B2414Tabulation.pdf
PDF 109 KB Posted
- Attached to
- Tra Thomas Park Improvements State and local contract opportunity
- Solicitation number
- B-24-14
- Issued by
- Volusia County, Florida
About this file
This document is a bid tabulation sheet for the Tra Thomas Park Improvements project in Florida, featuring a detailed pricing comparison among five construction contractors: Asphalt Icons, DDS Enterprises, Drewry Site Development, Garcia Civil Construction, and Sanderson Concrete Construction. The project involves multiple infrastructure improvements, including mobilization, maintenance of traffic, sediment barriers, excavation, concrete work, sidewalks, curbing, pavement markings, and landscaping. The bid tabulation lists 20 separate line items with quantities, unit prices, and total extended prices for each contractor.
The total bid prices vary significantly among contractors, ranging from a low of $121,015.94 (Garcia Civil Construction) to a high of $289,600.85 (Asphalt Icons). Each contractor has different unit prices for individual items, with some providing zero-cost bids for certain elements like soil tracking prevention devices or portable changeable message signs. The document includes a note that all bids are subject to review and the tabulation is not final, indicating that the contract award has not yet been determined. The pricing details provide a comprehensive breakdown of expected costs for each construction element in the park improvement project.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| RCA.pdf | ||
| B2414ADD1.pdf | ||
| B2414Plans.pdf | ||
| B2414Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item No. Description Unit Quantity Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price Unit Price Extended Price
101-2 Mobilization LS 1 $72,530.00 $72,530.00 $15,000.00 $15,000.00 $13,390.00 $13,390.00 $23,003.09 $23,003.09 $17,000.00 $17,000.00
102-1 Maintenance of Traffic LS 1 $10,417.49 $10,417.49 $15,000.00 $15,000.00 $4,800.00 $4,800.00 $4,506.01 $4,506.01 $8,500.00 $8,500.00
102-99 Portable Changeable Message Sign (Temporary) ED 30 $15.60 $468.00 $166.50 $4,995.00 $59.00 $1,770.00 $170.77 $5,123.10 $0.00
104-10-3 Sediment Barrier LF 454 $2.44 $1,107.76 $5.50 $2,497.00 $4.25 $1,929.50 $5.59 $2,537.86 $1.65 $749.10
104-15 Soil Tracking Prevention Device EA 1 $4,444.25 $4,444.25 $2,500.00 $2,500.00 $5,800.00 $5,800.00 $5,894.66 $5,894.66 $0.00
104-18 Inlet Protection System EA 1 $143.00 $143.00 $500.00 $500.00 $750.00 $750.00 $358.87 $358.87 $200.00 $200.00
110-1-1 Clearing & Grubbing LS 1 $25,571.00 $25,571.00 $15,000.00 $15,000.00 $5,800.00 $5,800.00 $13,078.87 $13,078.87 $10,000.00 $10,000.00
110-4-10 Removal of Existing Concrete SY 336 $36.27 $12,186.72 $31.50 $10,584.00 $12.00 $4,032.00 $23.41 $7,865.76 $31.00 $10,416.00
120-1 Regular Excavation LS 1 $11,476.00 $11,476.00 $10,000.00 $10,000.00 $8,980.00 $8,980.00 $12,654.18 $12,654.18 $2,400.00 $2,400.00
160-4 Type B Stabilization (8") SY 10 $417.19 $4,171.90 $250.00 $2,500.00 $35.00 $350.00 $116.55 $1,165.50 $70.00 $700.00
334-1-12 Superpave Asphaltic Conc, Traffic B, 2", PG 76-22 TN 2 $2,002.99 $4,005.98 $1,250.00 $2,500.00 $725.00 $1,450.00 $1,566.62 $3,133.24 $1,000.00 $2,000.00
520-2-4 Concrete Curb, Type D LF 652 $23.14 $15,087.28 $32.00 $20,864.00 $15.98 $10,418.96 $21.60 $14,083.20 $35.00 $22,820.00
520-3 Concrete Valley Gutter LF 22 $169.00 $3,718.00 $25.00 $550.00 $45.00 $990.00 $88.64 $1,950.08 $31.00 $682.00
522-1 Concrete Sidewalk 4" Thick SY 93 $126.36 $11,751.48 $85.00 $7,905.00 $47.00 $4,371.00 $84.98 $7,903.14 $49.00 $810.00
522-2 Concrete Sidewalk & Driveway 6" Thick SY 684 $146.25 $100,035.00 $115.00 $78,660.00 $64.90 $44,391.60 $63.98 $43,762.32 $54.00 $36,936.00
527-2 Detectable Warning (Preformed Thermoplastic) SF 27 $65.00 $1,755.00 $28.00 $756.00 $42.00 $1,134.00 $14.98 $404.46 $30.00 $810.00
542-70 Concrete Bumper Guard (Parking Lot) EA 15 $104.00 $1,560.00 $100.00 $1,500.00 $150.00 $2,250.00 $443.51 $6,652.65 $50.00 $750.00
570-1-2 Performance Turf, Sod SY 817 $7.25 $5,923.25 $4.50 $3,676.50 $5.25 $4,289.25 $14.51 $11,854.67 $6.50 $5,310.50
700-1-50 Single Post Sign, Relocate AS 1 $195.00 $195.00 $250.00 $250.00 $250.00 $250.00 $117.73 $117.73 $100.00 $100.00
710-90 Painted Pavement Marking, Standard White, Solid, 6" LF 228 $0.85 $193.80 $21.95 $5,004.60 $6.21 $1,415.88 $12.16 $2,772.48 $9.40 $2,143.20
711-11-123 Thermoplastic, Standard White, Solid, 12" for Crosswalk LF 151 $18.94 $2,859.94 $16.50 $2,491.50 $16.25 $2,453.75 $20.86 $3,149.86 $13.95 $2,106.45
$289,600.85 $202,183.60 $121,015.94 $171,971.73 $124,433.25Total
*Note: All bids are subject to review and tabulation is not final.
Asphalt Icons DDS Enterprises, LLC Drewry Site Development Garcia Civil Construction Sanderson Concrete Construction, Inc.
B-24-14 Tabulation
Tra Thomas Parl Improvements
Sheet1