D_SF1449_M6700120Q1077.pdf

PDF 412 KB Posted

Attached to
Vertical Knee Milling Machines Federal contract opportunity
Solicitation number
M6700120Q1077
Issued by
United States Marine Corps

View the file

Other files for this federal contract opportunity

Other files attached to Vertical Knee Milling Machines, newest first.
File Type Posted
A1_Attachment B_Contractor Performance Requirements.pdf PDF
A1_Attachment A_FRC East Drawing PE-21893.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

M6700120Q1077 23-Jun-2020

b. TELEPHONE NUMBER

252-466-5044

8. OFFER DUE DATE/LOCAL TIME

12:00 PM 23 Jul 2020

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

M670019. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

JENNIFER R. BURBAGE

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

N6592320SUYZ6KE

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

M67001MARINE CORPS FIELD CONTRACTING SYS

ATTN: JENNIFER BURBAGE

PSC BOX 8018

BLDG 159, MCAS

CHERRY POINT NC 28533-0018

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE N65923 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

N65923

GEORGE GRIFFIN

FLEET READINESS CENTER EAST DLA

BEACHY RD. BUILDING 148, BAY C

CHERRY POINT NC 28533-5040

TEL: (252)464-8966 FAX:

(252)466-8492FAX:

TEL: (252)466-5044 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

333519

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF68

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

M6700120Q1077

Section SF 1449 - CONTINUATION SHEET

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 4 Each Manual Vertical Knee Milling Machine

FFP

Manual Vertical Knee Milling Machines with articulating heads and 3-axis Acu- Rite digital readouts with accessories, tooling, and Vidmar cabinet in accordance with the Purchase Description for Fleet Readiness Center East aboard Marine Corps Air Station Cherry Point, NC.

Location: Building 133 - Qty 1 Location: Building 137 - Qty 2 Location: Building 4225 - Qty 1 NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

MILSTRIP: N00D18920RX00442

MFR PART NR: Manual Vertical Knee Mill

PURCHASE REQUEST NUMBER: N6592320SUYZ6KE

PSC CD: 3417

NET AMT

0002 1 Each Manual Vertical Knee Mill Machine

FFP

Manual Vertical Knee Mill Machine with articulating heads and 3-axis Acu-Rite digital readouts with accessories, tooling, and Vidmar cabinet in accordance with the Purchase Description for Marine Corps Air Station Beaufort, SC.

Location: Building 594 - Qty 1 NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

MILSTRIP: N00D18920RX00442

MFR PART NR: Manual Vertical Knee Mill

0003 1 Each Removal, Installation, Training

FFP

Removal of Old Machines in accordance with the Purchase Description.

Installation, Training, & Technical Data Rights of the new Vertical Knee Milling Machines in accordance with the Purchase Description.

Location: Building 133 - Qty 1 - MCAS Cherry Point, NC Location: Building 137 - Qty 2 - MCAS Cherry Point, NC Location: Building 4225 - Qty 1 - MCAS Cherry Point, NC Location: Building 594 - Qty 1 - MCAS Beaufort, SC FOB: Destination

MILSTRIP: N00D18920RX00442

MFR PART NR: Vertical Knee Mill Machines

0004 1 Each Freight of Milling Machines

FFP

Freight of Vertical Knee Milling Machines in accordance with the Purchase Description.

Location: Building 133 - Qty 1 - MCAS Cherry Point, NC Location: Building 137 - Qty 2 - MCAS Cherry Point, NC Location: Building 4225 - Qty 1 - MCAS Cherry Point, NC Location: Building 594 - Qty 1 - MCAS Beaufort, SC

THE FREIGHT CHARGES ARE AN ESTIMATED AMOUNT AND SHALL BE

SHOWN ON THE SAME INVOICE AS SUPPLIES ARE BILLED, BUT AS A

SEPERATE ITEM. THE AMOUNT BILLED FOR FREIGHT SHOULD BE

EQUAL TO THE ACTUAL AMOUNT PAID BY THE CONTRACTOR. ANY

EXCESS CHARGES WILL NOT BE PAID. IF THE FREIGHT COSTS

EXCEED $100.00, A FREIGHT BILL MUST ACCOMPANY THE INVOICE.

FOB: Destination

MILSTRIP: N00D18920RX00442

MFR PART NR: Vertical Knee Milling Machines

PURCHASE DESCRIPTION

PURCHASE DESCRIPTION FOR THE ACQUISITION OF FIVE

(5) MANUAL VERTICAL KNEE MILLS

1.0 SCOPE. The content of this purchase description describes the minimum requirements of the Government for five (5) manual Vertical Knee Mill Machines to include articulating heads and 3-Axis Acu-Rite digital readouts. This purchase description also includes the minimum requirements for technical data, tooling and accessories, additional equipment, delivery, unloading and rigging, installation, testing, and training. This requirement is for Four (4) Vertical Knee Mill Machines to be delivered and installed at Buildings (1) 133, (2)137, (1) 4225 Fleet Readiness Center East (FRCE) at Marine Corps Air Station (MCAS) Cherry Point, N.C.

and one (1) machine will be delivered and installed at satellite location at MCAS Beaufort, S.C Building 594.

2.0 APPLICABLE DOCUMENTS

2.1 General. The documents listed in this section are cited in sections 3 and 4 of this specification. This section does not include documents cited in other sections of this specification or recommended for additional information or as examples. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of documents cited in sections 3 and 4 of this specification, whether or not they are listed.

2.2 Government Documents.

2.2.1 Specifications, Standards, and Handbooks. The following specifications, standards, and handbooks form a part of this document to the extent specified herein. Unless otherwise specified, the issues of these documents are those listed in the solicitation or contract

STANDARDS – FEDERAL

FED-STD-H28A: Screw Thread Standards for Federal Service (1994 Ed.)

