This Performance Work Statement (PWS) details an exterior lighting upgrade project for Building 3413 at the Devens Reserve Forces Training Area (RFTA) in Massachusetts. The project involves demolishing 38 existing 12' light poles with retrofitted LED heads and installing 15 new government-furnished light poles, including 20' four-inch square steel poles with 150W LED exterior flood fixtures. The contractor will be responsible for providing new concrete bases, underground conduit systems, and electrical connections, with two connection points to be provided by Devens RFTA. The work includes excavation, foundation preparation, pole installation, and ensuring a complete, functional lighting system that meets all technical specifications and safety requirements. The project requires careful coordination with the Directorate of Public Works, adherence to environmental protection guidelines, and preservation of existing site conditions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment W15QKN25QA1640001 SF 30.pdf | ||
| B3413 Propose Exterior Lighting Plan.png | PNG image | |
| 25-Q-A164 - Exterior Lighting - Questions and Answers (1).docx | DOCX document | |
| Solicitation - W15QKN25QA164 (Released).pdf | ||
| Construction Cost Breakdown Form.xls | XLS spreadsheet | |
| 25-Q-A164 - DBA WD MA20250001 (d. 04.04.2025).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US ARMY GARRISON DEVENS RFTA B3413 EXTERIOR LIGHTING UPGRADES
DIRECTORATE OF PUBLIC WORKS PROJECT NO. DEP-G-28301-5P
PERFORMANCE WORK STATEMENT
FOR
B3413 EXTERIOR LIGHTING UPGRADES
DEVENS RESERVE FORCES TRAINING AREA
(RFTA) 3400 AREA,
DEVENS, MA 01434
U.S. ARMY GARRISON DEVENS RFTA
30 QUEBEC STREET
DEVENS, MA 01434
PROJECT NO. DEP-G-28301-5P 14 March 2025
TABLE OF CONTENTS
STATEMENT OF WORK AND CONSTRUCTION SPECIFICATIONS
FOR
B3413 EXTERIOR LIGHTING UPGRADES
DEVENS RESERVE FORCES TRAINING AREA (RFTA)
DEVENS, MA
PROJECT NO. DEP-G-28301-5P
Table of Contents
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 GENERAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 57 20 ENVIRONMENTAL PROTECTIONS (DEVENS RFTA)
DIVISION 26 - ELECTRICAL
26 56 00 EXTERIOR LIGHTING
DIVISION 33 – UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
SECTION 01 10 00 – GENERAL REQUIREMENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00 GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
The existing exterior lighting system at Building 3413 is to be replaced with new lighting system. Work includes demolishing the existing lighting system, installing 15 (fifteen) new Government Furnished light poles and LED lights to be set on new Contractor provided concrete bases.
The poles, light fixtures, and light pole anchor bolt sets are stored in the DPW’s 3400 Area Warehouse, the location of which is shown in Attachment 1. Lights will be connected to a new Contractor provided underground electrical distribution system through the bases to the building where points of connection will be made available.
1.2 WORK COVERED BY THE CONTRACT DOCUMENTS
A. Project Identification: B3413 EXTERIOR LIGHTING UPGRADE.
B. Project Location: Building 3413, 53 Quebec Street. Devens Reserve Forces Training Area, Devens, MA. 01434
C. The Contractor will provide all plant, labor, equipment, materials, transportation, handling and hoisting, supervision, incidentals, and services necessary to remove and replace each of 15 (fifteen) exterior lighting poles and lamps as detailed in this PWS.
D. The Contractor shall perform the following tasks:
1) The Contractor shall provide all plant, labor, equipment, materials, transportation, handling and hoisting, supervision, incidentals, and services necessary to install the exterior lighting system as specified herein.
2) Prior to start of work, the Contractor submit the documents listed in this and other Sections Paragraph entitled SUBMITTALS.
3) Prior to start of work, provide all engineering associated with the disconnection, removal and disposal of the exterior lighting system and associated equipment as specified in GENERAL
CONDITIONS.
4) Obtain all permitting associated with the disconnection, removal and disposal of the exterior lighting system and associated equipment, if required by the State or Local Governments.
5) Prior to the start of work, provide a detailed schedule for execution of the work. All work shall be coordinated with the Devens RFTA DPW and NE ARISC POCs.
6) Prior to the start of work, perform a DigSafe survey of the building’s exterior within the area of work.
