This solicitation is for a firm fixed-price construction contract to replace the fire system at the National Interagency Fire Center Building 405 in Ada County, Idaho. The Bureau of Land Management seeks to award a single-award contract to remove the existing fire system and install a new one by May 2023. Offerors must propose pricing for the entire scope of work and attend a mandatory site visit on April 12, 2022. Questions are due by April 20th and proposals are due on May 3rd. The estimated value is between $500,000 and $1 million. The set-aside is for total small business. Plans, specifications, and wage determinations are provided.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| NIFC_405-HGR_Fire_Safety_-_Bid_Schedule-V2_0003.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Prologue_5-6-2022_Addendum_3_0003.pdf | ||
| Sol_140L3722R0007_Amd_0003.pdf | ||
| Sol_140L3722R0007_Amd_0002.pdf | ||
| Sol_140L3722R0007_Amd_0001.pdf | ||
| Site_Visit_Roster_0001.pdf | ||
| BLM_NW31_Addenda_1_0001.pdf | ||
| NIFC_405-HGR_Fire_Safety-_QA_0001.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Prologue_4-26-2022_0001.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Specs.pdf | ||
| Sol_140L3722R0007.pdf | ||
| CertificationVaccination.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Bid_Schedule.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Prologue.pdf | ||
| B08_SF1442_HowTo_1Nov2021.pdf | ||
| Wage_Determination_ID20220025_02-25-2022.pdf | ||
| NIFC_405-HGR_Fire_Safety_-_Plans.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO: 140L3722R0007
PROJECT DESCRIPTION: NIFC 405 HGR Fire System Replacement
140L3722R0007 NIFC 405 HGR Fire System Replacement
Type of Contract: Construction, Firm Fixed Priced (FFP), Single Award Contract County: Ada, ID Type of Construction: Building
FAR Magnitude: $500k-$1M NAICS: 237110 SIZE STD: $39.5M SET-ASIDE: Total Small Business
Bureau of Land Management Contacts
Contracting Officer (CO) (Primary Contact)
Contracting Officer Representative
(COR)
Name: Matt Steele TBD at award
Email: masteele@blm.gov TBD at award
Proposal Submittal Information:
Site Visit: April 12, 2022 / 11AM Mountain Time (See clause instructions below / FAR 52.236-27)
Questions Due Date: April 20, 2022 / 2PM Mountain Time
Proposal Due Date: May 3, 2022 / 2PM Mountain Time
Table of Contents
SECTION A: SOLICITATION / CONTRACT FORM
SECTION B: BID SCHEDULE
SECTION C: SPECIFICATIONS/DRAWINGS
SECTION D: PACKAGING AND MARKING
SECTION E: INSPECTION AND ACCEPTANCE
SECTION F: DELIVERIES OR PERFORMANCE
SECTION G: CONTRACT ADMINISTRATION DATA
SECTION H: SPECIAL CONTRACT REQUIREMENTS
SECTION I: CONTRACT CLAUSES
SECTION J: LIST OF ATTACHMENTS
SECTION K: REPRESENTATIONS, CERTIFCATIONS, AND OTHER STATEMENTS OF OFFERORS
SECTION L: INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
SECTION M: EVALUATION FACTORS FOR AWARD
PART I – THE SCHEDULE
SECTION A: SOLICITATION / CONTRACT FORM
Refer to pages 1-3 of this solicitation package (SF1442 - Solicitation, Offer, and Award)
(END OF SECTION)
SECTION B: BID SCHEDULE
CONTRACT PRICE SCHEDULE
Offerors are required to submit an offer that conforms to the solicitation documents with pricing for line items. Failure to do so may render the proposal unacceptable. Offerors shall submit: 1) SF1442 (insert total price into block 17), and 2) a completed supplemental price breakout (see attachments). The supplemental price worksheet will be used for government price analysis, but the subsequent contract will be written with a single lump-sum line item.
SECTION C: SPECIFICATIONS/DRAWINGS
Specifications and drawings are attached in section J and incorporated herein by reference.
SECTION D: PACKAGING AND MARKING
Not Applicable.
