About this file

This document is a Statement of Work (SOW) for the procurement of welded steel cattle guard grids and precast concrete cattle guard foundations for the Bureau of Land Management's (BLM) Worland Field Office (WFO) in Wyoming.

The SOW provides detailed technical specifications for the cattle guard grids, including size, loading, and steel construction requirements. It also specifies the requirements for the precast concrete foundations, including size, concrete strength, reinforcement, and curing. The period of performance is within 365 days from the date of award. Relevant AASHTO, ACI, ASTM, AISC, and AISI standards are referenced. Vendors are required to submit electronic copies of manufacturer drawings or cut sheets for the proposed products. Delivery is required to the BLM's Worland Field Office ware yard, with coordination between the vendor and the Contracting Officer's Representative (COR). The related federal contract opportunity is Solicitation Number 140L6224Q0054 for "WFO CATTLE GUARDS" issued by the Department of the Interior's Bureau of Land Management, Wyoming Region.

View the file

Other files for this federal contract opportunity

Other files attached to WFO CATTLE GUARDS, newest first.
File Type Posted
Questions_Addressed_0001.docx DOCX document
323153-1A_0001.pdf PDF
Sol_140L6224Q0054_Amd_0001.pdf PDF
323153-1_Steel_Cattle_Guard_Grid_(with_and_without_Cleanout).pdf PDF
Sol_140L6224Q0054.pdf PDF
Bid_Schedule.xlsx XLSX spreadsheet
902881-5_Cattle_Guard_Base_(L-Block).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW for WFO Cattle Guards Page 7 of 14

Bureau of Land Management

Wind River / Bighorn Basin District Office

Worland Field Office (WFO) Cattle Guards

Statement of Work for Cattle Guard Materials

Statement of Work (SOW) for Cattle Guard Materials

1.0 General

1.1 Background

The mission of the Bureau of Land Management is to sustain the health, diversity, and productivity of public lands for the use and enjoyment of present and future generations. This acquisition is seeking to purchase and have delivered cattle guard grids, bases, and wings to the Worland Field Office Ware Yard located near Worland, Wyoming.

1.2 Period of Performance

The period of performance of this contract is within 365 days from the date of award.

1.3 Applicable Documents

A. American Association of State Highway and Transportation Officials:

AASHTO T 26-79 Test for Quality of Water to be Used in Concrete

B. American Concrete Institute:

ACI 305R-89Hot Weather Concreting
ACI 306R-88Cold Weather Concreting
ACI 347R-88Guide to Formwork for Concrete

C. American Society for Testing and Materials:

ASTM A 615-90Deformed and Plan Billet-Steel Bars for Concrete Reinforcement
ASTM C 33-90Concrete Aggregates
ASTM C 94-90Ready-Mixed Concrete
ASTM C 143 REV A-90Slump of Portland Cement Concrete
ASTM C 150-89Portland Cement
ASTM C 260-86Air Entraining Admixture for Concrete
ASTM C 309-81Liquid Membrane-Forming Compound for Curing Concrete

D. American Institute of Steel Construction

AISC M 016-89 Manual of Steel Construction Allowable Stress Design

E. American Iron and Steel Institute:

AISI SG 503-76 Design & Fabricating of Cold-Formed Steel Structurals AISI SG 673-86 Cold formed Steel Design Manual

F. Concrete Reinforcing Steel Institute:

CRSI P1-1986 Placing Reinforcing Bars

2.0 Specific Requirements

2.1 Welded Steel Cattle Guards

2.1.1 Cattle Guard Grids

A. Provide cattleguard grids without cleanout sections. See attached Standard Detail Drawing No. 323153-1.

B. Size: Cattle guard grids shall measure 8 feet in the direction of travel and shall have a width of 12, 14, 16, or 20 feet as specified in the bid schedule.

C. Loading: Grids shall be designed for HS-20 loading.

D. Steel grids shall be all-welded construction. Welds shall be secure and complete along both edges of cross pieces and at joints in the frame. Only new material shall be used in the fabrication of cattleguard grids.

E. Torque Bars are required on cattleguard grid rails fabricated with cold-formed structural steel tubing (Alternate Rails). Do not weld torque bars on cattleguard grid rails fabricated with “A” Style cap rails.

F. Paint: The prime coat shall be a lead free, zinc-rich, rust-inhibitive alkyd metal primer. The finish coat shall be an oil alkyd-enamel, gloss paint. Color shall be Federal Safety Yellow or match color no. 13655, Fed. Spec. TT-C-595.

2.2 Precast Concrete Cattle Guard Foundations

2.2.1 Concrete “L-Block” Foundations

A. Provide cattle guard foundations. See attached Standard Detail No. WY-941-02881-5.

B. Size: Cattle guard foundation dimensions shall be as shown on the drawings. The length shall be 12, 14, 16, or 20 feet as specified in the bid schedule.

C. Ready-Mixed Concrete: Ready-mixed concrete shall be designed to meet a minimum of a 28-day compressive strength of 3,000 psi and a maximum slump of 4-inches.

D. Reinforcing Steel: Reinforcing steel shall be deformed and meet the requirements of ASTM A 615 Grade 40. The sizes and lengths of the bars shall be as indicated on the drawings. Reinforcement steel supports shall be sized, arranged, and tied to prevent movement. Reinforcement assembly shall maintain a 3-inch distance from all edges.

E. Concrete Placement: Concrete shall be adequately vibrated into place to fill voids.

F. Concrete Surface Finishes: The top surface of the concrete shall be given a magnesium-float finish after screeding, followed by steel troweling and finished with a broom texture.

G. Concrete Curing: Formwork may be removed after 24 hours. Keep concrete moist for the first 48 hours. Allow concrete to cure for a minimum of 7 days.

H. Handling and Transportation: Foundations shall not be transported until concrete compressive strength has reached a minimum of 70% of design strength. Protect foundations from load stresses, shock load and excessive vibration.

I. Before acceptance by the Government, concrete shall be free of cracks, chipped edges, and honeycombs.

3.0 Required Submittals

3.1 Submittals

A. Requirements: Submit electronic copies of submittals from the supplier for each of the Contractor-furnished items shown on the bid schedule. Submit electronic copies of the manufacturer's drawings or a spec or cut sheet that clearly shows the salient features as listed in section 2 specifications when submitting a bid. Clearly state any exclusions or variations from the salient features. Submit estimated delivery date.

3.0 Delivery

A. Delivery: Protect products from damage while in transit to the delivery location.

Products shall be delivered to Worland Field Office ware yard approximately 1.5 miles north of Worland, WY. From the junction of US Highway 20 and state highway 433 in Worland, WY. Head north on highway 433 for 1.5 miles to the ware yard gate on the east side of the road. Latitude 44.037051, Longitude -107.968980. Delivery shall occur between Monday – Thursday from 8am to 4:30 pm. Exact delivery date shall be coordinated with the COR. Vendor shall provide at least 3 days notice of delivery. BLM will have equipment to unload the delivery truck. The ware yard is unmanned and requires truck driver coordination to have BLM employees on site to unload. For delivery contact:

Josh Trickey(307) 347-5187
BLM Worland Field Office Front Desk(407) 347-5100

File details come from the government source that posted it. Updated .