FED-STD-313E: Material Safety Data, Transportation Data, and Disposal Data for Hazardous Materials Furnished to Government Activities (2014 Ed.)

U.S Department of Labor, Occupational Safety and Health Administration (OSHA)

29 CFR 1910: General Industry, OSHA Safety and Health Standards (2016 Ed.)

(Application for copies should be addressed to the OSHA Publications Superintendent of Documents P.O. Box 37535 Washington, D.C. 20013-7535)

Environmental Protection Agency (EPA)

40 CFR 761: Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions (2016 Ed.)

(Application for copies should be addressed to the EPA Ariel Rios Building 1200 Pennsylvania Avenue, N.W. Washington, DC 20460)

U.S. NAVY

OPNAV 5100.23G w/change 1: Navy Safety and Occupational Health Program Manual (2011 Ed.)

(Application for copies of the OPNAVINST should be addressed to Office of the Chief of Naval Operations, The Pentagon, Washington, DC 20350-2000 or to Commander, Naval Safety Center 375 A Street Norfolk, VA 23511 or on the internet at http://www.public.navy.mil/navsafecen)

NAVAL FACILITIES ENGINEERING COMMAND

NAV P-307 w/Change 3: Management of Weight Handling Equipment (June 2012 Rev.)

(Copies available online at https://portal.navfac.navy.mil/portal/page/portal/docs/doc_store_pub/p- 307%20december%202009.pdf or from Naval Inventory Control Point, ATTN: NAVICP 03334 Room 3200, 700 Robbins Avenue, Philadelphia, PA 19111-5098)

UNIFIED FACILITIES CRITERIA (UFC)

UFC 1-200-01w/Change 3: General Building Requirements (2013 Ed.)

(Copies can be acquired at https://assist.daps.dla.mil/quicksearch)

US ARMY CORPS OF ENGINEERS (USACE)

COE EM 385-1-1: Safety and Health Requirements Manual - Incorporated Changes and Errata (2014 Rev.)

(A copy of this instruction can be acquired at http://www.usace.army.mil/publications/eng-manuals/em385-1-1/entire.pdf )

MILITARY STANDARDS

MIL-STD-130N w/Change 1: Identification Marking of U.S. Military Property (2012 Ed.) Item Unique Identification Marking (IUID)

MIL-STD-1472G w/Change 1: Human Engineering (2019 Ed.)

(Application for copies should be addressed to Air Force Product Data Systems Modernization Standards (TMSS) Office, 554 ELSG/SBP, 4375 Chidlaw Road, Bldg. 262, Room S008, Wright- Patterson AFB, OH 45433-5006, Phone (937) 257-0870 or 0853 or https://assist.daps.dla.mil/quicksearch)

2.2.2 Other Government Documents, Drawings, and Publications. The following other Government documents, drawings, and publications form a part of this document to the extent specified herein.

Unless otherwise specified, the issues of these documents are those listed in the solicitation or contract.

LOCAL FACILITY DOCUMENTS

FRCEASTINST 5000.1B – Visitor/Contractor Site Specific Rules and Compliance

FRCEASTINST 5090.1 : Environmental Compliance Manual

FRCEASTINST 10290.1: Tool Control Program (Latest Rev)

FRCEASTINST 10380.1: Electrical Arc Flash Safety Program (Latest Rev)

Attachment A: FRC East Drawing PE-21893 – Machine Layout and Utilities Locations

Attachment B: Contract Performance Requirements

(Applications for these documents should be addressed to the contracting officer)

2.3 Non-Government Documents. The following specifications, standards, and handbooks form a part of this document to the extent specified herein. Unless otherwise specified, the issues of these documents are those listed in the solicitation or contract.

American Gear Manufacturers Association (AGMA)

AGMA ISO 1328-1-B14: Cylindrical Gears - ISO System of Flank Tolerance Classification - Part 1:

Definitions and Allowable Values of Deviations Relevant to Flanks of Gear Teeth (2014 Rev)

(Address application for copies to: 1001 N. Fairfax Street, Suite 500, Alexandria, VA 22314-1587)

American National Standards Institute, Inc. (ANSI)

ANSI B5.1M: T-Slots, their Bolts, Nuts, and Tongues, Revision of ANSI B5.1-1975 (2014 Rev.)

ANSI B11.8: Safety Requirements for Manual Milling, Drilling and Boring Machines with or without Automatic Control (2001, R 2012)

(Address application for copies to the American National Standards Institute, 11 West 42nd Street, New York, NY 10036)

American Society of Mechanical Engineers (ASME)

ASME A13.1: Scheme for the Identification of Piping Systems (2015 Ed.)

ASME Y14.100-2013: Engineering Drawing Practices (2013 Rev.)

(Applications for copies should be addressed to ASME International Three Park Avenue New York, NY 10016-5990 or www.asme.org)

International Organization for Standardization (ISO)

ISO 4413: Hydraulic fluid power-General rules and safety requirements for systems and their components (2010 Ed.)

ISO 4414: Pneumatic power-General rules and safety requirements for systems and their components (2010 Ed.)

ISO 18938: Imaging materials - Optical discs - Care and handling for extended storage - Second Edition (2014 Ed.)

(Application for copies should be addressed to the International Organization for Standardization (ISO) 1 rue de Varembé, Casepostale56, CH211Geneva 20, Switzerland)

National Electrical Manufacturers Association (NEMA)

NEMA 250: Enclosures for Electrical Equipment (1000 Volts Maximum) (2014 Ed.)

NEMA ICS 1: Industrial Control and Systems General Requirements (2015 Rev.)

NEMA ICS 6: Industrial Control and Systems: Enclosures (2011 Rev.)

NEMA MG 1: Motors and Generators (2016 Ed.)

NEMA Z535.4: Product Safety Signs and Labels (2011 Ed.)

(Application for copies should be addressed to the National Electrical Manufacturers Association, 1300 N 17th Street, Rosslyn, VA 22209)

National Fire Protection Association (NFPA)

NFPA 70: National Electrical Code (2017 Ed.)

NFPA 79: Electrical Standard for Industrial Machinery (2015 Ed.)

(Applications for copies should be addressed to the National Fire Protection Association, ATTN: Support Services, 11 Tracy Drive, Avon, MA 02322)

2.4 Order of Precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulation unless a specific exemption has been obtained.

3.0 REQUIREMENTS

3.1 Vertical Knee Milling Machine Specifications.

3.1.1 General.

3.1.1.1 The item offered shall be new and a current commercially available model. A current model is defined as the manufacturer’s currently produced model, which, on the date this solicitation is issued, has been designed, engineered, sold or is being offered for sale through advertisements or manufacturers published catalogue or brochures. Products such as a prototype unit, pre-production model, or experimental unit do not qualify as meeting the requirements specified herein.

3.1.1.2 The machine shall include all components, parts, and features necessary to meet the performance requirements specified herein.

3.1.1.3 All parts subject to wear, breakage or distortion shall be accessible for adjustment, replacement, and repair.

3.1.1.4 The government will not consider the purchase of any equipment that is manufactured in part or in whole in a country not identified in DFAR 252.225-7000, Buy American Act. If at any point the government finds parts or equipment made in a country not identified in DFAR 252.225-7000, the equipment shall be removed from the FRC East and the contract will be terminated for default.

3.1.2 Measuring and Indicating Device Graduations. All measuring and indicating devices on the machines shall be graduated in U.S. customary units.

3.1.3 Controls. All electrical, mechanical, hydraulic, and pneumatic operating controls should be located convenient to the operator's work station(s).

3.1.4 Safety and Health Requirements.

3.1.4.1 All machine parts, components, mechanisms, and assemblies furnished on the machines, whether or not specifically required herein, shall comply with all of the requirements of

OSHA 29 CFR 1910.

3.1.4.2 Safety signs and labels on all equipment shall comply with NEMA Z535.4.

3.1.5 Safety Guarding.

3.1.5.1 Covers, guards, or other safety devices shall be provided per ANSI B11.8

3.1.5.2 The safety devices shall not interfere with the operation of the machines.

3.1.5.3 The safety devices shall prevent unintentional contact with the guarded part, and shall be easily removable to facilitate inspection, maintenance, and repair of the parts.

3.1.6 Audible Noise Level.

3.1.6.1 Audible noise emitted by the equipment shall not exceed 84 decibels (dB), measured on the

“A” weighted scale of a standard Type II sound level meter, at the operator's work position or any point at a distance of three (3) feet from the equipment.

3.1.6.2 Noise generated by the work piece shall be excluded in determining compliance of the equipment with the 84 dB requirements.

3.1.7 Mercury Restriction. The machines shall not contain mercury or mercury compounds nor be exposed to free mercury during manufacture with the exception of fluorescent lighting where required.

3.1.8 Asbestos Restriction. Asbestos and materials containing asbestos shall not be used on or in the machine.

3.1.9 Lead. Lead and materials containing lead shall not be used on or in the machines with the exception to radiation cladding and lead solder in circuits.

3.1.10 Use of Polychlorinated Biphenyl (PCB). The use of polychlorinated biphenyl (PCB) on or in the equipment is prohibited. The machines shall be considered PCB free providing certification to be verified containing less than five (5) parts per million (<5ppm) in accordance with 40 CFR part 761.

3.1.11 Environmental Protection.

3.1.11.1 Under the operating, service, transportation, and storage conditions described herein, the machines shall not emit materials hazardous to the ecological system as prohibited by Federal, state, or local statutes in effect at the point of installation.

3.1.11.2 FRCEASTINST 5090.1G, Environmental Compliance regulations, shall be included with regards to equipment and installation of this specification.

3.1.11.3 Any violation of regulations shall fall on the sole responsibility of the contractor; the government will monitor the installation of equipment.

3.1.12 Lubrication.

3.1.12.1 Means shall be provided to ensure adequate lubrication (oil, grease, coolant, etc.) for all moving parts.

3.1.12.2 Recirculating lubrication systems shall include a filter that is cleanable or replaceable.

3.1.12.3 Each lubricant reservoir shall have at least a 24-hour capacity.

3.1.12.4 Means shall be provided to indicate a low lubrication condition.

3.1.12.5 When a low lubrication condition occurs, the machine shall complete the current operation and come to a complete stop.

3.1.12.6 Machine manuals shall indicate how to refill the lubrication reservoirs.

3.1.12.7 All oil holes, grease fittings, and filler caps shall be easily accessible.

3.1.13 Replacement Parts. Replacement parts are those that are subject to wear or failure such as gears, bearings, shafts, feed screws, drive belts, pumps, and seals. Electrical replacement parts include, but are not limited to, motors, relays, fuses, switches, magnetics, pushbuttons, light bulbs, braking mechanisms, and solid-state devices.

3.1.13.1 All parts subject to replacement shall be manufactured to definite dimensions and tolerances.

3.1.13.2 Replacement parts shall be interchangeable without requiring modification.

3.1.13.3 Tooling and accessories normally supplied as standard items shall be considered replacement parts.

3.1.14 Fail-Safe. In accordance with MIL-STD-1472G, paragraph 4.5, a fail-safe design shall be provided in those areas where failure can cause catastrophe through damage to equipment, injury to personnel, or inadvertent operation of critical equipment.

3.1.15 Human Engineering.

3.1.15.1 Criterion for selecting off-the-shelf commercial or Government equipment shall include the degree to which the equipment conforms to MIL-STD-1472G.

3.1.15.2 Where off-the-shelf equipment requires modification in order to interface with other equipment, the modification shall be designed to comply with the criteria in MIL-STD- 1472G.

3.1.15.3 Redesign of off-the-shelf equipment shall have the approval of the procuring activity.

3.1.16 Castings and Forgings.

3.1.16.1 All castings and forgings shall be free of defects, scale, and mismatching.

3.1.16.2 No processes such as welding, peening, plugging, filling with solder or paste shall be used for reclaiming any defective part.

3.1.16.3 Castings shall be Meehanite® for superior rigidity and wear resistance.

3.1.17 Fastening Devices.

3.1.17.1 All screws, pins, bolts, and other fasteners shall be installed to prevent unintentional loosening.

3.1.17.2 Fastening devices subject to removal or adjustment shall not be permanently installed.

3.1.18 Threads. All threaded parts used on the machines related attachments and accessories shall conform to FED-STD-H28A and the applicable "Detailed Standard" section referenced therein.

3.1.19 Gears.

3.1.19.1 All gears of axis drive trains shall conform to or exceed all provisions of ANSI/AGMA ISO 1328-1-B14.

3.1.19.2 All gears shall be of proper width and size to transmit full-rated torque and horsepower throughout the speed ranges without failure for the expected service life of the machines.

3.1.19.3 Gears in drive trains shall be hardened and ground steel.

3.1.19.4 Working surface hardness shall be not less than 48 Rockwell C.

3.1.20 Surfaces.

3.1.20.1 All surfaces shall be clean and free of harmful or extraneous materials.

3.1.20.2 All edges shall be either rounded or beveled unless sharpness is required to perform a necessary function.

3.1.20.3 The condition and finish of all surfaces shall be in accordance with the manufacturer's commercial practice.

3.1.20.4 The table surface shall be hardened and ground

3.1.21 Welding, Brazing, or Soldering.

3.1.21.1 Welding, brazing, or soldering shall be employed only where specified in the original design.

3.1.21.2 Welding, brazing, or soldering shall not be employed as a repair measure for any defective part.

3.1.22 Painting.

3.1.22.1 The machines shall be painted in accordance with the manufacturer’s commercial practice.

3.1.22.2 All paint shall be of the lead free type.

3.1.23 Workmanship.

3.1.23.1 The machines shall be constructed of parts that are new, without defects, and free of repairs.

3.1.23.2 The structure shall withstand all forces encountered during operation of the machines to the maximum rating and capacity without distortion.

3.1.23.3 Workmanship of the machines shall meet all requirements specified herein

3.1.23.4 Workmanship shall be of a quality equal to that prevailing among manufacturers producing equipment of the type covered by this purchase description.

3.1.24 Warranty. Equipment shall be covered with a one (1) year standard manufacturer’s warranty from time of installation.

3.1.25 Environmental Operating Conditions. The machines shall be capable of operating in a factory environment of 73° ±18° Fahrenheit, atmospheric pressures between 25.5 and 30.5 inches of mercury, and relative humidity of 10% to 95%, without exceeding the designed operating limits of any of its components. Temperature changes are understood to not vary more than three (3) degrees in a one (1) hour period or 10 degrees in 24 hours.

3.2 Components. The machines shall consist of not less than the following components:

3.2.1 Base.

3.2.1.1 The base shall be a stress relieved, heavy duty, ribbed casting or steel weldment having characteristics that minimize both thermal and vibration effects.

3.2.1.2 The base shall provide the strength and size to assure maximum rigidity and support for any load within the rated capacity of the machine.

3.2.1.3 Means shall be provided for accurate, ease of leveling.

3.2.2 Table.

3.2.2.1 The worktable shall be a casting of iron, or iron alloy, internally ribbed and proportioned to support and withstand the maximum capacity work-piece weights and tool thrust loads.

3.2.2.2 The worktable shall be precision fitted to the ways of the saddle and be the compound type, arranged to provide work-piece travel in X and Y axes.

3.2.2.3 The worktable shall be hardened with a ground finish.

3.2.2.4 The worktable ways shall be dovetail type.

3.2.3 Machine Ways.

3.2.3.1 Machines X, Y, and Z ways shall be hardened and ground.

3.2.3.2 The ways shall include one-piece wipers.

3.2.3.3 Movement of the slides on the way surfaces shall be through adjustable preloaded, re-circulating roller bearing cartridges or nonmetallic way liners having a low coefficient of friction, with excellent slip-stick and damping properties.

3.2.3.4 Protection of the machine ways shall be either telescoping or curtain type way covers with one-piece way wipers.

3.2.3.5 Machines X and Y ways shall be coated with Turcite® B.

3.2.3.6 The machine shall include column and knee way covers.

3.2.3.7 Knee ways and column ways shall be square type.

3.2.4 Axes.

3.2.4.1 The X and knee axes of the machines shall be actuated through a close loop, high-gain electrical servo mechanism.

3.2.4.2 Infinitely variable feed drives shall be provided for the X axes.

3.2.4.3 Axes shall be machined to accept way bearings of a precise fit to their respective ways.

3.2.4.4 The way bearings shall be an antifriction type and shall be provided with adjustable gibs, guides, or bearings to maintain and adjust alignment of the table to the ways and prevent causing excessive loading of the feed drive motor.

3.2.4.5 The X-axis shall be the longitudinal axis (Main table moving horizontally left to right as standing at the front of the machine).

3.2.4.6 The Y-axis shall be the transverse axis (Main table moving horizontally, front to back, as standing at the front of the machine).

3.2.4.7 The Z-axis shall be the vertical axis (Spindle moving vertically).

3.2.4.8 Friction in the pre-loaded ball screw and nut assemblies shall not excessively load the feed motors under normal cutting operations for which the machine is designed.

3.2.4.9 A positive means of lubrication shall be provided for the ball screw and nut assemblies.

3.2.4.10 Ball screws and nuts shall be shielded from contaminants and cutting debris by a method of the manufacturer's standard.

3.2.5 Articulating Head.

3.2.5.1 The machines shall have an articulating head for machining and drilling compound angles.

3.2.5.2 Worm gear angular positioning of head shall not be less than two (2) positions.

3.2.6 Ball screws/Leadscrews.

3.2.6.1 X and Y ball screws shall be factory installed with locking mechanisms.

3.2.6.2 Z leadscrew shall be chromed.

3.2.6.3 X and Y ball screws shall be preloaded for backlash compensation.

3.2.6.4 Z leadscrew shall have a double nut for backlash compensation.

3.2.7 Air Powered Draw Bar. The machines shall be installed with a 5/8 – 11 threads per inch air powered drawbar.

3.2.8 Spindle/Quill.

3.2.8.1 The spindle and quill shall meet or exceed size and performance requirements specified in Table 1 and Table 3.

3.2.8.2 The spindle shall be hardened and ground.

3.2.8.3 The spindle shall have a hand operated brake.

3.2.8.4 The Spindle shall have a reversing switch for clockwise and counter clockwise operation.

3.2.8.5 The spindle shall be equipped with ABEC 7 rated CP4 Spindle Bearings.

3.2.8.6 The Quill shall be Chromed and Ground.

3.2.8.7 Manual rapid quill movement shall be lever operated.

3.2.8.8 A hand wheel shall be provided for fine quill feed.

3.2.8.9 The machines quill shall have adjustable automatic feed disengagement for feed in both directions.

3.2.9 Coolant Mist System.

3.2.9.1 A coolant mist system with a switch and flexible segmented coolant nozzles shall be provided.

3.2.9.2 The system shall have means for draining and cleaning as necessary.

3.2.9.3 Means shall be provided to permit the operator to direct and control the amount of coolant mist over the entire work area.

3.2.10 Hydraulic System.

3.2.10.1 Where the design of the machine uses a hydraulic system, the hydraulic system and all components shall conform to ISO 4413.

3.2.10.2 The hydraulic system shall be complete, including all pumps, valves, piping, cylinders, and pressure controls.

3.2.11 Pneumatic System.

3.2.11.1 Where the design of the machine uses a pneumatic system, the pneumatic system and all components shall conform to ISO 4414.

3.2.11.2 The pneumatic system shall be complete, including all pumps, valves, piping, cylinders, and pressure controls.

3.2.11.3 The pneumatic system shall have an airline filter, water trap, and oil mist lubricator as necessary.

3.2.11.4 Air pressure gauges shall be provided to indicate input air pressure in all lines that are downstream from a pressure control device.

3.2.12 Electrical System.

3.2.12.1 The machines and ancillary equipment’s electrical system shall conform to NFPA 79.

3.2.12.2 The electrical system shall be designed for fail-safe operation and shall be insulated, isolated, shielded and grounded for safe operation.

3.2.12.3 The Government will provide power source(s), at location(s) and distance(s) to allotted space, as shown in drawing PE-21893.

3.2.12.4 The machine and ancillary equipment’s electrical system shall be tolerant of fluctuation of ±

10 percent of existing power source.

3.2.12.5 The electrical system shall be complete, including any electrical transformer(s) that may be required to modify the existing source voltage to the proper operating voltage of the machine and ancillary equipment.

3.2.12.6 A properly rated, and fused, single point disconnect device shall be utilized on the machine with means of lockout in the off position only.

3.2.13 Electrical Enclosures.

3.2.13.1 The electrical enclosures shall conform to NEMA ICS 6 standards.

3.2.13.2 The enclosures shall be a NEMA type 12.

3.2.13.3 The enclosures shall provide for ventilation of components.

3.2.13.4 The enclosures shall be designed for an indoor, non-hazardous location.

3.2.13.5 All electrical components shall conform to applicable NEMA ICS 1 standards.

3.2.13.6 The machine shall be provided with interlocks on its electronic cabinet that instantly remove power from the equipment when the door is opened in accordance with NFPA 79.

3.2.14 Arc Flash Protection. The machines enclosures shall be marked for arc flash in accordance with

NFPA 79 Paragraph 16.2.3 “Safety Signs for Electrical Enclosures” for arc flash safety.

3.2.15 Solid-State Components.

3.2.15.1 Electrical devices used to power electrical servo and spindle motors of control voltage delivered to solid-state electrical components shall be solid-state devices.

3.2.15.2 All electrical devices shall handle the electrical load imposed by operation of the machine to its maximum capability.

3.2.15.3 The use of selenium in solid-state components shall be restricted to those devices that protect other solid-state components from voltage surge.

3.2.16 Motors.

3.2.16.1 Motors shall be rated for continuous duty.

3.2.16.2 Alternating-current (AC) motors shall be designed to operate on 60-Hz.

3.2.16.3 Each motor enclosure shall meet the requirements for a drip-proof enclosure.

3.2.16.4 All motors shall meet the requirements of NEMA MG-1.

3.2.16.5 Each motor shall have an identification plate in accordance with paragraph 3.9.3 to identify manufacturer, model number, serial number, voltage, amperage, horsepower, phase, frequency, and frame number.

3.2.16.6 Motor horsepower shall be the manufacturer’s standard or standard optional horsepower as indicated on the manufacturer's design and construction drawing(s).

3.2.17 Work light.

3.2.17.1 A 110-Volt LED work light with three-pronged plug shall be provided.

3.2.17.2 The light shall comply with NFPA 79 requirements, have a protective shield, and provide maximum light to the work area.

3.3 Size and Capacity.

3.3.1 The maximum size of machines and all equipment, including any ancillary equipment, shall be less than the allotted space shown on drawing PE-21893.

3.3.2 The machines shall meet or exceed size and capacity requirements specified in Table 1.

Table 1: Size and Capacity

Characteristic Size/Capacity Table Size ( L x W) 54 inch by 10 inch X-Axis Travel ( Longitudinal ) 40 inch Y-Axis Travel ( Cross ) 15 inch Table to Spindle 4.5 inch to 18.5 inch Quill Diameter 4.125 inch Knee Travel 13.5 inch Ram Travel 21.5 inch No. of T-Slots 3 T-Slot Width 5/8 inch T-Slot Center Distance 2.484 inch Table Capacity 1100 pounds Spindle Taper NMTB40 Spindle Travel 5 inch Head Tilt 90 Degrees Right & Left Spindle Tilt 45 Degrees Inward & Outward

3.4 Accuracy and Alignment. The accuracy and alignment of the machine shall meet or exceed the tolerances specified in Table 2.

Table 2: Accuracy, Alignment, and Repeatability

*R&L is squareness between Z and X axes **P&S is squareness between Z and Y axes

Characteristic Tolerance

Spindle Runout 0.0005 inch Full Travel

Spindle Nose Movement 0.0006 inch Taper Runout 0.001 inch per 12 inch Transversal Traverse of Table R&L* 0.001 inch per 12 inch Parallelism of Table Surface 0.001 inch per 12 inch Parallelism Between T Slot & Longitudinal Movement 0.001 inch per 12 inch Perpendicularity of Table in Longitudinal Movement 0.001 inch per 12 inch Parallelism of Table to Knee R&L* 0.001 inch per 12 inch Parallelism of Table to Knee P&S** 0.001 inch per 12 inch Ram Slide Parallelism with Table Top 0.001 inch per 12 inch

3.5 Performance. The machines performance characteristics shall meet or exceed the values specified in

Table 3.

Table 3: Performance Characteristic Value

Spindle Speeds (Low and High Ranges)

Low Range: 75-750 revolution per minute (rpm)

High Range: 550-4250 revolution per minute (rpm)

Spindle Power 5 horsepower (hp) Quill Feed .0015/.0031/.006 (inch per revolution)

3.6 Standard Tooling and Equipment.

3.6.1 All standard tooling and equipment required for proper operation of each machine (such as special tools needed for drawbar, adjustment of articulated head, and maintenance) shall be furnished.

3.6.2 All standard tooling and equipment required for removal, installation, and setup of recommended spare parts shall be furnished.

3.6.3 A list of standard tooling and equipment shall be provided with proposal.

3.7 Additional Equipment. The following additional equipment shall be provided with each machine.

Detailed information of all additional equipment shall be provided with proposal.

3.7.1 Required Options and Accessories.

3.7.1.1 3-Axis with Spindle 10” X 54” Acu-Rite 300 DRO, installed.

3.7.1.2 Coolant Mist System

3.7.1.3 Metal tray for collection of chips

3.7.1.4 Micrometer depth stop

3.7.1.5 Air Powered Drawbar

3.7.1.6 X, Y Ball Screws I/O Lead Screws

3.7.1.7 110-Volt Auto Lube Pump

3.7.1.8 X, Y Axis Servo Feed

3.7.1.9 AC Rapid Vertical Drive (Knee)

3.7.2 Work Holding Devices.

3.7.2.1 52 Piece Clamping Kit

3.7.2.2 Six Inch Kurt Vise

3.7.2.3 Six Inch Kurt Swivel Base

3.7.2.4 Vise Step Kit 11/16 x 5/8 (set of Two)

3.7.3 Tooling.

3.7.3.1 NMTB40 Milling Chuck Kit w/7 Collets

3.7.3.2 ½” Keyless Drill Chuck

3.7.3.3 1/8” – 5/8” Keyless Drill Chuck

3.7.3.4 Tool Kit, (Drawbar and Articulated head adjustment wrenches) Test and Accuracy Chart

3.7.3.5 NMTB40 taper end mill holder set with the following hole diameters:

a. 3/16 inch

b. 3/8 inch

c. ½ inch

d. 5/8 inch

e. ¾ inch

f. 7/8 inch

g. 1 inch

h. 1-1/4 inch

i. 1-1/2 inch

3.7.4 Mobile Cabinet. Vidmar cabinet, part number RP1441AL, shall be provided with each machine with the following requirements:

a. Wood table top

b. 35-inch counter height

c. 30-inch width

d. 27.75-inch depth

e. Four (4) drawers

f. Heavy duty mobile casters

g. Medium gray in color

3.8 Marking on Instruments, Control Panels, and Plates.

3.8.1 General.

3.8.1.1 All words on plates shall be in the English language.

3.8.1.2 Characters shall be engraved, etched, embossed, or stamped in boldface on a contrasting background.

3.8.1.3 All plates shall be corrosion resistant.

3.8.2 Lubrication Plate.

3.8.2.1 A lubrication plate shall be permanently and securely attached to each machine.

3.8.2.2 The lubrication plate shall contain the following information:

Points of Lubricant Application Servicing Interval Type of Lubricant Viscosity Military or Federal Specification for Each Lubricant (If available) Size and Type of Each Lubricant Filter

3.8.3 Nameplate.

3.8.3.1 A nameplate shall be permanently and securely attached to each machine.

3.8.3.2 If the machine is a special model, the model designation shall include the model number of the basic standard machine and a suffix identified in the manufacturer's permanent records.

3.8.3.3 The nameplate shall contain the following information:

Nomenclature Manufacturer's Name Manufacturer's Model Designation Manufacturer's Serial Number Power Input (Volts, Total Amps, Phase, Frequency) Contract Number Date of Manufacture

3.8.4 Identification Marking of Military Property.

3.8.4.1 An Item Unique Identification Marking (IUID) shall be provided in accordance with MIL- STD-130N and all applicable documents within the standard with Machine Readable Information (MRI) for item identification marking and automatic data capture.

3.8.4.2 The application of Human Readable Information (HRI) shall be used in combination with MRI and free text.

3.8.4.3 At a minimum, the IUID shall contain the information listed in paragraph 3.10.3, Nameplate.

3.9 Technical Data.

3.9.1 General.

3.9.1.1 One (1) hard copies and two (2) electronic copy(s) of technical data shall be provided with each machine at delivery.

3.9.1.2 Each electronic copy shall be provided on a read-only optical disc created and handled in accordance with ISO 18938.

3.9.1.3 All engineering drawings shall be in accordance with ASME Y14.100.

3.9.1.4 Technical data shall contain technical information, specifications, instructions for the operation and maintenance of the machine, consumables and expendables information, and recommended spare parts list.

3.9.1.5 The contractor shall provide a list of all consumables and expendables and recommended spare parts at time of proposal.

3.9.1.6 All original software manuals and registration keys/codes shall be provided, along with original software installation disks.

3.9.1.7 All copies of technical data shall be legible and written in the English language.

3.9.2 Service and Operator Manuals

3.9.2.1 The contractor shall supply factory service and operator manuals for the type and model of the machine being purchased.

3.9.2.2 The manuals shall contain technical information, specifications, instructions for the operation and maintenance of the machine and all associated accessories.

3.9.2.3 The service manuals shall contain the procedures for replacing the parts withing the equipment showing exploded view engineering drawings that show all fasteners with the torque values and part numbers.

3.9.2.4 Procedures shall be included in the service manuals for recalibrating (if required) the part that was replaced and operational checks that ensure proper operation of the replaced part.

3.9.2.5 The manuals shall address diagnositc procedures for isolating and correcting faults.

3.9.2.6 The manuals shall clearly define preventative and predictive maintenance tasks, including oil and vibration analysis, and show recommended intervals of tasks.

3.9.3 Instrument and Calibration Procedures.

3.9.3.1 Calibration procedures and/or tooling requiring operator verification or recalibration as part of a production run or on a daily or periodic basis shall be provided to the Government.

3.9.3.2 The contractor shall provide a list of these items at the time of proposal.

3.9.3.3 All items shall have a certificate of calibration traceable to the National Institute of Standards and Technology (NIST).

3.9.4 Plan of Action and Milestones (POA&M).

3.9.4.1 The contractor shall provide a POA&M to identify contractor performance dates of all major events from contract award to completion of all contract requirements.

3.9.4.2 The initial POA&M shall be delivered within thirty (30) calendar days after contract award for Government review.

3.9.4.3 The Government will review and approve or reject the POA&M within fifteen (15) business days of submission.

3.9.4.4 The Contractor shall re-submit any required changes to the POA&M within five (5) business days for review and approval by the Government.

3.9.4.5 The milestones shall be prepared using a recognized project management technique

(preferably Microsoft Project).

3.9.4.6 The Contractor shall review the POA&M with the Government on a monthly basis.

3.9.4.7 The contractor shall notify the Government prior to making any changes to the POA&M. The

Government will approve all changes to the POA&M in advance.

3.9.4.8 The POA&M shall detail such items as procurement of major hardware, assembly, operational debug, contract quality assurance testing (origin), shipment, installation, final inspection and acceptance, test (destination), and training.

3.9.5 Site Preparation and Installation Plan

3.9.5.1 The contractor shall provide a site preparation and installation plan.

3.9.5.2 The contractor shall field verify all dimensions and site conditions while developing the site preparation and installation plan.

3.9.5.3 As part of the site preparation and installation plan, the contractor shall include facilities preparation instructions including detailed information concerning any equipment that applies a load to a facility structure, wall, or roof.

3.9.5.4 The initial plan shall be provided during Post Award Conference (PAC) for FRC East review.

3.9.5.5 The designated FRC East POC will respond with comments no later than fifteen (15) business days after receiving the initial plan.

3.9.5.6 The Contractor shall submit final site preparation and installation plan no later than thirty

(30) days prior to installation for approval by FRC East.

3.10 All Contractors. Subcontractors shall utilize the FRC East approved site preparation and installation plan for execution of all installation work described herein.

3.10.1 The site preparation and installation plan shall include, but not be limited to:

a. Detailed description of all installation work including exiting equipment disassembly and removal

b. A detailed site layout including position and orientation of new machine with any ancillary and additional equipment

c. General equipment specifications (i.e. size, weight, etc.)

d. Any required structural modifications or additions

e. Utility requirements and location

f. Pertinent compressed air and electrical details

3.10.2 Installation.

3.10.2.1 Contractors who enter the FRC East facility to perform installation work described herein shall comply with FRCEASTINST 5000.1 and FRCEASTINST 5090.1.

3.10.2.2 The Contractor shall submit, to the designated FRC East POC, all Safety Data Sheets (SDS) for any Hazardous material (HM), as defined under 29 CFR 1910.1200, supplied to the FRC East for installation, testing, or operation of installed machine. The Contractor shall maintain copies of the SDS on site throughout the project.

3.10.2.3 Prior to supplying any HM, the Contractor shall complete FRC East Form 5090/20 and return to the designated FRC East POC.

3.10.2.4 No HM shall be left on site at completion of the contract.

3.10.2.5 All Contractors who enter the FRC East facility to perform installation work described herein shall comply with FRCEASTINST 10290.1 chapter 4, paragraphs 1.e, 11.a, and 11.b, and chapter 5, paragraphs 2.a through 2.e.

3.10.2.6 All Contractors who enter the FRC East facility to perform electrical work described herein shall comply with FRCEAST 10380.1.

3.10.2.7 The contractor shall abide by all COE EM 385-1-1 regulations while performing work inside and/or outside FRC East buildings.

3.10.2.8 The Contractor shall not scale drawing PE-21893 for installation purposes. In the event of omission of necessary dimensions, the Contractor shall notify the Contracting Officer.

3.10.2.9 The Contractor shall secure and pay for all permits, fees, and licenses required for proper execution of installation work described herein.

3.10.2.10 The Contractor shall comply with all provisions of all applicable laws and order of public officials with jurisdiction for safety of persons and property.

3.10.2.11 The Contactor shall verify with the manufacturer/supplier the size, location and characteristics of all work and equipment that is to be furnished by the Government or other contractors prior to installation work pertaining to the same has begun.

3.10.2.12 No equipment loads shall be added to a building roof without prior approval from the Contracting Officer.

3.10.2.13 The contractor shall not transport loads across any mezzanine or building roof without prior approval of a contractor supplied rigging plan.

3.10.2.14 The contractor shall not use Government equipment to accomplish work described herein.

3.10.2.15 Contractors shall not operate Navy owned category 1 and 2 cranes.

3.10.2.16 The contractor shall provide all materials, qualified personnel, transportation, and rigging support for the shipping, installation, set-up, alignment and testing of the equipment and all associated tooling and components unless otherwise stated in this specification.

3.10.2.17 Off-loading of the equipment from the delivery vehicle, and placement of the equipment on foundation for the installation and startup, shall be the responsibility of the contractor. See drawing PE-21893 for installation path, clearances, and annotated equipment.

3.10.2.18 The equipment shall not inhibit the travel of any material handling bridge crane system or jib crane over the entire footprint of the crane travel.

3.10.2.19 The contractor shall be responsible for and be required to pay incurred expenses resulting from damages to work or materials in place on the premises, or included in this contract, during the execution of this contract.

3.10.3 Facility Electrical.

3.10.3.1 The Government will provide electrical source(s) at location(s) shown on drawing PE-21893.

3.10.3.2 The Contractor shall use the electrical source(s) shown on drawing PE-21893 for installation of new equipment.

3.10.3.3 Electrical connections made to the facility electrical system shall be completed by a contractor holding a current electrical contractor’s license issued by the North Carolina Board of Examiners of Electrical Contractors in accordance with the provisions and requirements of Chapter 87, Article 4 of The General Statutes of North Carolina. Contractor shall provide proof of current electrical contractor’s license within thirty (30) days after contract award.

3.10.3.4 Electrical connections shall conform to NFPA 70 and be performed in accordance with NFPA 70E and UFC 1-200-01.

3.10.3.5 Electrical connections shall not inhibit the travel of any material handling bridge crane system or jib crane over the entire footprint of the crane travel.

3.10.3.6 The contractor shall be fully responsible for providing the correct size and type power source enclosure with the appropriate circuit breaker for over-current protection of machine and ancillary equipment.

3.10.3.7 The circuit breaker shall match kAIC rating of source.

3.10.3.8 The contractor shall be responsible for the complete electrical installation including electrical service from power source to machine and any ancillary equipment requiring electrical connection.

3.10.3.9 Connection boxes, outlet boxes, junction boxes, and similar devices and fixtures exposed to the weather, condensation, or excessive dampness shall comply with NEMA ICS 6.

3.10.3.10 Enclosures in interior locations exposed to dripping liquids or falling objects shall meet NEMA 250 Type 2 as a minimum.

3.10.3.11 Enclosures in interior locations exposed to water spray, mist or splashing water shall meet NEMA 250 Type 4X as a minimum.

3.10.3.12 Watertight distribution panel cabinets shall be cast or welded construction with external mounting lugs and externally operable switches.

3.10.3.13 Any penetration into an enclosure shall not affect the degree of protection of the enclosure.

3.10.3.14 Ferrous components of equipment subject to corrosion shall be galvanized or similarly treated before painting. Painting is an acceptable corrosion resistant treatment for switchboard panels, distribution cabinets, and similar enclosures.

3.10.3.15 The contractor shall provide three (3) inches × five (5) inches (W × L) engraved identification placard for new power source enclosure, fusible safety disconnect switch, and motor controller with the following information: equipment name, volt, amp, hertz, and power source feed.

3.10.3.16 The placard shall be black lettering on a white background and attached to the center of the motor controller, main disconnect and all disconnect covers.

3.10.3.17 The placard shall provide all power feed information if the motor controller has multiple power sources (120VAC, 208VAC, and 480VAC etc.).

3.10.3.18 The contractor shall provide an ampere-rating label for new busway plug-in unit.

3.10.3.19 The ampere-rating label shall be 7/8 inch by 2-1/4 inch (W × H) size, black letter with yellow background color, vinyl film or similar material type as other existing enclosure labels.

3.10.4 Facility Compressed Air. (Note: SCFM is CFM at standard conditions. The standard conditions of air are defined as 60 degrees Fahrenheit, 14.7 PSIA and relative humidity of zero. The existing compressed air pressure available is normally 83-93 psi, but does fluctuate.)

3.10.4.1 The contractor shall use the existing compressed air pipe size and location shown on drawing PE-21893 for installation of new equipment.

3.10.4.2 The piping installation shall meet or exceed the current Department of Defense construction criteria as defined in UFC 1-200-01.

3.10.4.3 The contractor shall be responsible for design, procurement, and installation of all new, Government reviewed and Government accepted, compressed air piping additions and modifications.

3.10.4.4 All new piping shall be installed parallel and perpendicular to the building structure.

3.10.4.5 New piping installation shall not block or restrict any existing or new equipment operation or maintenance access.

3.10.4.6 New piping installation shall not…