SECTION E: INSPECTION AND ACCEPTANCE
CLAUSES INCORPORATED BY REFERENCE
Clause Title Date
52.246-12 Inspection of Construction August 1996
52.246-13 Inspection -- Dismantling, Demolition, or Removal of Improvements August 1996
52.246-21 Warranty of Construction March 1994
SECTION F: DELIVERIES OR PERFORMANCE
52.242-14 Suspension of Work April 1984
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (April 1984)
The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 150 calendar days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G: CONTRACT ADMINISTRATION DATA
CLAUSES INCORPORATED BY FULL TEXT
DIARS 1452.201-70 AUTHORITIES AND DELEGATIONS (September 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
G-1 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should a)provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated:
"The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
G-2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System
(IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice date and Government Contract Number
2. Billing period specified with beginning and ending dates. The beginning date must not be later than the completion date or within any previous billing dates.
3. The accounting must follow the approved schedule of values as described in the specification attachment.
4. Total amount due for the billing period
5. Certification of Progress Payment
6. Payrolls (Mail weekly)
7. Substantiation of Subcontractor Payment
8. 52.223-9 Certification with final payment request.
9. A Release of Claims (See 1452.204-70) with a request for final payment.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
G-3 LOCAL INTERNET PAYMENT PLATFORM (IPP) HOTLINE
To check payment status, contact the Payment Hotline at 877-480-9724 or 303-236-2850. You will need to leave a message with the following information:
1. Company Name
2. Contract Number
3. Invoice Number
4. Invoice Amount
5. A brief description of why you are calling
6. Your contact information
If you do not receive a callback from the Payment Hotline within 72 hours, please contact the Contract Officer with the day and time you contacted the Payment Hotline.
G-4 GOVERNMENT POINTS OF CONTACT
Contracting Officer (Primary POC) Matt Steele masteele@blm.gov Bureau of Land Management, NIFC 3833 S Development Ave Boise, ID 83705
SECTION H: SPECIAL CONTRACT REQUIREMENTS
H-1 WORK HOURS
The performance period established for this contract is based upon all work being conducted during regular working hours between 8:00am and 4:30pm, Monday through Friday, excluding government holidays. If the contractor desires to carry on work outside regular hours (Saturdays, Sundays, government holidays), a written request must be submitted to the contracting officer in sufficient time allow satisfactory arrangements to be made by the government for access to the work site and inspection.
H-2 FIRE DANGER SEASON
If the contracting officer representative (COR) allows the contractor to continue work during periods of declared fire danger or season, the contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
H-3 DRAWINGS
(a) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the contracting officer to adapt the design to existing conditions at the structure location.
(b) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective offerors desiring to review a copy of the full-size drawings may contact the primary contracting office point-of-contact contracting identified in the solicitation.
H-4 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the contracting officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the contracting officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The contractor shall immediately notify the contracting officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
H-5 SAFETY AND QUALITY CONTROL PLAN
Within 10-days following contract award, the contractor must provide effective quality control and safety plans for acceptance by the government.
H-6 FEDERAL HOLIDAYS
The following federal holidays are observed, to include those proclaimed by executive order:
New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Day Independence Day Labor Day Columbus Day Veterans’ Day Thanksgiving Day Christmas Day
H-7 LIMITATIONS ON SUBCONTRACTING REPORTING
In accordance with 52.219-14 Limitations on Subcontracting, the prime contractor must perform at least 15% of the cost of the contract, excluding the cost of materials with its own employees and employees of a similarly situated subcontractor. A similarly situated subcontractor is a small business concern subcontractor that is a participant of the same SBA program that qualified the prime contractor as an eligible offeror and awardee of the contract. The contractor is responsible for ensuring compliance with the Limitations on Subcontracting clause.
At the conclusion of the period of performance and prior to final payment, the contractor shall submit a limitations on subcontracting report directly to the contracting officer. The following information is required as part of the report:
1) The total amount paid to the prime during the performance period broken out by labor and materials
2) List of similarly situated subcontractors and the amounts paid to each during the performance period broken out by labor and materials
3) List of any other subcontractors and the amounts paid to each during the performance period broken out by labor and materials
If the contracting officer review of the report finds that the contractor is not in compliance for the period of performance, the contractor will be notified in writing. Penalties for failure to comply are described in 13 CFR 125.6(h) which states:
Whoever violates the requirements set forth in paragraph (a) of this section shall be subject to the penalties prescribed in 15 U.S.C.
