display Units
Submittal Prep - 101400.10 Exterior Signage
Submittal Review/Approve - 101400.10 Exterior Signage
Procure/Deliver - 101400.10 Exterior Signage
Submittal Prep - 101400.20 Interior Signage
Submittal Review/Approve - 101400.20 Interior Signage
Procure/Deliver - 101400.20 Interior Signage
Submittal Prep - 114600 Food Dispensing Equipment
Submittal Review/Approve - 114600 Food Dispensing Equipment
Submittal Prep - 114700 Ice Machines
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 5 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
SR-2810 Submittal Review/Approve - 114700 Ice Machines 15 15 0% 04-Jan-21 25-Jan-21 235 OWN
PR-3690 Procure/Deliver - 114700 Ice Machines 45 45 0% 26-Jan-21 30-Mar-21 235 GC
115300 Labratory Equipment and Fumehoods115300 Labratory Equipment and Fumehoods 95 95 24-Dec-20 11-May-21 224
SP-2100 Submittal Prep - 115300 Laboratory Equipment and Fumehoods 20 20 0% 24-Dec-20 25-Jan-21 224 GC
SR-2820 Submittal Review/Approve - 115300 Laboratory Equipment and Fumehoods 15 15 0% 26-Jan-21 16-Feb-21 224 OWN
PR-3700 Procure/Deliver - 115300 Laboratory Equipment and Fumehoods 60 60 0% 17-Feb-21 11-May-21 224 GC
117000 General Requirements for Medical and Dental Equipment117000 General Requirements for Medical and Dental Equipment 15 15 24-Dec-20 15-Jan-21 285
SR-2830 Submittal Review/Approve - 117000 General Requirements for Medical and Dental Equipment15 15 0% 24-Dec-20 15-Jan-21 285 OWN
117100 Warming Cabinets Sterilizers and Associated Equipment117100 Warming Cabinets Sterilizers and Associated Equipment 95 95 24-Dec-20 11-May-21 212
SP-2120 Submittal Prep - 117100 Warming Cabinets Sterilizers and Associated Equipment20 20 0% 24-Dec-20 25-Jan-21 212 GC
SR-2840 Submittal Review/Approve - 117100 Warming Cabinets Sterilizers and Associated Equipment15 15 0% 26-Jan-21 16-Feb-21 212 OWN
PR-3720 Procure/Deliver - 117100 Warming Cabinets Sterilizers and Associated Equipment60 60 0% 17-Feb-21 11-May-21 212 GC
117213 Medical Equipment Misc117213 Medical Equipment Misc 15 15 24-Dec-20 15-Jan-21 304
SR-2850 Submittal Review/Approve - 117213 Medical Equipment Misc 15 15 0% 24-Dec-20 15-Jan-21 304 OWN
117400 Dental Equipment117400 Dental Equipment 35 35 24-Dec-20 16-Feb-21 265
SP-2140 Submittal Prep - 117400 Dental Equipment 20 20 0% 24-Dec-20 25-Jan-21 265 GC
SR-2860 Submittal Review/Approve - 117400 Dental Equipment 15 15 0% 26-Jan-21 16-Feb-21 265 OWN
Division 12 - FurnishingsDivision 12 - Furnishings 110 110 24-Dec-20 02-Jun-21 197
123570 Healthcare Casework123570 Healthcare Casework 110 110 24-Dec-20 02-Jun-21 197
SP-2150 Submittal Prep - 123570 Healthcare Casework 25 25 0% 24-Dec-20 01-Feb-21 197 GC
SR-2870 Submittal Review/Approve - 123570 Healthcare Casework 15 15 0% 02-Feb-21 23-Feb-21 197 OWN
PR-3750 Procure/Deliver - 123570 Healthcare Casework 70 70 0% 24-Feb-21 02-Jun-21 197 GC
123600 Countertops123600 Countertops 40 40 24-Dec-20 23-Feb-21 267
SP-2160 Submittal Prep - 123600 Countertops 25 25 0% 24-Dec-20 01-Feb-21 267 GC
SR-2880 Submittal Review/Approve - 123600 Countertops 15 15 0% 02-Feb-21 23-Feb-21 267 OWN
Division 13 - Special ConstructionDivision 13 - Special Construction 70 70 24-Dec-20 06-Apr-21 169
132148 Prefrabricated Audiometric Rooms132148 Prefrabricated Audiometric Rooms 70 70 24-Dec-20 06-Apr-21 161
SP-2180 Submittal Prep - 132148 Prefabricated Audiometric Rooms 5 5 0% 24-Dec-20 31-Dec-20 161 GC
SR-2900 Submittal Review/Approve - 132148 Prefabricated Audiometric Rooms 15 15 0% 04-Jan-21 25-Jan-21 161 OWN
PR-3780 Procure/Deliver - 132148 Prefabricated Audiometric Rooms 50 50 0% 26-Jan-21 06-Apr-21 161 GC
134910 X-Ray Shielding134910 X-Ray Shielding 30 30 24-Dec-20 08-Feb-21 209
SP-2190 Submittal Prep - 134910 X-Ray Shielding 15 15 0% 24-Dec-20 15-Jan-21 209 GC
SR-2910 Submittal Review/Approve - 134910 X-Ray Shielding 15 15 0% 19-Jan-21 08-Feb-21 209 OWN
Division 21 - Fire SuppressionDivision 21 - Fire Suppression 140 140 24-Dec-20 15-Jul-21 114
211313.0020 Wet Pipe Sprinkler System Fire Protection211313.0020 Wet Pipe Sprinkler System Fire Protection 140 140 24-Dec-20 15-Jul-21 114
SP-2210 Submittal Prep - 211313.0020 Wet Piping Sprinkler System Fire Protection 20 20 0% 24-Dec-20 25-Jan-21 114 GC
SR-2930 Submittal Review/Approve - 211313.0020 Wet Piping Sprinkler System Fire Protection30 30 0% 26-Jan-21 09-Mar-21 114 OWN
PR-3810 Procure/Deliver - 211313.0020 Wet Piping Sprinkler System Fire Protection 90 90 0% 10-Mar-21 15-Jul-21 114 GC
Division 22 - PlumbingDivision 22 - Plumbing 105 105 24-Dec-20 25-May-21 159
220070 Plumbing Healthcare Facilities220070 Plumbing Healthcare Facilities 105 105 24-Dec-20 25-May-21 137
SP-2220 Submittal Prep - 220070 Plumbing Healthcare Facilities 10 10 0% 24-Dec-20 08-Jan-21 137 PL
SR-2940 Submittal Review/Approve - 220070 Plumbing Healthcare Facilities 15 15 0% 11-Jan-21 01-Feb-21 137 OWN
PR-3820 Procure/Deliver - 220070 Plumbing Healthcare Facilities 80 80 0% 02-Feb-21 25-May-21 137 PL
220548.0020 Mechanical Sounds Vibration and Seismic Control220548.0020 Mechanical Sounds Vibration and Seismic Control 15 15 24-Dec-20 15-Jan-21 217
SR-2950 Submittal Review/Approve - 220548.0020 Mechanical Sounds Vibration and Seismic Control15 15 0% 24-Dec-20 15-Jan-21 217 OWN
223100 Water Softeners Cation-Exchange (Sodium Cycle)223100 Water Softeners Cation-Exchange (Sodium Cycle) 85 85 24-Dec-20 27-Apr-21 178
SP-2240 Submittal Prep - 223100 Water Softeners Cation-Exchange (Sodium Cycle) 10 10 0% 24-Dec-20 08-Jan-21 178 PL
SR-2960 Submittal Review/Approve - 223100 Water Softeners Cation-Exchange (Sodium Cycle)15 15 0% 11-Jan-21 01-Feb-21 178 OWN
PR-3840 Procure/Deliver - 223100 Water Softeners Cation-Exchange (Sodium Cycle) 60 60 0% 02-Feb-21 27-Apr-21 178 PL
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Submittal Review/Approve - 114700 Ice Machines
Procure/Deliver - 114700 Ice Machines
Submittal Prep - 115300 Laboratory Equipment and Fumehoods
Submittal Review/Approve - 115300 Laboratory Equipment and Fumehoods
Procure/Deliver - 115300 Laboratory Equipment and Fumehoods
Submittal Review/Approve - 117000 General Requirements for Medical and Dental Equipment
Submittal Prep - 117100 Warming Cabinets Sterilizers and Associated Equipment
Submittal Review/Approve - 117100 Warming Cabinets Sterilizers and Associated Equipment
Procure/Deliver - 117100 Warming Cabinets Sterilizers and Associated Equipment
Submittal Review/Approve - 117213 Medical Equipment Misc
Submittal Prep - 117400 Dental Equipment
Submittal Review/Approve - 117400 Dental Equipment
Submittal Prep - 123570 Healthcare Casework
Submittal Review/Approve - 123570 Healthcare Casework
Procure/Deliver - 123570 Healthcare Casework
Submittal Prep - 123600 Countertops
Submittal Review/Approve - 123600 Countertops
Submittal Prep - 132148 Prefabricated Audiometric Rooms
Submittal Review/Approve - 132148 Prefabricated Audiometric Rooms
Procure/Deliver - 132148 Prefabricated Audiometric Rooms
Submittal Prep - 134910 X-Ray Shielding
Submittal Review/Approve - 134910 X-Ray Shielding
Submittal Prep - 211313.0020 Wet Piping Sprinkler System Fire Protection
Submittal Review/Approve - 211313.0020 Wet Piping Sprinkler System Fire Protection
Procure/Deliver - 211313.0020 Wet Piping Sprinkler System Fire Protection
Submittal Prep - 220070 Plumbing Healthcare Facilities
Submittal Review/Approve - 220070 Plumbing Healthcare Facilities
Procure/Deliver - 220070 Plumbing Healthcare Facilities
Submittal Review/Approve - 220548.0020 Mechanical Sounds Vibration and Seismic Control
Submittal Prep - 223100 Water Softeners Cation-Exchange (Sodium Cycle)
Submittal Review/Approve - 223100 Water Softeners Cation-Exchange (Sodium Cycle)
Procure/Deliver - 223100 Water Softeners Cation-Exchange (Sodium Cycle)
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 6 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
226070 Gas and Vacuum Systems for Healthcare Facilities226070 Gas and Vacuum Systems for Healthcare Facilities 70 70 24-Dec-20 06-Apr-21 194
SP-2250 Submittal Prep - 226070 Gas and Vacuum Systems for Healthcare Facilities 10 10 0% 24-Dec-20 08-Jan-21 194 PL
SR-2970 Submittal Review/Approve - 226070 Gas and Vacuum Systems for Healthcare Facilities15 15 0% 11-Jan-21 01-Feb-21 194 OWN
PR-3850 Procure/Deliver - 226070 Gas and Vacuum Systems for Healthcare Facilities 45 45 0% 02-Feb-21 06-Apr-21 194 PL
Division 23 - HVACDivision 23 - HVAC 165 165 24-Dec-20 19-Aug-21 136
230000 Air Supply Distribution Ventilation and Exhaust Systems230000 Air Supply Distribution Ventilation and Exhaust Systems 140 140 24-Dec-20 15-Jul-21 24
SP-2260 Submittal Prep - 230000 Air Supply Distribution Ventilation and Exhaust Systems5 5 0% 24-Dec-20 31-Dec-20 24 MECH
SR-2980 Submittal Review/Approve - 230000 Air Supply Distribution Ventilation and Exhaust Systems15 15 0% 04-Jan-21 25-Jan-21 24 OWN
PR-3860 Procure/Deliver - 230000 Air Supply Distribution Ventilation and Exhaust Systems120 120 0% 26-Jan-21 15-Jul-21 24 MECH
230300.0020 Basic Mechanical Materials and Methods230300.0020 Basic Mechanical Materials and Methods 15 15 24-Dec-20 15-Jan-21 179
SR-2990 Submittal Review/Approve - 230300.0020 Basic Mechanical Materials and Methods15 15 0% 24-Dec-20 15-Jan-21 179 OWN
230593 Testing Adjusting and Balancing for HVAC230593 Testing Adjusting and Balancing for HVAC 20 20 24-Dec-20 25-Jan-21 260
SP-2280 Submittal Prep - 230593 Testing Adjust and Balancing for HVAC 5 5 0% 24-Dec-20 31-Dec-20 260 GC
SR-3000 Submittal Review/Approve - 230593 Testing Adjust and Balancing for HVAC 15 15 0% 04-Jan-21 25-Jan-21 260 OWN
230700 Thermal Insulation for Mechanical Systems230700 Thermal Insulation for Mechanical Systems 110 110 24-Dec-20 02-Jun-21 170
SP-2290 Submittal Prep - 230700 Thermal Insulation for Mechanical Systems 5 5 0% 24-Dec-20 31-Dec-20 170 MECH
SR-3010 Submittal Review/Approve - 230700 Thermal Insulation for Mechanical Systems15 15 0% 04-Jan-21 25-Jan-21 170 OWN
PR-3890 Procure/Deliver - 230700 Thermal Insulation for Mechanical Systems 90 90 0% 26-Jan-21 02-Jun-21 170 MECH
230900 Instrumentation and Control for HVAC230900 Instrumentation and Control for HVAC 145 145 24-Dec-20 22-Jul-21 56
SP-2300 Submittal Prep - 230900 Instrumentation and Control for HVAC 50 50 0% 24-Dec-20 09-Mar-21 56 MECH
SR-3020 Submittal Review/Approve - 230900 Instrumentation and Control for HVAC 15 15 0% 10-Mar-21 30-Mar-21 56 OWN
PR-3900 Procure/Deliver - 230900 Instrumentation and Control for HVAC 80 80 0% 31-Mar-21 22-Jul-21 56 MECH
230913 Instrumentation and Control Devices for HVAC230913 Instrumentation and Control Devices for HVAC 165 165 24-Dec-20 19-Aug-21 36
SP-2310 Submittal Prep - 230913 Instrumentation and Control Devices for HVAC 50 50 0% 24-Dec-20 09-Mar-21 36 MECH
SR-3030 Submittal Review/Approve - 230913 Instrumentation and Control Devices for HVAC15 15 0% 10-Mar-21 30-Mar-21 36 OWN
PR-3910 Procure/Deliver - 230913 Instrumentation and Control Devices for HVAC 100 100 0% 31-Mar-21 19-Aug-21 36 MECH
230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems 165 165 24-Dec-20 19-Aug-21 36
SP-2320 Submittal Prep - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems50 50 0% 24-Dec-20 09-Mar-21 36 MECH
SR-3040 Submittal Review/Approve - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems15 15 0% 10-Mar-21 30-Mar-21 36 OWN
PR-3920 Procure/Deliver - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems100 100 0% 31-Mar-21 19-Aug-21 36 MECH
230993 Sequences of Operation for HVAC Control230993 Sequences of Operation for HVAC Control 95 95 24-Dec-20 11-May-21 106
SP-2330 Submittal Prep - 230993 Sequences of Operation for HVAC Control 50 50 0% 24-Dec-20 09-Mar-21 106 MECH
SR-3050 Submittal Review/Approve - 230993 Sequences of Operation for HVAC Control15 15 0% 10-Mar-21 30-Mar-21 106 OWN
PR-3930 Procure/Deliver - 230993 Sequences of Operation for HVAC Control 30 30 0% 31-Mar-21 11-May-21 106 MECH
231125 Facility Gas Piping231125 Facility Gas Piping 35 35 24-Dec-20 16-Feb-21 229
SP-2340 Submittal Prep - 231125 Facility Gas Piping 10 10 0% 24-Dec-20 08-Jan-21 229 PL
SR-3060 Submittal Review/Approve - 231125 Facility Gas Piping 15 15 0% 11-Jan-21 01-Feb-21 229 OWN
PR-3940 Procure/Deliver - 231125 Facility Gas Piping 10 10 0% 02-Feb-21 16-Feb-21 229 PL
232113.0020 Low Temperatures Water (LTW) Heating System232113.0020 Low Temperatures Water (LTW) Heating System 35 35 24-Dec-20 16-Feb-21 225
SP-2350 Submittal Prep - 232113.0020 Low Temperatures Water (LTW) Heating System10 10 0% 24-Dec-20 08-Jan-21 225 MECH
SR-3070 Submittal Review/Approve - 232113.0020 Low Temperatures Water (LTW) Heating System15 15 0% 11-Jan-21 01-Feb-21 225 OWN
PR-3950 Procure/Deliver - 232113.0020 Low Temperatures Water (LTW) Heating System10 10 0% 02-Feb-21 16-Feb-21 225 MECH
232123 Hydronic Pumps232123 Hydronic Pumps 140 140 24-Dec-20 15-Jul-21 120
SP-2360 Submittal Prep - 232123 Hydronic Pumps 5 5 0% 24-Dec-20 31-Dec-20 120 MECH
SR-3080 Submittal Review/Approve - 232123 Hydronic Pumps 15 15 0% 04-Jan-21 25-Jan-21 120 OWN
PR-3960 Procure/Deliver - 232123 Hydronic Pumps 120 120 0% 26-Jan-21 15-Jul-21 120 MECH
232500 Chemical Treatment of Water for Mechanical Systems232500 Chemical Treatment of Water for Mechanical Systems 140 140 24-Dec-20 15-Jul-21 161
SP-2370 Submittal Prep - 232500 Chemical Treatment of Water for Mechanical Systems 5 5 0% 24-Dec-20 31-Dec-20 161 MECH
Oct N D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct
2021 2022
Submittal Prep - 226070 Gas and Vacuum Systems for Healthcare Facilities
Submittal Review/Approve - 226070 Gas and Vacuum Systems for Healthcare Facilities
Procure/Deliver - 226070 Gas and Vacuum Systems for Healthcare Facilities
Submittal Prep - 230000 Air Supply Distribution Ventilation and Exhaust Systems
Submittal Review/Approve - 230000 Air Supply Distribution Ventilation and Exhaust Systems
Procure/Deliver - 230000 Air Supply Distribution Ventilation and Exhaust Systems
Submittal Review/Approve - 230300.0020 Basic Mechanical Materials and Methods
Submittal Prep - 230593 Testing Adjust and Balancing for HVAC
Submittal Review/Approve - 230593 Testing Adjust and Balancing for HVAC
Submittal Prep - 230700 Thermal Insulation for Mechanical Systems
Submittal Review/Approve - 230700 Thermal Insulation for Mechanical Systems
Procure/Deliver - 230700 Thermal Insulation for Mechanical Systems
Submittal Prep - 230900 Instrumentation and Control for HVAC
Submittal Review/Approve - 230900 Instrumentation and Control for HVAC
Procure/Deliver - 230900 Instrumentation and Control for HVAC
Submittal Prep - 230913 Instrumentation and Control Devices for HVAC
Submittal Review/Approve - 230913 Instrumentation and Control Devices for HVAC
Procure/Deliver - 230913 Instrumentation and Control Devices for HVAC
Submittal Prep - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems
Submittal Review/Approve - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems
Procure/Deliver - 230923.02 BACNET Direct Digital Control for HVAC and other Building Control Systems
Submittal Prep - 230993 Sequences of Operation for HVAC Control
Submittal Review/Approve - 230993 Sequences of Operation for HVAC Control
Procure/Deliver - 230993 Sequences of Operation for HVAC Control
Submittal Prep - 231125 Facility Gas Piping
Submittal Review/Approve - 231125 Facility Gas Piping
Procure/Deliver - 231125 Facility Gas Piping
Submittal Prep - 232113.0020 Low Temperatures Water (LTW) Heating System
Submittal Review/Approve - 232113.0020 Low Temperatures Water (LTW) Heating System
Procure/Deliver - 232113.0020 Low Temperatures Water (LTW) Heating System
Submittal Prep - 232123 Hydronic Pumps
Submittal Review/Approve - 232123 Hydronic Pumps
Procure/Deliver - 232123 Hydronic Pumps
Submittal Prep - 232500 Chemical Treatment of Water for Mechanical Systems
P-9906 - Ambulatory Care Center Replacement N62473-18-D-5855/20-F-53530 Post Comments
P9066-1.10.4.A TSLD
Data Date: 30-Sep-20
Actual Level of Effort Actual Work Remaining Work C... Page 7 of 32 TASK filter: All Activities
Remaining Duration
Activity % Complete
Start Finish Total Float Responsibility
SR-3090 Submittal Review/Approve - 232500 Chemical Treatment of Water for Mechanical Systems15 15 0% 04-Jan-21 25-Jan-21 161 OWN
PR-3970 Procure/Deliver - 232500 Chemical Treatment of Water for Mechanical Systems120 120 0% 26-Jan-21 15-Jul-21 161 MECH
235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output) 110 110 24-Dec-20 02-Jun-21 150
SP-2380 Submittal Prep - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)5 5 0% 24-Dec-20 31-Dec-20 150 MECH
SR-3100 Submittal Review/Approve - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)15 15 0% 04-Jan-21 25-Jan-21 150 OWN
PR-3980 Procure/Deliver - 235243.0020 Low Pressure Water Heating Boilers (Under 800k BTU/HR Output)90 90 0% 26-Jan-21 02-Jun-21 150 MECH
236410 Water Chillers Vapor Compression Type236410 Water Chillers Vapor Compression Type 110 110 24-Dec-20 02-Jun-21 152
SP-2390 Submittal Prep - 236410 Water Chillers Vapor Compression Type 5 5 0% 24-Dec-20 31-Dec-20 152 MECH
SR-3110 Submittal Review/Approve - 236410 Water Chillers Vapor Compression Type 15 15 0% 04-Jan-21 25-Jan-21 152 OWN
PR-3990 Procure/Deliver - 236410 Water Chillers Vapor Compression Type 90 90 0% 26-Jan-21 02-Jun-21 152 MECH
236426 Chilled Chilled-Hot and Condenser Water Piping Systems236426 Chilled Chilled-Hot and Condenser Water Piping…