Bid Pricing Breakdown Sheet Century Station Air Cooled Chiller Replacementt .xlsx

XLSX spreadsheet 26 KB Posted

Attached to
Century Station Air Cooled Chiller Replacement Federal contract opportunity
Solicitation number
47PE0620R0016
Issued by
General Services Administration Public Buildings Service Region 4

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Sumary Sheet

Date: 03-01-2019Contractor Proposal Summary Worksheet
Design Stage: BidAgency: GSA, PBS Region 4Project: STFB FHWA Suite AlterationsFill In Gray AreasDraft
Location: Columbia, South CarolinaAgencyGSA, PBS Region 4Based on my professional judgement this cost estimate should be considered as the Independent Government Estimate (IGE) for the identified work.
Building # :ProjectSTFB FHWA Suite Alterations
DescriptionCostLocationColumbia, South Carolina
Division 1General Requirements$0.00
Division 2Site Work$0.00
Division 3Concrete$0.00Contractor InformationABC Construction Company, Inc. 1234 Anywhere Drive, City, State
Division 4Masonry$0.00Estimate Date3/1/19
Division 5Metals$0.00GC Overhead0%
Division 6Woods & Plastics$0.00GC Profit0%
Division 7Thermal & Moisture$0.00Insurance0%
Division 8Doors & Windows$0.00Bond0%
Division 9Finishes:$0.00AE Fees0%
Division 10Specialties$0.00Design StageBid
Division 11Equipment$0.00Building Number/Address
Division 12Furnishings$0.00Total SF- 0
Division 13Special Construction$0.00
Division 14Conveying$0.00
Division 21Fire Suppression$0.00
Division 22Plumbing$0.00
Division 23HVAC$0.00
Division 26.1Electrical$0.00ECCEstimated Cost of Construction
Division 26.2Lighting$0.00ECCAEstimated Cost of Construction at Award
Division 27Communication$0.00ETPCEstimated Total Project Cost
Division 28.1Fire Alarm$0.00
Division 28.2Security$0.00
Division 32Exterior$0.00
CSI Subtotal$0.00
GC MarkupsGC Overhead- .00%$0.00
GC Profit- .00%$0.00
Insurance- .00%$0.00
Bond- .00%$0.00
ECC$0.00
A&E Fees- .00%$0.00
ECCA$0.00
ABC Construction Company, Inc. 1234 Anywhere Drive, City, State

Division Detail Sheet

DIVISIONMATERIALLABOR
DescriptionQuantityUnitCostTotalHoursLabor RateTotal
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
0EA$0.00$0.000$0.00$0.00
Material Total$0.00Labor Total$0.00

DIVISION TOTAL $0.00