645(d), except that the fine shall be treated as the greater of $500,000 or the dollar amount spent, in excess of permitted levels, by the entity on subcontractors. A party's failure to comply with the spirit and intent of a subcontract with a similarly situated entity may be considered a basis for debarment on the grounds, including but not limited to, that the parties have violated the terms of a government contract or subcontract pursuant to FAR 9.406-2(b)(1)(i) (48 CFR 9.406-2(b)(1)(i)).
H-8 PROTECTING THE FEDERAL WORKFORCE AND REQUIRING MASK-WEARING, FEDERAL FACILITY COVID
PROTOCOLS
All workforce and individuals interacting with the Federal workforce, and to ensure the continuity of Government services and activities, on-duty or on-site Federal employees, on-site Federal contractors, and other individuals in Federal buildings and on Federal lands shall adhere to other public health measures as provided in CDC guidelines. Furthermore, NIFC requires all visitors to complete a vaccination attestation form for entry to the facility.
(END OF SECTION & PART I)
PART II – CONTRACT CLAUSES
SECTION I: CONTRACT CLAUSES
52.202-1 Definitions June 2020
52.203-3 Gratuities April 1984
52.203-5 Covenant Against Contingent Fees May 2014
52.203-6 Restrictions on Subcontractor Sales to the Government June 2020
52.203-7 Anti-Kickback Procedures June 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity May 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014
52.203-12 Limitation on Payments to Influence Certain Federal Transactions June 2020
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights
June 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements January 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper May 2011
52.204-9 Personal Identify Verification of Contractor Personnel January 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards June 2020
52.204-13 System for Award Management Maintenance October 2018
52.204-14 Service Contract Reporting Requirements October 2016
52.204-19 Incorporation by Reference of Representations and Certifications December 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems November 2021
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities
November 2021
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
November 2021
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters October 2018
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November 2015
52.215-2 Audit and Records – Negotiation June 2020
52.215-8 Order of Precedence – Uniform Contract Format October 1997
52.215-21, Alt III Requirements for Certified Cost or Pricing Data and Data Other than Certified Cost or Pricing Data – Modifications
November 2021
52.219-6 Notice of Total Small Business Set Aside November 2020
52.219-8 Utilization of Small Business Concerns October 2018 52.219-28 Post-Award Small Business Program Representation September 2021 52.222-3 Convict Labor June 2003
52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation March 2018
52.222-6 Construction Wage Requirements August 2018 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records July 2021
52.222-9 Apprentices and Trainees July 2005 52.222-10 Compliance with Copeland Act Requirements February 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination-Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations May 2014
52.222-14 Disputes Concerning Labor Standards February 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities April 2015 52.222-26 Equal Opportunity September 2016
52.222-27 Affirmative Action Compliance Requirements for Construction April 2015 52.222-35 Equal Opportunity for Veterans June 2020
52.222-36 Equal Opportunity for Workers with Disabilities June 2020 52.222-37 Employment Reports Veterans June 2020
52.222-40 Notification of Employee Rights Under the National Labor Relations Act December 2010
52.222-50 Combating Trafficking in Persons November 2021
52.222-54 Employment Eligibility Verification November 2021 52.222-55 Minimum Wages Under Executive Order 13658 January 2022 52.222-62 Paid Sick Leave Under Executive Order 13706 January 2017 52.223-3 Hazardous Material Identification and Material Safety Data February 2021 52.223-5 Pollution Prevention and Right-to-Know Information May 2011 52.223-6 Drug Free Workplace May 2001 52.223-15 Energy Efficiency in Energy-Consuming Products May 2020
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
August 2018
52.223-18 Encouraging Contractor Policy to Ban Text Messaging While Driving June 2020
52.223-21 Foams June 2016
52.225-13 Restrictions on Certain Foreign Purchases February 2021
52.227-1 Authorization and Consent June 2020
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement June 2020
52.227-4 Patent Indemnity – Construction Contracts December 2007
52.228-2 Additional Bond Security October 1997
52.228-5 Insurance – Work on a Government Installation January 1997
52.228-11 Pledges of Assets February 2021
52.228-12 Prospective Subcontractor Requests for Bonds May 2014
52.228-14 Irrevocable Letter of Credit November 2014 52.228-15 Performance and Payment Bond – Construction June 2020 52.229-3 Federal, State and Local Taxes February 2013 52.232-5 Payments under Fixed-Price Construction Contracts May 2014
52.232-17 Interest May 2014
52.232-23 Assignment of Claims May 2014
52.232-27 Prompt Payment for Construction Contracts January 2017
52.232-33 Payment by Electronic Funds Transfer-- System for Award Management October 2018
52.232-39 Unenforceability of Unauthorized Obligations June 2013
52.232-40 Providing Accelerated Payments to Small Business Subcontractors November 2021
52.233-1, Alt 1 Disputes May 2014 December 1991
52.233-3 Protest After Award August 1996 52.233-4 Applicable Law for Breach of Contract Claim October 2004 52.236-2 Differing Site Conditions April 1984 52.236-3 Site Investigation and Conditions Affecting the Work April 1984
52.236-5 Material and Workmanship April 1984 52.236-6 Superintendence by the Contractor April 1984
52.236-7 Permits and Responsibilities November 1991
52.236-8 Other Contracts April 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. April 1984
52.236-10 Operations and Storage Areas April 1984 52.236-11 Use and Possession Prior to Completion April 1984
52.236-12 Cleaning up April 1984
52.236-13 Accident Prevention November 1991
52.236-14 Availability and Use of Utility Services April 1984
52.236-15 Schedules for Construction Contracts April 1984
52.236-17 Layout of Work April 1984 52.236-21, Alt I Specifications and Drawings for Construction February 1997
April 1984
52.236-26 Preconstruction Conference February 1995 52.242-13 Bankruptcy July 1995 52.242-14 Suspension of Work April 1984
52.243-4 Changes June 2007
52.244-6 Subcontracts for Commercial Products and Commercial Services January 2022
52.245-1 Government Property September 2021
52.245-9 Use and Charges April 2012
52.248-3 Value Engineering – Construction October 2020
52.249-2, Alt I Termination for Convenience of the Government (Fixed-Price) April 2012 September 1996
52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements
April 2012
52.249-10, Alt I Default (Fixed-Price Construction) April 1984 52.253-1 Computer Generated Forms January 1991
DIAR 1452.203-70 Restrictions on Endorsements – Department of the Interior July 1996
DIAR 1452.204-70 Release of Claims – Department of the Interior July 1996
DIAR 1452.215-70 Examination of Records – Department of the Interior April 1984
DIAR 1452.236-70 Prohibition Against Use of Lead-Based Paint – Department of the Interior July 1996
DIAR 1452.237-70 Information Collection – Department of the Interior July 1996
CLAUSES INCORPORATED BY FULL TEXT
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPEMENT (November 2021)
(a) Definitions. As used in this clause— Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means–
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means–
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 (50 U.S.C. 4817).
Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.
Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.
Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.
(b) Prohibition. (1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.
(c) Exceptions. This clause does not prohibit contractors from providing—
(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(d) Reporting requirement. (1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause to the Contracting Officer, unless elsewhere in this contract are established procedures for reporting the information; in the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (d)(1) of this clause
(i) Within one business day from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known); brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services.
(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (b)(2), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services.
52.219-14 LIMITATIONS ON SUBCONTRACTING (Sep 2021)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:
(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.
(i) The following services may be excluded from the 50 percent limitation:
(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.
(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.
(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded.
(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause – [Contracting Officer check as appropriate.] X By the end of the base term of the contract and then by the end of each subsequent option period; or __ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS (November 2021)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: none
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction Material Description
Unit of Measure Quantity Price (dollars)*
Item1:
Foreign construction material Domestic construction material
Item2:
Foreign construction material Domestic construction material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .