BID SCHEDULE.docx
DOCX document 15 KB Posted
- Attached to
- Y1DA--Correct Deficiencies 1W sub-basement 506-21-210 Federal contract opportunity
- Solicitation number
- 36C25022B0058
About this file
This bid schedule outlines pricing requirements for a project to replace elevators at five buildings on the Battle Creek VA Medical Center campus. Contractors must provide lump sum pricing for the base bid to modernize elevators in all five buildings over 730 calendar days. Two deductive alternates are also specified to remove specific buildings or elevators from the scope, shortening the performance period to 640 days. Pricing is solicited to either replace elevators across all buildings, or selectively remove buildings under the deductive alternates, with the lowest aggregate bid across the specified line items to be awarded.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Notice of Award.pdf | ||
| Project 506-21-210 Specifications Updated.pdf | ||
| Project 506-21-210 Drawings Updated.pdf | ||
| 36C25022B0058 Amendment 0001.pdf | ||
| Project 506-21-210 Drawings.pdf | ||
| Project 506-21-210 Specifications.pdf | ||
| Project 506-21-210 Statement of Work (SOW).pdf | ||
| RFI Form Solicitation.doc | DOC document | |
| 36C25022B0058.pdf | ||
| Wage Determination MI20220100 7-15-22.pdf | ||
| Contractor EMR Certification Form .docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
36C25022B0037 Project 515-21-103 Replace Elevators Building 2, 7, 13, 39 & 82 at the Battle Creek VA Medical Center
ALL ITEMS MUST BE PRICED IN ORDER TO BE RESPONSIVE TO THE SOLICITATION
Per Veterans Affairs Acquisition Regulation (VAAR) Provision 852.236-92 – NOTICE TO BIDDERS – ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) The low bid shall be the Bidder that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base line item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive line items that provide the most features within the funds determined available.
The included Deductive Bid Items are listed in descending order of priority in the event funds are not available to award Bid Item I, Base Bid, Entire Project. Deductive No. 1 is the highest priority, and Deductive No. 2 second highest priority.
BID ITEMS
Bid Item No. I, Base Bid, Entire Project: Contractor shall furnish all labor, materials, equipment, supervision, and all other necessary items to complete entire project 515-21-103 Replace Elevators Building 2, 7, 13, 39 & 82 per contract documents, specification drawings. Re-keying Phase: re-key all existing firefighters service for elevators in Building 5, 14, 22, 83, 84, 200 and Elevator #2 in Building 39 and 82. Work location is the Battle Creek VA Medical Center 5500 Armstrong Rd., Battle Creek, MI 49037.
Performance Period for Bid Item I, Base Bid, Entire Project is Seven Hundred Thirty (730) Calendar Days after receipt of Notice to Proceed.
Total Bid Item No. I Base Bid, Entire Project: $________________________ (Lump Sum)
Bid Item No. II, Deductive No. 1: Deduct from the Base Bid Item I:
• Delete all work in Building 13
• Remove all work associated with elevator modernization.
• Provide re-keying of fire-fighting service only.
• Performance Period for Bid Item II, Deductive No. 1 is Six Hundred Forty (640) Calendar Days after receipt of Notice to Proceed.
Deduction for Bid Item No. II, Deductive No. 1: Subtract -$________________________ Bid Item No. III, Deductive No. 2: Deduct from the Base Bid Item I:
• Delete all work in Building 13 and all work for Elevator 3 in Building 2.
• Remove all work for the entire project associated with elevator modernization.
• Provide re-keying of fire-fighting service only.
• Performance Period for Bid Item III, Deductive No. 2 is Six Hundred Forty (640) Calendar Days after receipt of Notice to Proceed.
Deduction for Bid Item No. III, Deductive No. 2: Subtract-$________________________
END OF BID SCHEDULE