Results shall be reviewed with the DPW and determination of hand digging areas will be defined.
7) Due to the presence of underground fiber optic service to B3413, vacuum excavation and hand digging will be required for excavation 10’ each side of the fiber location.
8) Clean up the work area upon project completion, remove waste and surplus materials, rubbish, and construction debris from the site and restore all affected areas to pre-work conditions. Sweep paved areas and rake clean landscaped areas.
9) The USAG Devens RFTA Directorate of Public Works (DPW) POC for this work is George Markt, e-mail:
george.h.markt.civ@army.mil, office phone 978-615- 6549, cell phone 978-201-6473. The DET 1, NE ARISC POCs for this project are 1LT Jonanthan Bates, OIC, office phone no 910-598-8249) and MSG Donald Love, office phone 910-598-8248.
10) All planned on-site work shall be verified with the DPW at least two (2) weeks in advance of actual execution for coordination with the NE ARISC to ensure not impact to mission.
E. Building Access. Contractor shall contact George Markt at
(978) 615-6549 for building access. Access to the building will be controlled, limited, and restricted.
F. The USAG Devens RFTA Directorate of Public Works (DPW)
Point of Contact (POC) for this work is George Markt george.h.markt.civ@army.mil, office phone no. (978) 615- 6549, work cell phone No. (978) 201-6473.
G. Work Hours: Normal work hours are 0730 to 1600, Monday through Friday. Weekend and off-peak hour construction MAY be required to avoid NE ARISC mission impact.
H. LEGAL AND REGULATORY COMPLIANCE
Unless otherwise stated, the Contractor shall obtain and pay for, but not limited to, all fees, licenses, permits, certificates, etc. as required by Local, State, and or Federal Laws and Regulations and Laws necessary for the prosecution of the work.
I. SITE PREPARATION
1) Safety plan: A safety plan must be submitted by the
Contractor and approved by the safety officer before the Contractor mobilizes onsite.
2) Site Access: The Contractor and all related personnel shall submit security application to DOD Garrison Police and be approved for access.
3) Safety Fencing: The work area shall be demarked by a security fence to prevent access and accidents before work commences.
1.3 WARRANTY
The contractor shall provide a warranty for parts and labor at the contractor and manufacturer’s cost for one (1) year on the exterior light system and all associated installed materials and equipment. The warranty requirement excludes Government Furnished materials.
1.4 REFERENCES
A. Where references (e.g., ASTM, ACI, etc.) are noted for compliance throughout this Section, Contractor shall use the most current and up to date copy at time of actual construction.
B. Contractor shall be responsible for obtaining copies of references.
1.5 DEFINITIONS
A. Drawings – That part of the Contract Documents which graphically shows the scope, extent, and character of the Work to be performed by the Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.
B. Existing Conditions - Including but not limited to, all existing buildings and interior utilities (HVAC, electricity, plumbing, etc.), structures, fences, roads, sidewalks, pavement, curbs, above and underground utilities and equipment, existing improvements, vegetation (trees, shrubs, grass, etc.), and underground facilities.
C. Furnish – When used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.
D. Install, Perform or Provide – When used in conjunction with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.
E. Shop Drawings – All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for the Contractor and submitted by Contractor to illustrate some portion of the Work.
F. Site – Including but not limited to land, buildings, structures and or areas indicated in the Contract Documents as being furnished by the Government upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by the Government which are designated for use by the Contractor.
G. Underground Facilities – All underground pipelines, conduits, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.
H. Work – The entire construction, on- and off-site, or the various separate identifiable parts thereof required to be provided under this Contract. Work includes and is the result of performing or providing all labor, services, submittals, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by this Contract.
I. Unless stated otherwise in the Contract, words or phrases which have a well-known technical or construction industry or trade meaning shall be used in the Contract in accordance with such recognized meaning.
1.6 PROJECT/SITE CONDITIONS
A. Existing Conditions
The existing condition of the exterior and associated equipment to be replaced is provided in Attachment 2.
Record Drawings/Specifications may provide additional information and shall be used in conjunction with the existing condition information provided in Attachment 2.
Current conditions may vary from the records. A Contractor site visit for verification of work site conditions prior to bid is HIGHLY encouraged.
B. Work Under Other Contracts
1) During the performance period of this Contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of
Work. In addition, members of the U.S. Armed Forces may be performing work or occupying facilities on or adjacent to the area;
2) Contractor shall arrange his plan and shall schedule and perform this Work to fully cooperate with all Contractors and Government agencies. No direct or extra compensation will be allowed on account of the coordination or cooperation required.
C. Coordination Between Contractors
1) It shall be the responsibility of the prime contractor to fully coordinate with other contractors, or with utility or subcontractor’s forces engaged in collateral work;
2) In case of disputes, the decision of the Contracting
Officer shall be final and binding upon the parties affected;
3) Delays resulting from a lack of proper coordination shall not be grounds for a time extension, direct or extra compensation, or affect the requirements for a timely completion.
1.7 SUBMITTAL PROCEDURES
A. General
1) Units of weights and measures used on all submittals are to be the same as those used in the Contract Documents.
2) Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.
3) Prior to submission to Contracting Officer, all submittals shall be checked and approved by the Contractor as stated in the Contract. Each item shall be stamped, signed, and dated by the Contractor indicating action taken.
4) Proposed deviations from the Contract requirements are to be clearly identified. Include within submittal items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts, or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
5) Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
6) Samples remaining upon completion of the Work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
7) The Contractor shall also comply with Special Contract
Requirements as required based on procurement type and total cost of this Contract.
8) All submittals shall be forwarded to USAG Devens RFTA
Directorate of Public Works 30 Quebec Street, Box 10, Building 666, Devens, MA 01434-4479. Four copies each shall be submitted for all submittals.
B. Submittal Classification
1) Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
2) Information Only
Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or
Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
C. Approved/Accepted Submittals
1) The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.
2) Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.
The Contractor under the Contractor’s quality control program requirements of this Contract is responsible for dimensions, details, and the satisfactory construction of all work, etc.
3) After submittals have been approved or accepted by the
Contracting Officer, no re-submittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
D. Disapproved/Rejected Submittals
1) Contractor shall make corrections required by the
Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes" is to be given to the Contracting Officer.
2) Contractor is responsible for the dimensions, details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
3) If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
E. Withholding of Payment
1) Payment for materials incorporated in the Work will not be made if required approvals have not been obtained.
2) No payment will be made for any materials incorporated into the Work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
F. Scheduling
Submittals covering component items forming a system or items that are interrelated shall be submitted concurrently and scheduled to be coordinated.
Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 14 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
G. Transmittal Form
1) Transmittal Form (ENG Form 4025) shall be used for submitting both Government Approved and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor during the pre-construction meeting. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
2) The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the Work covered in this Contract.
H. Submittal Procedure
1) Quantity of Submittals
The Contractor shall submit four (4) copies for each submittal specified in the Contract.
2) Variations from contract requirements require government approval pursuant to the Contract Clauses and will be considered where advantageous to the government.
a. Considering Variations
Discussions with the Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP). Specifically point out variations from contract requirements in transmittal letters.
Failure to point out deviations may result in the government requiring rejection and removal of such work at no additional cost to the government.
b. Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government.
If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
c. Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
3) Government Approved Submittals
Upon completion of review of submittals requiring government approval, the submittals will be identified as having received approval by being so stamped and dated. Two (2) copies of the submittal will be retained by the Contracting Officer and two (2) copies of the submittal will be returned to the Contractor.
4) Information Only Submittals
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the drawings and specifications; it will not prevent the Contracting Officer from requiring removal and replacement of non-conforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
I. Stamps
Stamps used by the Contractor on all Submittals, to certify that the submittal meets contract requirements, shall be similar to the following:
CONTRACTOR
(Firm Name)
_____ Approved
_____ Approved with corrections as noted on submittal data and/or attached sheets(s).
SIGNATURE:
TITLE:
1.8 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are to be provided for information. Submit the following in accordance with the Submittal Procedures in SECTION 01 11
01 GENERAL REQUIREMENTS.
Work Plan and Schedule, G
Includes: Proposed procedures, methods, and timelines of definable features of work, including, but not limited to: mobilization, demolition, installation, startup, and commission the new exterior lighting system and associated equipment.
Safety Plan, G Accident Protection Plan, G As-Built Drawings and Records, G
Shop Drawings, schematics, and records of the completed construction.
Real Property Records, G
Near the completion of Project, but a minimum of 60 (sixty) days prior to final acceptance of the work, complete and submit an accounting of all installed property on DD FORM 1354. Include any additional assets, improvements, and alterations. Contact the Contracting Officer for any project specific information necessary to complete the DD FORM 1354.
Refer to UFC 1-300-08 for instruction on completing the DD FORM 1354. For convenience, a blank fillable PDF DD FORM 1354 may be obtained at the following link:
www.esd.whs.mil/Portals/54/Documents/DD/forms/dd/dd 1354.pdf
Submit the completed Checklist for DD FORM 1354 of Installed Equipment items. Attach this list to the DD FORM 1354.
1.9 CONTRACTOR USE OF PREMISES
A. Storage Areas http://www.esd.whs.mil/Portals/54/Documents/DD/forms/dd/dd1354.pdf http://www.esd.whs.mil/Portals/54/Documents/DD/forms/dd/dd1354.pdf
Construction staging, equipment, and material storage shall be located in an area as directed by the Contracting Officer.
B. Work Limits
As instructed by the Contracting Officer, the Contractor shall restrict Contractor’s employees to the immediate work areas on the jobsite and in no way go beyond the work limits as indicated by the Contracting Officer.
C. Contractor’s Receipt of Supplies:
1) The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the jobsite.
2) Government personnel are not permitted to receive or sign for items delivered to the site.
D. Utility Interruptions:
1) To the extent practicable, make utility interruptions after normal working hours or on Saturdays, Sundays, and Government holidays.
2) Coordinate all utility cutovers and interruptions with the Contracting Officer.
3) Permission to interrupt any building utility services shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
E. Identification of Employees
1. The Contractor shall be responsible for furnishing the Contracting Officer with a list of all the names of employees prior to employees work on-site; each employee shall be required to carry on their person some sort of identification.
2. The Contractor shall become acquainted with all Post
Regulations in advance. Compliance with the provisions of this paragraph by the Contractor’s subcontractors and their employees will be the responsibility of the Contractor.
1.10 EXISTING WORK
A. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
B. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.11 EXAMINATION OF SITE
It is HIGHLY recommended that the Contractor visit the Site and become familiar with general, local, and Site conditions which may affect cost, progress, or performance of the Work. A site visit shall be scheduled through the Army Contracting Command New Jersey.
1.12 PROTECTION
A. Provide and maintain protection for all existing conditions on or adjacent to the Site, as well as nearby third-party property which is not part of the Work; this also includes parts of the Contract which do not unreasonably interfere with the Work. It is recommended that the Contractor become very familiar with the Site and any adjacent property.
B. Upon discovery of unknown utility or concealed conditions, notify the Contracting Officer immediately and re-direct work to avoid delay.
C. Avoid damage to existing vegetation to remain in place and only remove vegetation when specifically authorized to do so.
D. Any damage to existing conditions, including third party property, as a result of failure to comply with the requirements of the Contract or failure to exercise reasonable care in conducting the Work shall be immediately repaired. If Contractor fails or refuses to promptly repair the damage, the Contracting Officer shall exercise its rights to repair the damage at the expense of the Contractor.
E. During the Work, the Contractor shall provide temporary protection at all times for:
1. Damaged portions of existing structures and land where materials are handled, and equipment is moved and or relocated.
2. The interior of existing structures for the prevention of damage and the intrusion of dust and inclement weather. Prior to the starting any phases or work, all surfaces that are to remain in place and intact shall be adequately protected; this protection shall be maintained until all associated work in the area is completed and accepted by Government.
1.13 RESTORATION
A. All existing conditions which are disturbed, damaged and or removed as a result of the Work, shall be fully restored (restored shall mean, but not be limited to, repaired, put back into service, replaced, etc).
Restorations shall match elevations, conditions prior to the start of the Work. Except as otherwise noted, materials and workmanship used in restoring the damaged work shall conform in type and quality to that of original existing conditions. All restorations shall be at the expense of the Contractor.
B. The Contractor shall not cut, alter or remove any structural components, nor disturb any plumbing, steam, gas, or electric utilities without prior approval from the Contracting Officer.
C. Prior to any disturbance to existing conditions, the
Contracting Officer shall be notified immediately when conditions which are to be altered and or extended are found to be defective in any way.
D. Changes in contract price and or time as a result of restoration to damaged existing conditions which were not shown in the Contract Documents or were unknown to the Government will be covered by the clauses entitled “CHANGES” (FAR 52.243-5) and “DIFFERING SITE CONDITIONS”
(FAR 52.236-2).
1.14 PHYSICAL DATA
A. Data and information furnished or referred to is for the Contractor’s information only. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. The indications of physical conditions on the drawings are the result of As-Built Drawings. The Contractor by his own site investigations shall determine actual field conditions and measurements.
C. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by the drawings. Bidders are expected to examine site of work and, after investigation, decide for themselves character of materials and make their bids accordingly.
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall reasonably make existing utilities available to the Contractor. The Contractor shall carefully conserve any utilities which are furnished without charge.
B. At the expense of the Contractor and the satisfaction of the Contracting Officer, all necessary temporary facilities (electricity, heating, cooling, telephone, controls, distribution lines, etc.), shall be installed and maintained.
C. Prior to final acceptance of the Work, the Contractor shall remove all temporary facilities and any associated appurtenances, and clean and repair damage caused by installation or use of temporary facilities.
1.16 MATERIALS AND EQUIPMENT TO BE SALVAGED
A. Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at a Government designated storage area located within 5 miles of the construction site.
B. Contractor shall maintain property control records for material or equipment designated as salvage.
Contractor's system of property control may be used if approved by the Contracting Officer.
C. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
1.17 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.18 CLEANUP
A. The Contractor shall remove and properly dispose of all waste material and other debris generated by the work daily. It shall be removed off the Site in a manner as to prevent spillage on streets and adjacent roads. Do not allow the materials to accumulate on the Site.
B. Removal, as indicated above, shall be in accordance with all Federal, State, and Local Regulations and Laws.
C. Do not burn or bury materials and or debris on site.
Leave site in clean condition.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 Contractor’s Responsibility
The contractor is responsible for the coordination of all work to meet the requirements of the contract. The contractor shall inspect and survey the existing lights, conduit runs, wiring, shutoffs, feed line, electrical power supply and equipment to demolish the necessary equipment.
Contractors shall connect to the two connection points provided to front and back of building.
The contractor shall ensure that the new exterior lights and associated equipment are complete and useable upon completion of the work.
3.2 DEMOLITION
A. The Contractor shall coordinate all work with Directorate of Public Works Point of Contact.
B. Disconnect, demolish, and dispose of 38 each 12’ poles, including associated 2’ diameter, 4’ deep concrete bases, with retrofitted screw-in LED heads as shown on Attachment 2. No ballasts or HID lamps remain in these fixtures.
C. For information only, a site utilities drawing is provided as Attachment 3. It is the Contractor’s responsibility to verify the location of all underground features in the work area.
D. The Contractor must be aware of mission critical underground fiber optic conduit and cable within the project area. Demolition will require extreme caution to ensure the underground fiber optic conduit is not disturbed. The Contractor shall vacuum excavate and/or hand dig withing 10’ of fiber optic cable.
3.3 NEW UNDERGROUND CONDUIT SYSTEM AND CONCRETE BASES
A. Install a new underground conduit system and wiring to the provide power to the new LED fixtures.
B. Contractor shall provide and install the new concrete pole bases, utilizing the government-furnished bolt kits, underground conduit, electrical vault boxes, and all other material necessary to ensure a complete, working system.
C. The contractor shall be responsible for all excavation required to install the new bases and conduit system, and for restoring site conditions to their prior condition upon completion of the project.
3.4 INSTALL EXTERIOR LIGHTING SYSTEM
A. Devens RFTA DPW will furnish fifteen (15) each 150W LED fixtures exterior flood fixtures suitable for pole mounting; 20’ four-inch square steel poles, including the manufacturer’s approved light pole bolt kits for installation on new concrete bases to be furnished by the
B. Contractor shall install the lights, poles, anchor, bolts to the underground conduit system.
C. Devens RFTA will provide two (2) exterior connection points on the building with controlled power for use in the new exterior lighting system.
3.5 WELDING: All welding shall be performed by AWS certified
welders.
ATTACHMENTS
Attachment 1 USAG Devens RFTA
3400 Area
-- END OF SECTION 01 10 00 --
PROJECT LOCATION
GOVERNMENT FURNISHED EQUIPMENT
IS STORED IN THE DPW WAREHOUSE
Section 01 33 00 - SUBMITTAL PROCEDURES
SECTION 01 33 00 SUBMITTAL PROCEDURES
1.1 SUBMITTAL IDENTIFICATION
Submittals required are identified by SD numbers and titles as follows:
SD-01 Preconstruction Submittals
A document, required of the Contractor, or through the Contractor, from a supplier, installer, manufacturer, or other lower tier Contractor, the purpose of which is to confirm the quality or orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel, qualifications, or other verifications of quality.
SD-02 Shop Drawings
Submittals which graphically show relationship of various components of the work, schematic diagrams of systems, details of fabrication, layouts of particular elements, connections, and other relational aspects of the work.
SD-03 Product Data
Preprinted manufacturer material describing a product, system, or material, such as catalog cuts.
SD-04 Samples
Samples, including both fabricated and un-fabricated physical examples of materials, products, and units of work as complete units or as portions of units of work.
SD-05 Design Data
Submittals, which provide calculations, descriptions, or documentation regarding the work.
SD-06 Test Reports
Reports of inspections or tests, including analysis and interpretation of test results.
SD-07 Certificates
Statement signed by an official authorized to certify on behalf of the manufacturer of a product, system, or material, attesting that the product, system or material meets specified requirements. The statement must be dated after the award of the contract, must state the Contractor's name and address, must name the project and location, and must list the specific requirements, which are being certified.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material; including special notices and material safety data sheets, if any, concerning impedances, hazards, and safety precautions.
SD-09 Manufacturer's Field Reports
Daily reports from specially suppliers to the contractor that provide information, data, tests result for a product.
SD-10 Operation and Maintenance Data
Data, which forms a part of an operation and maintenance manual.
SD-11 Closeout Submittals
All data, documentations, information, and drawings to achieve contract closeout.
SD-12 Schedules
All data, documentations, information, and drawings to achieve contract closeout.
SD-13 Records
Documentation to record compliance with technical or administrative requirements.
1.2 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
A. Government Approved/Accepted (G)
All submittals classified for Government Approval/Acceptance (G) are identified in the approved submittal register Form 4288. A code following the "G" designation indicates the action authority; codes of "DPW" for Director of Public Works, and "AE" for Architect- Engineer action.
1) Government Approved
Government approval is required for all specification submittal items found in specifications having structural steel connections, extensions of design, Fire Protection/Life Safety, and Commissioning of HVAC, and other items as designated by the Contracting Officer.
Government approval (G) is also required for all submittals designated as such in the technical specifications. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are "shop drawings". The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below.
2) Government Accepted
Government acceptance applies to the Quality Control Plan, the Accident Prevention Plan, and the Drug Free Workplace Certification. These submittals are within the terms of the Contract Clauses entitled "Inspection of Construction", "Accident Prevention", and "Drug Free Workplace" respectively. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below.
B. Information Only
All Contractor submittals not requiring Government approval will be for information only. FIO submittals are identified in the approved submittal register Form 4288R. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above. FIO Submittals will be retained at the project site and reviewed prior to Preparatory Meetings.
1.3 APPROVED/ACCEPTED SUBMITTALS
The Contracting Officer's approval/acceptance of submittals shall not be construed as a complete check but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.4 DISAPPROVED/NON-ACCEPTED SUBMITTALS
The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the
1.5 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
PART 2 PRODUCTS (NOT APPLICABLE)
3.1 GENERAL
The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used on the contract drawings or required per the contract documents.
Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) System Manager and each item shall be stamped, signed, and dated by the Contractor's Quality Control CQC System Manager indicating action taken. Proposed deviations from the contract requirements shall be clearly identified.
Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
No work shall be performed on the project without Government accepted and approved plans/drawings stamped and submitted by the Contractor for approval by the Devens RFTA Director of Public Works.
3.2 SUBMITTAL REGISTER
A submittal register showing items of equipment and materials for which submittals are required by the specifications is attached to the specifications; this list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format. Thereafter, the Contractor shall maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the Government will be included in its export file to the Contractor. The Contractor shall track all submittals. NOTE: The Contractor is required to add additional entries to the Submittal Register for all items requiring multiple submittals, including Formwork Shop Drawings per Lift, Concrete Reinforcement per Lift, Concrete Lift Drawings per Lift, Multiple Shop Assembly Drawings, etc. These entries should be made prior to original submission of the submittal register within 30 days of Notice to Proceed.
3.3 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 30 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals. An additional 30 calendar days shall be allowed and shown on the register for review and approval of submittals for HVAC control systems.
3.4 ALL SUBMITTALS WHICH EXCEED THE DETAIL SHOWN ON THE
CONTRACT DRAWINGS
A. Submittal details or drawings which exceed that which is shown on the contract drawings to be transmitted in electronic format. All such submittals must include, along with the hard copy of the drawings required above, CADD files of the submittal in a commercially available format, such as MicroStation or AutoCAD, for incorporating into as-built or record drawings.
B. These submittals include those that reflect structural details, foundation layouts, equipment, sizes, mechanical room layouts, and other similar data, including all extensions of design, which were not shown or have changed from the original drawings.
3.5 TRANSMITTAL FORM (ENG FORM 4025)
The sample transmittal form (ENG Form 4025) attached at the end of this section shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted.
Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.
3.6 SUBMITTAL PROCEDURE
Submittals shall be made as follows:
A. Procedures
The Contractor shall submit to the Contracting Officer six copies of all submittals of items requiring shop inspection and all other submittals required of these specifications.
Submittals will be returned electronically.
B. Deviations
The column "variation" of ENG Form 4025 shall be checked for Submittals which include proposed deviations. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
3.7 CONTROL OF SUBMITTALS
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
3.8 GOVERNMENT APPROVED SUBMITTALS
Upon completion of review of submittals requiring Government approval/acceptance, the submittals will be identified as having received approval/acceptance by being so stamped and dated. Three copies of the submittal will be retained by the Contracting Officer and three copies of the submittal will be returned to the Contractor.
3.9 INFORMATION ONLY SUBMITTALS
The Contractor is responsible for preparing and retaining two copies of all FIO submittals in a pair of "Government" files at the Contractor's field office. One copy of the FIO submittals will be used for historical record and transferred to the customer upon completion of the project.
The second copy will be used for Quality Assurance reviews but may be retained at the Government's field office at the discretion of the Quality Assurance Representative. Both files shall be maintained in good order and filed by specification section. A minimum of 30 days in advance of the Approval Needed By date (Submittal Register, ENG Form 4288, Contractor Schedule Dates, Item "t") the Contractor shall submit only the transmittal form (ENG Form 4025-R) to the Government. The required submittal information shall be complete and available for review at the Contractor's field office. Government personnel will perform discretionary Quality Assurance reviews of the submittals as necessary to satisfy the Government that the Contractor's Quality Control system is providing the specified level of quality.
Submittals that contain both Government Approval and Information Only items shall be processed as Government Approved Submittals. Submittals that do not meet the contract requirements will be assigned an "FX" action code by the Contracting Officer, and the submittal deficiencies will be forwarded to the Contractor. The Contractor shall resubmit for Government Approval and in accordance with Paragraph "Disapproved Submittals". Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
3.10 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:
CONTRACTOR
(Firm Name)
_____ Approved
_____ Approved with corrections as noted on submittal data and/or attached sheets(s).
SIGNATURE:
TITLE:
-- END OF SECTION 01 33 00--
Section 01 57 20 - ENVIRONMENTAL PROTECTIONS (DEVENS RFTA)
SECTION 01 57 20
ENVIRONMENTAL PROTECTIONS (DEVENS RFTA)
1.1 REFERENCES (NOT APPLICABLE)
1.2 DEFINITIONS
A. Contractor Generated Hazardous Waste - Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work but are not fully consumed during construction. Examples include, but are not limited to, excess paint thinners (i.e., methyl ethyl ketone, toluene etc.), waste thinners, excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.
B. Environmental Pollution and Damage - Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;
affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.
C. Environmental Protection - Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air;
biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
D. Hazardous Materials - As defined by the Environmental
Protection Agency (EPA) or State Hazardous Control Authority. Hazardous material is any material that is regulated as a hazardous material by the EPA or requires a Material Safety Data Sheet (MSDS), or during end use, treatment, handling, packaging, storage, transpiration, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste.
Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).
Nonetheless, the exposure may occur incident to manufacture, storage, use and demilitarization of these items.
E. Hazardous Waste - Any discarded material, liquid, solid, or gas, which meets the definition of hazardous material or is designated hazardous waste by the Environmental Protection Agency or State Hazardous Control Authority.
F. Land Application for Discharge Water - The term "Land
Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "Waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and regulations.
G. Oily Waste - Those materials which are, or were, mixed with used oil and have become separated from that used oil. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, used oil and may be appropriately tested and discarded in a manner which is in compliance with Federal, State and local requirements.
H. Pesticide - Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.
I. Solid Waste - Garbage, refuse, debris, sludge, or other discharged material, including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.
J. Surface Discharge - The term implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur.