21._Attachment_A_-_Pilot_Butte_Construction_Specification.pdf

PDF 847 KB Posted

Attached to
Pilot Butte Substation Stage 04 - Capacitor Bank Federal contract opportunity
Solicitation number
DE-SOL-0008520
Issued by
Department of Energy Western Area Power Administration

About this file

Attachment A - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Pilot Butte Substation Stage 04 - Capacitor Bank, newest first.
File Type Posted
21._IFB_Letter-signed.pdf PDF
21._Attachment_F_-_Bid _Performance _Payment_Bond.pdf PDF
21._Attachment_D_-_DPO.pdf PDF
21._DE-SOL-0008520.pdf PDF
21._Attachment_E_-_Foreign_National_Data_Card.pdf PDF
21._Attachment_B_-_Pilot_Butte_Construction_Drawings.pdf PDF
21._Attachment_C_-_Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

27 May 2015

Attachment A

Pilot Butte Substation, Stage 04 Project Specifications

DE-SOL-0008520

PILOT BUTTE SUBSTATION

STAGE 04

Spec. No. 853

SECTION C

DESCRIPTION/SPECIFICATIONS

WYOMING

SECTION C

DESCRIPTION/SPECIFICATIONS

PILOT BUTTE SUBSTATION STAGE 04

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DECSRIPTION OF WORK

1. Substation Concrete

2. Substation Metal Work

3. Substation Electrical

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1. Commencement and Completion

2. Submittal Approval Time

3. Commencement of Control Work

4. Maximum Available Fault Current

5. Construction Schedule and Outage Restrictions

6. Typical Foundations for Electrical Equipment

E. CONSTRUCTION PROGRAM

1. Submittal Time

2. Format and Detail

F. MATERIAL

1. Points-of-Delivery

G. GEOLOGIC INVESTIGATIONS

H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

I. WATER FOR CONSTRUCTION PURPOSES

J. EXPLOSIVES AND BLASTING

K. SUBMITTALS AND CORESPONDENCE

1. General

2. Submittal Response

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Miscellaneous sitework”

2. Bidding Schedule does not contain separate items

DIVISION 3 – CONCRETE

A. GENERAL

1. Material

2. Test for Potential Reactivity of Sand and Coarse Aggregate

3. Curing

B. DESCRIPTION OF BIDDING SCHEDULE

1. Bidding Schedule item “Concrete foundations”

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL

1. Measurement

B. DECSRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Steel structures, welded (galvanized)”

DIVISION 9 – SUBSTATION – ELECTRICAL

A. GENERAL

1. Bidding Schedule for Government-furnished items

2. Bidding Schedule for items (not furnished by the Government)

3. Associated Support Structures Provided for Each Electrical Equipment Rated Above 7-kV

B. DECSRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item Shunt capacitor bank, 115-kV, 15 MVAR (Government-furnished)”

2. Bidding Schedule item “Horizontal interrupter with disconnect switch and grounding blades, 115-kV, 1200 amps”

3. Bidding Schedule item “Pre-insertion inductors”

4. Bidding Schedule item “Outdoor bus system”

5. Bidding Schedule item “Associated electrical equipment and material”

6. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable”

7. Bidding Schedule items “Furnishing 12/c No. 10 AWG control cable”

8. Bidding Schedule items “Installing 5/c No. 10 AWG control cable”

9. Bidding Schedule items “Installing 12/c No. 10 AWG control cable”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION

1. Environmental Quality Protection

B. SPECIAL REQUIRMENTS

1. Special Requirements

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete Pilot Butte Substation, Stage 04, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western’s Construction Standards, including Standard 1 – General Requirements (September 2013), Standard 2 – Sitework (September 2013), Standard 3 – Concrete (September 2013), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2013), Standard 9 – Substation – Electrical (September 2013), Standard 13 – Environmental Quality Protection (September 2015), Standard 15 – Drawings (September 2013); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

Western’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at http://www.wapa.gov/business/buys.htm.

Western Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DECSRIPTION OF WORK:

Paragraphs “Description of Bid Items” in Divisions – 1, 2, 3, 4, 9, and 13 describe the work to be performed.

The work is located near the city of Riverton, WY as shown on Drawing PB 0015.

The principle components of work include:

1. SUBSTATION CONCRETE:

a. Provide foundations and anchor bolts for substation structures, electrical equipment.

2. SUBSTATION METAL WORK:

a. Provide all galvanized steel structures.

3. SUBSTATION ELECTRICAL:

a. Provide circuit interrupter.

b. Provide pre-insertion inductors for existing interrupter.

c. Install GFE shunt capacitor bank and neutral bus PT’s.

d. Furnish and install electrical equipment per drawings and specifications including but not limited to high voltage bus, grounding system, conduit, insulated cables, and terminal boxes.

e. Provide substation signs.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Providing a Construction Program and Safety and Health Program.

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:

1. COMMENCEMENT AND COMPLETION: Begin work within 30-calendar days after date of receipt of Notice to Proceed, and complete all work within 180-days.

2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 40-calendar days for review of drawings or data submitted for approval.

3. COMMENCEMENT OF CONTROL WORK: Do not perform any outdoor equipment wiring until receipt of Government-furnished wiring diagrams. Western will furnish outdoor wiring and schematic diagrams no later than January 29, 2015.

4. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current in the115-kV area is 2,964 amps and the X/R ratio is 5.1.

b. A minimum of one (1) 1/0 grounds shall be used in the 115-kV area.

c. Protective Ground Leads: Each protective ground lead shall have a permanent identification tag with unique identification number, certified wire size, and test date. Each protective ground lead shall be tested complete with connectors, in accordance with ASTM F 2249. Protective ground leads shall be retested and recertified annually. A protective ground lead without an identification tag to relate it to the annual certification of that protective ground lead shall not be used. No protective ground lead shall be longer than 36-feet, unless approved by Contracting Officer’s Representative (COR). Test results shall be submitted to the COR for approval prior to use of the grounds. When using the DC test method, the Contractor shall submit testing information in the format shown below in the Personal Protective Grounds Test Report. When using the AC test method, the Contractor shall submit testing information in accordance with the test set manufacturers recommendations.

CABLE

ID

CABLE

SIZE

CABLE

CONDITION

CABLE

LENGTH

ASTM

RESISTANCE

(MΩ)

MEASURED

RESISTANCE

(MΩ)

PASS/FAIL

FT IN

Tester’s Signature

Test Temperature ______

Test Date ___________________

5. CONSTRUCTION SCHEDULE AND OUTAGE RESTRICTIONS: In addition to the restrictions listed in the standard specifications, the following outage restrictions shall apply:

a. No concurrent main and transfer bus outages.

b. The Contractor shall not work more than 60-hours in 1-calendar week, unless prior approval from the COR.

6. TYPICAL FOUNDATIONS FOR ELECTRICAL EQUIPMENT: Typical foundations are shown on Drawings PB 2300 and PB 2301. Western will design these foundations after receipt of informational drawings and data, from the equipment manufacturer. Western will forward the revised construction drawings for these foundations no later than 45-days prior to the “NLT” delivery date listed in the, “Material” section. If the “NLT” delivery date is adjusted by Western, forwarding of revised foundation construction drawings will be automatically adjusted in a like manner.

E. CONSTRUCTION PROGRAM:

1. SUBMITTAL TIME: Submit a Construction Program to the COR within 45-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by Western as listed below:

ITEM

ESTIMATED

WEIGHT

(LBS)

ESTIMATED

DELIVERY

DATE

1. One (1) 3-phase, shunt capacitor bank, 115-kV

3,900 ea (per phase)

NST 01-15-16

NLT 02-12-16

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY: The shunt capacitor bank furnished by Western will be delivered to the Pilot Butte Substation, Fremont County, WY. The equipment supplier is responsible for unloading.

G. GEOLOGIC INVESTIGATIONS:

Geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.

Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant.

Western does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.

The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the worksite.

H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Electric power up to a maximum of approximately 10-kVA for construction purposes will be available without cost. Source of supply is located in the receptacles throughout the substation. The Contractor may furnish power for his operations by other means. Power made available by Western will be delivered as single-phase, 60 Hz, AC, at approximately 120-240 V. Coordinate with the COR for establishing electric power service.

I. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.

J. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

K. SUBMITTALS AND CORESPONDENCE:

1. GENERAL: The Contractor shall transmit all project correspondence and submittals as specified in Western’s Construction Standards and this Project Specification as follows:

a. Email to RMR-J5600-CS@wapa.gov with the following attachments:

(1) Cover letter (.docx, .pdf) containing:

(a) Western contract number DE-WA000xxxx.

(b) Project Title.

(c) Bidding Schedule Contract Line Item Number (CLIN).

1) Only one (1) CLIN per submittal permitted.

(d) Specification division number and paragraph associated with the CLIN.

(2) Drawings (.pdf or .dwg, AutoCad 2010).

(3) Product data (.pdf) with specific equipment model and details highlighted.

b. Non-electronic (as specified) mailed to the following address:

Western Area Power Administration

ATTN: J5600 COR

P.O. Box 3700

Loveland, CO 80539-3003

2. SUBMITTAL RESPONSE: Western will return submittal responses via email. The email may include, but is not limited to:

a. Submitted item status, “Approved” or “Not Approved”.

b. Comments or recommendations.

c. Conditional approval.

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Miscellaneous sitework” includes the following:

a. Replacing and protecting existing gravel surfacing.

b. Providing a soil-applied herbicide where gravel surfacing is disturbed.

2. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:

a. Excavations for foundations, structures.

b. Placing and compacting earth material and backfill.

c. Providing gravelfills under concrete foundations as shown on the Drawings.

d. Disposing of Excavated Material: Material from excavations not suitable or required for earthwork shall be disposed in accordance with Division 13.

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

a. Cement: Type IIA cement.

b. Compressive Strength: 4000 psi at 28-days for substation concrete.

c. Water-Cement Ratio: Net water-cement ratio, exclusive of water absorbed by the aggregates, shall not exceed 0.45 by weight.

d. Type A and D water-reducing and retarding admixtures may be used if approved by the

COR.

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform test for each source used. Perform tests for potential reactivity for the sand and coarse aggregate to be used by the Contractor. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source will be obtained by the Contractor.

3. CURING: Exposed, formed surfaces of concrete foundations shall be cured with water, resin-base curing compound without fugitive dye, or by covering with polyethylene film.

B. DESCRIPTION OF BIDDING SCHEDULE:

1. Bidding Schedule item “Concrete foundations” includes the following:

a. Earthwork, formwork, reinforcement, material used in concrete anchor bolts, curing, finishing, joints, and other related work and material needed to complete the concrete construction.

b. Concrete foundations for steel structures.

c. Concrete foundations for electrical equipment.

d. Casing auger excavations, if required.

Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing PB 2002. The concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing.

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL:

1. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “AISC Code of Standard Practice for Steel Buildings and Bridges”, except that weights for nonrectangular shapes and plates are to be based on actual detailed dimensions.

B. DECSRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:

a. Two (2) Bus Pole – Type III.*

b. Four (4) Tee Poles – Type I.*

c. One (1) 45-feet Ground Mast – Type I.

d. Two (2) – Type III Switch Operating Platforms, including grating.*

*Denotes structures requiring approval drawings.

The above material including connection bolts, nuts, washers, and lock nuts shall be galvanized.

DIVISION 9 – SUBSTATION – ELECTRICAL

A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES”

Standard Equipment Specifications, as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications and standards as applicable.

Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum ........................................................................................... +40C

Maximum 24-Hour Average .............................................................. +30C

Minimum ............................................................................................. -40C

Elevation:

Above Mean Sea Level .............................................................. 5,475 Feet

*ASCE-7 Wind Load:

Minimum Basic Wind Speed .......................................................... 90 MPH Importance Factor ................................................................................ 1.15

*IEEE Seismic Qualification ............................................................................ Low

*Wind and seismic loads are nonsimultaneous.

1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:

a. Unless otherwise indicated, unloading and inspecting Government-furnished items.

b. Installing Government-furnished items as shown on drawings.

c. Furnishing equipment and material not furnished by Western.

2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the

Contractor and shall include the following:

a. Providing (furnishing and installing) bidding schedule items.

b. Furnishing equipment and material not furnished by Western.

c. Installing bidding schedule items as shown on drawings.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel. If tubular steel supports are furnished, they shall be galvanized internally and externally.

B. DECSRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item Shunt capacitor bank, 115-kV, 15 MVAR (Government-furnished)” includes support structures.

DESIGNATION PY7B

Manufacturer TBD

Voltage Rating (kV) 115

Rating (kVAR) 15,000

Estimated Total Weight (LBS) 11,700

The equipment supplier is responsible for unloading the shunt capacitors in location designated by COR.

a. The spare parts furnished by the capacitor bank supplier should include, but not be limited to, the following:

(1) A minimum of 20 percent spare fuses of each type shall be furnished for the capacitor bank. These fuses shall be identical to those used on the individual capacitor units supplied with the equipment.

(2) A minimum of 10 percent spare individual capacitor units of each type furnished for the capacitor bank shall be supplied. The spare units shall be suitable for substitution in any rack.

(3) A minimum of two (2) insulators of each type furnished for the capacitor bank equipment shall be furnished.

2. Bidding Schedule item “Horizontal interrupter with disconnect switch and grounding blades, 115-kV, 1200 amps” includes providing interrupter in accordance with WAPA ES 8.1 Equipment Standard and providing associated support structure:

DESIGNATION YY7D

System Nominal Voltage (Rating) (kV) 115

Rated Maximum Voltage (kV) 123

Basic Impulse Insulation Level (kV) 550

Continuous Current Rating (Amps) 1200

Fault Interrupting current (3s) (Amps) 38,000

Minimum Phase Spacing 5’-6”

Grounding Blades Yes

Preinsertion inductors Yes

a. Interrupters, including associated support structure, shall be qualified to operate under service conditions specified in paragraph A. General and as follows:

*IEEE 693 Seismic Qualification:

Performance Level ....................................................... Qualification Method

*Wind loads per paragraph A. General and seismic loads are nonsimultaneous.

b. Interrupter shall be outdoor, 3-pole, single-throw, group-operated horizontal interrupter in series with an integral vertical-break disconnect switch.

c. Interrupter shall be equipped with 3-pole, manually group-operated grounding switch on load (capacitor bank) side of interrupter for maintenance purposes. The grounding blades shall have the option to be decoupled and locked.

d. Interrupter shall be capable of switching and protecting a single bank of 15 MVAR shunt capacitors and shall be provided with pre-insertion inductors as follows:

PARAMETER RATING BASIS

Reactance 0.30 800 μH at 60 Hz

Voltage drop 15.6 Volts 52 amps*0.3

System voltage 121-kV 105% of 115-kV

Continuous current 52 amps 118% of 8,750 KVAR capacitor current

Mechanical short circuit current 6,500 amps

2.17 times short-circuit current ref C57-16 table 8X/R = 4.9

Thermal short circuit current 3,000 amps maximum bus fault

Frequency 60 Hz

BIL 550-kV standard at 115-kV

3. Bidding Schedule item “Pre-insertion inductors” includes providing pre-insertion inductors for existing interrupter YY7C in accordance with WAPA ES 8.1 Equipment Standard and removing existing YY7C pre-insertion resistors:

PARAMETER RATING BASIS

Reactance 0.30 800 μH at 60 Hz

Voltage drop 15.6 Volts 52 amps*0.3

System voltage 121-kV 105% of 115-kV

Continuous current 52 amps 118% of 8,750 KVAR capacitor current

Mechanical short circuit current 6,500 amps

2.17 times short-circuit current ref C57-16 table 8X/R = 4.9

Thermal short circuit current 3,000 amps maximum bus fault

Frequency 60 Hz

BIL 550-kV standard at 115-kV

4. Bidding Schedule item “Outdoor bus system” includes providing material and services required to expand the jumper and rigid bus installations. Unless otherwise specified on the drawings, splices, elbows, pad type terminal connectors, and other fittings used on rigid or cable buses shall be compression type (DMC Power Bus and Cable Connectors and Swage System, AFL Swage system, or equal). Informational drawings and data are required for the insulators only.

5. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material, and services required to expand as necessary the following substation installations as shown on the Drawings:

a. Electrical Conduit System: Electrical conduit system including embedded and exposed conduit as shown in drawings. All conduits shall have sealing compound installed at both ends.

b. Grounding System: Includes providing material and services required to complete the substation grounding system in the area of new construction. Due to the ongoing copper theft problems, all new exposed ground wire shall be copper clad steel. NOTE: That the included drawings and standards and have not been revised to show this new requirement. Unless otherwise specified on the Drawings, splices, crosses, tees, and other fittings used on grounding system may be compression type (DMC Power Swage system, AFL Swage system, or equal). Informational drawings and data are not required for this item.

c. Insulated Conductors: Insulated conductors and cables except 5/C and 12/c No. 10 AWG control cable.

d. Terminal Boxes: Terminal boxes’ internal components arrangements shown on Drawings 31 1085 and 31 1086 are typical.

e. Lighting Units: Material for the lighting units shall include lamps, ballasts, fixture wire, fittings, mounting devices, and other accessories required to complete the installation.

Material shall conform to UL standards and to the following:

(1) For Bracket Mounting: General electric-type floodlight catalog No.

PF4S2450A1(7X6)DBL, or equal, 400-W high-pressure sodium lamp connected for operation at 120 V.

(2) Fixture Wire: Single conductor copper, No 14 AWG standard, Type SF-2 silicon rubber insulated, 600 V.

(3) Waterproof junction box or conduit body.

f. Phase Identification Signs (31 1000):

(1) One (1) on each phase at both ends of tee poles, and on each phase of an instrument transformer or single-phase transformer:

(a) Phase A – (3) required.

(b) Phase B – (3) required.

(c) Phase C – (3) required.

g. Equipment Identification Signs (31 1000): Lettering on the signs shall be as follows:

(1) SHUNT CAPACITOR BANK

PB 774

INTERRUPTER/SW YY7D

(2) SHUNT CAPACITOR BANK

PB 780

GND SW ZY7B 115KV

(3) SHUNT CAPACITOR BANK

PY7B1

115KV

(4) SHUNT CAPACITOR BANK

PY7B2

(5) SHUNT CAPACITOR BANK

PY7B3

(6) SHUNT CAPACITOR BANK

VY7B1

VOLTAGE TRANSFORMER

(7) SHUNT CAPACITOR BANK

VY7B2

(8) SHUNT CAPACITOR BANK

VY7B3

(9) SHUNT CAP VT

EY7B

TERMINAL BOX

6. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable” include furnishing 5/c

No. 10 AWG control cable. The Contractor to shall leave 60-feet 0-inches coil of 5/c No. 10 AWG control cable at cable entrance into building. Western crews will terminate cables in control service building.

7. Bidding Schedule items “Furnishing 12/c No. 10 AWG control cable” include furnishing

12/c No. 10 AWG control cable. The Contractor to shall leave 60-feet 0-inches coil of 12/c No. 10 AWG control cable at cable entrance into building. Western crews will terminate cables in control service building.

8. Bidding Schedule items “Installing 5/c No. 10 AWG control cable” include 5/c No. 10 AWG control cable.

9. Bidding Schedule items “Installing 12/c No. 10 AWG control cable” include 12/c No. 10 AWG control cable.

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION:

1. ENVIRONMENTAL QUALITY PROTECTION: The Bidding Schedule does not contain separate items for the following. Include these items in the applicable Bidding Schedule items.

a. Environmental Requirements (See Section 13.3 of Standard).

b. Landscape Preservation (See Section 13.4 of Standard).

c. Preservation of Cultural Resources (See Section 13.5 of Standard).

d. Noxious Weed Control (See Section 13.6 of Standard).

e. Recycled Material Quantities (See Section 13.7 of Standard).

f. Use of Products Containing Recovered Materials (See Section 13.8 of Standard).

g. Disposal of Waste Material (See Section 13.9 of Standard).

h. Contractor’s Liability for Regulated Material Incidents (See Section 13.10 of Standard).

i. Pollutant Spill Prevention, Notification, and Cleanup (See Section 13.11 of Standard).

During oil deliveries for the transformer, the oil supply tanker must be kept in a location at the site that provides for secondary containment in case of accidental spills. Secondary containment shall be provided by the Contractor and may be in the form of placing temporary booms or dirt berms around the vehicle to ensure spills are controlled.

j. Pesticides (See Section 13.12 of Standard).

k. Prevention of Air Pollution (See Section 13.14 of Standard).

l. Prevention of Water Pollution (See Section 13.17 of Standard).

m. Testing, Draining, Removal, and Disposal of Oil-Filled Electrical Equipment (See

Section 13.18 of Standard).

n. Removal of Oil-Contaminated Material (See Section 13.19 of Standard).

o. Conservation of Biological Resources (See Section 13.20 of Standard).

B. SPECIAL REQUIRMENTS:

1. The following special requirements must be observed for the Pilot Butte Substation Capacitor Bank construction project.

a. All work to be confined within the existing fenced perimeter of the substation.

b. This substation is subject to a Spill Prevention, Control and Countermeasure (SPCC) plan.

c. There is no mineral oil contained in the new equipment. The circuit switch will contain sulfur hexafluoride (SF6) insulation.

Message from the Administrator

At Western, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to Western. In performing work for Western, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

Safety procedures or common sense must be applied by each

Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure Western is a safe place to work.

Mark A. Gabriel

Administrator

PB DIV_01 General Requirements
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. SUBSTATION CONCRETE:
2. SUBSTATION METAL WORK:
3. SUBSTATION ELECTRICAL:
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT AND COMPLETION: Begin work within 30-calendar days after date of receipt of Notice to Proceed, and complete all work within 270-days.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 14 Change where less than 40-days review time is applicable calendar days for review of drawings or data submitted for approval.
3. COMMENCEMENT OF CONTROL WORK: Do not perform any control board or outdoor equipment wiring until receipt of Government-furnished wiring diagrams. Western will furnish outdoor and indoor wiring and schematic diagrams no later than 2-weeks after sw...
4. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized to carry the maximum available fault current in accordance with the Standard 1 – General Requirements, Section 1.4 “Safety and H...
5. CONSTRUCTION SCHEDULE AND OUTAGE RESTRICTIONS:
6. TYPICAL FOUNDATION FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT: Typical foundation is shown in drawing PD 2301. Western will design this foundation after receipt informational drawings and data, from the equipment manufacturer. Western will fo...
7. TYPICAL FOUNDATION FOR CONTRACTOR-FURNISHED ELECTRICAL EQUIPMENT: Typical foundation is shown in drawing PD 2300. Western will design this foundation after receipt informational drawings and data, from the equipment manufacturer. Western will fo...
E. CONSTRUCTION PROGRAM:
1. SUBMITTAL TIME: Submit a Construction Program to the COR within 45-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by Western as listed below:
1. POINTS-OF-DELIVERY: The shunt capacitor bank furnished by Western will be delivered to the Pilot Butte Substation, Fremont County, WY. The equipment supplier is responsible for unloading.
G. GEOLOGIC INVESTIGATIONS:
H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
I. WATER FOR CONSTRUCTION PURPOSES:
J. EXPLOSIVES AND BLASTING:
K. A. SUBMITTALS:
1. 1. GENERAL:
2. The Contractor shall transmit submittals as specified in Western’s Construction Standards and this Project Specification as follows:
1) Only one (1) CLIN per submittal permitted.

3. SUBMITTAL RESPONSE: Western will return submittal responses via email. The email may include, but is not limited to:

PB DIV_02,03, 04 SubCivil
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
A. GENERAL:
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
A. GENERAL:
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
PB DIV_09 Substation Electrical
A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES” standard equipment specifications, as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL and Federal specifications ...
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS: