Bid_Schedule.pdf
PDF 153 KB Posted
- Attached to
- DIAMOND VALLEY MASTICATION Federal contract opportunity
- Solicitation number
- 140L3924Q0075
About this file
The provided document is a Bid Schedule for the 2024 Diamond Valley Mastication Project. The Bid Schedule outlines the unit, quantity, bid price per unit, and total bid for the Diamond Valley Mastication work, which consists of 251 acres. The bid price per acre is to include all labor, equipment, supplies, materials, and incidentals required to complete the work, and payment will be made based on the number of acres satisfactorily completed. The related federal contract opportunity is Solicitation Number 140L3924Q0075, issued by the Department of the Interior Bureau of Land Management Nevada Region, for the Diamond Valley Mastication project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_SOW.pdf | ||
| A06_Map_1.pdf | ||
| B03_Wage_Determination.pdf | ||
| Sol_140L3924Q0075.pdf | ||
| A06_Map_2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2024 Diamond Valley Mastication Project
Bid Schedule
Table 1: Bid Schedule
Unit Acres Bid Price Per
Acre Bid Totals Per Unit
Diamond Valley Mastication 251
NOTE:
The bid shall include the cost of all labor, equipment, supplies, materials, and incidentals to complete the work in the contract. Mobilization includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, plants, and incidentals to the project site; and for other work and operations which must be performed, or cost incurred prior to beginning work and after completion on the various items on the project site.
Work will be measured and paid for by the number of acres that are satisfactorily completed in accordance with specifications in this contract. Payment will be made at the unit price per acre specified in the Bid Schedule and shall include cost of all work described in these specifications. All measurements will be based on a horizontal plane.