B1580-FIRE PROTECTION UPGRADE-FINAL.pdf
PDF 5 MB Posted
- Attached to
- Building 1580 Fire Protection Federal contract opportunity
- Solicitation number
- N40080-20-R-0025
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Building 1580 FIre Protection amendment 0002.pdf | ||
| BUILDING 1580 FIRE PROTECTION AMENDMENT 0001.pdf | ||
| Expected Visitor Form blank 1.doc | DOC document | |
| RFP Template for BUILDING 150 FIRE PROTECTION.docx | DOCX document | |
| bLANK VETTING FORM.pdf | ||
| NAVADMIN 100-20 Face Coverings 20200405.pdf | ||
| SECDEF Cloth Face Coverings Guidance 20200405.PDF | ||
| Enclosure 1 CUSFF_NAVNORTH COVID-19 Screening Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
eProjects WORK ORDER NO.
N40080- -
At the
PREPARED BY:
NAVFAC WASH, South Potomac
REQUEST FOR PROPOSAL PREPARED BY:
Architectural: Electrical:
Civil: Fire Protection:
Structural: Environmental:
Mechanical: Cost Estimating:
Customer Acceptance (Non Technical) Signature Date:
Design Manager Name Signature Date:
CI Team Lead/PMEB Name Signature Date:
FINAL RFP
Fire Protection Upgrades in Building 1580 Work Order Number 1560461 NSA South Potomac, Dahlgren, VA
Table Of Content-Page 1
1.0 Table of Contents (RFP Parts 2-6)
PART 1– DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
PART 2 - DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT
CONTRACT MANAGEMENT SYSTEM
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 35 40.00 20 ENVIRONMENTAL MANAGEMENT
01 42 00 SOURCE FOR REFERNCE PUBLICATION
01 45 00.00 20 QUALILTY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE
SUPPORT INFORMATION (eOMSI)
PART 3 – PROJECT PROGRAM
CHAPTER 1 & 2. PROJECT DESCRIPTION AND PROJECT OBJECTIVES
PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS
PART 4 PERFORMANCE TECHNICAL SPECIFICATIONS
PART 5 – PRESCRIPTIVE SPECIFICATIONS
NOT USED
PART 6 – ATTACHMENTS
BASIS OF DESIGN
LIFE SAFETY REPORT
SPECIFICATIONS
DRAWINGS
BID SCHEDULE
PART ONE - PROPOSAL FORMS & DOCUMENTS - Page 1
PART ONE - PROPOSAL FORMS & DOCUMENTS
Contractor Bid Schedule:
All Contractors shall provide their bid proposal in accordance with the bid schedule; see Part 6, Attachments for the blank Excel Spreadsheet bid schedule form. Proposals will not be accepted without completion of the bid schedule form.
The Contractor can add additional definable features of work as necessary to help clarify their bid proposals.
Contractor Project Schedule:
All Contractors shall provide an overall project schedule which reflects all major features of work including, but not limited to; contract award, shop drawings, phase schedule, construction submittals and reviews (including government approved submittals), fabrication of definable features of work, inclement weather days and all required construction timeframes.
DOCUMENT 00 01 15-Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET NUMBER SHEET TITLE NAVFAC
DWG NO.
G-001 COVER SHEET 13112077
A-001 ARCHITECTURAL SYMBOLS-DETAILS 13112078
AD-101 REFLECTED CEILING PLAN - FIRST FLOOR 13112079
AD-102 REFLECTED CEILING PLAN - SECOND FLOOR 13112080
FA-001 FIRE ALARM NOTES & LEGEND 13112081
FA-101 BLDG. 1580 FIRE ALARM 1ST FL.
DEMOLITION PLAN -AREA-A
13112082
FA-102 BLDG. 1580 FIRE ALARM 1ST FL.
DEMOLITION PLAN -AREA-B
13112083
FA-103 BLDG. 1580 FIRE ALARM 1ST FL.
DEMOLITION PLAN -AREA-C
13112084
FA-104 BLDG. 1580 FIRE ALARM 1ST FL. UNDER
FL. DEMO PLAN - AREA-A
13112085
FA-105 BLDG. 1580 FIRE ALARM 1ST FL. UNDER
FL. DEMO PLAN - AREA-B
13112086
FA-106 BLDG. 1580 FIRE ALARM 1ST FL. UNDER
FL. DEMO PLAN-AREA-C
13112087
FA-107 BLDG. 1580 FIRE ALARM 2ND FL.
DEMOLITION PLAN
13112088
FA-121 BLDG. 1580 FIRE ALARM 1ST FL. NEW WORK
PLAN -AREA-A
13112089
FA-122 BLDG. 1580 FIRE ALARM 1ST FL. NEW WORK
PLAN -AREA-B
13112090
FA-123 BLDG. 1580 FIRE ALARM 1ST FL. NEW WORK
PLAN -AREA-C
13112091
FA-125 BLDG. 1580 FIRE ALARM 1ST FL. UNDER
FL. NEW PLAN - AREA - B
13112092
FA-126 BLDG. 1580 FIRE ALARM 1ST FL. UNDER
FL. NEW PLAN - AREA - C
13112093
FA-127 BLDG. 1580 FIRE ALARM 2ND FL. NEW WORK
PLAN
13112094
FA-501 FIRE ALARM DETAILS 13112095
FA-502 FIRE ALARM DETAILS 13112096
FA-503 FIRE ALARM DETAILS 13112097
DOCUMENT 00 01 15-Page 2
FA-601 BUILDING 1580 RISER DIAGRAM, MATRIX
AND SCHEDULE
13112098
FX-001 FIRE SUPPRESSION NOTES & LEGEND 13112099
FX-002 FIRE SUPPRESSION ZONING PLAN 13112100
FX-101 BLDG. 1580 FIRE SUPP. 1ST FL. DEMO
PLAN - AREA-A
13112101
FX-102 BLDG. 1580 FIRE SUPP. 1ST FL. DEMO
PLAN - AREA-B
13112102
FX-103 BLDG. 1580 FIRE SUPP. 1ST FL. DEMO
PLAN - AREA-C
13112103
FX-104 BLDG. 1580 FIRE SUPPORESSION 2ND FL.
DEMO PLAN
13112104
FX-121 BLDG. 1580 FIRE SUPP. 1ST FL. NEW PLAN
- AREA-A
13112105
FX-122 BLDG. 1580 FIRE SUPP. 1ST FL. NEW PLAN
- AREA-B
13112106
FX-123 BLDG. 1580 FIRE SUPP. 1ST FL. NEW
PLAN - AREA-C
13112107
FX-124 BLDG. 1580 FIRE SUPPRESSION 2ND FL.
NEW WORK PLAN
13112108
FX-501 FIRE SUPPRESSION DETAILS 13112109
FX-502 FIRE SUPPRESSION DETAILS 13112110
FX-503 FIRE SUPPRESSION DETAILS 13112111
E-001 SYMBOLS - ABBREVIATIONS 13112112
E-101 EXISTING ELECTRICAL - FIRST FLOOR 13112113
-- End of Document --
STANDARD TEMPLATE - PART TWO - GENERAL REQUIREMENTS - Page 1
PART TWO - GENERAL REQUIREMENTS
SECTION 01 11 00 - Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes provision of automatic sprinkler systems, demolition of existing, demolition of existing Halon system, acceptance testing, painting, cleanup and incidental related work.
1.2.2 Location
The work is located at the Dahlgren NSWC, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located on the Dahlgren NSWC station.
SECTION 01 11 00 - Page 2
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
SECTION 01 14 00 - Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. Code (USC)
10 USC 6011 Navy Regulations
8 USC 1101 Definitions
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Automatic fire sprinkler system must be ready for operation as approved by Contracting Officer before work is started on demolition of the existing systems which would interfere with normal operation.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
c. The existing fire alarm systems will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Identification Badges and Installation Access
SECTION 01 14 00 - Page 2
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Defense Biometric Identification System (DBIDS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through DBIDS are the responsibility of the Contractor. The previous NCACS credentials will no longer be valid after 31 August 2017. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.
Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a. DBIDS Program: See http://dbids.dmdc.mil for more information.
b. One-Day Passes: Participation in the NCACS is not mandatory, and if the
Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations under the cognizance of NAVFAC Washington except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of a period established by the Contractor Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays. Pretest and final acceptance testing of the fire alarm and suppression systems may take place outside of normal working hours.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Occupied and Existing Buildings
The Contractor shall be working in and around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all http://www.uscis.gov/portal/site/uscis http://dbids.dmdc.mil/
SECTION 01 14 00 - Page 3 times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the during the construction period.
Relocate movable furniture approximately [1.8 m] 6 feet away from the Contractor's working area and as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and visitors. Do not use these areas for parking or storage of materials.
Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials
Daily Cleaning: Contractor will be working is spaces occupied by Government Personnel during normal working hours. Coordinate with Contracting Officer for where work will occur on a particular night. Government employees will clear cubicle shelf tops and desktops prior to contractor entry into the space. Provide temporary covering, consisting of 6-mil polyethylene sheeting or canvas drop cloths, of working and seating surfaces prior to beginning work, and clean and remove covers at the end of each work period.
Vacuum carpets and sweep floors before entry of Government Personnel.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruptions are further limited to 8 hours. This time limit includes time for deactivation and reactivation.
1.4 SECURITY REQUIREMENTS
1.4.1 Naval Surface Warfare Center (NSWC), Dahlgren, VA
A copy of the security regulations may be obtained from the security office of the station. Contractor employees will be required to be escorted by Government employees at all times while work is being performed.
Government will provide escorts. Base bid on utilization of 3 escorts.
SECTION 01 14 00 - Page 4
Escorts can supervise up to 5 contractor employees each but must remain under direct supervision and line of site of escort.
Not Used
SECTION 01 20 00.00 20 - Page 1
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
11/11
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating
Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
Schedule of Prices; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building(s), and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting
SECTION 01 20 00.00 20 - Page 2 records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the
Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Quality Control (QC) Manager as required by the contract.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form
7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC LANT Form 4-330/110 (New 7/84) on NAVFAC LANT contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
1.5.2 Submission of Invoices
If NFAS Clause 5252.232-9301 is included in the contract, the documents listed in paragraph "CONTENT OF INVOICE" shall be provided in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's
Final Release Form must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification
SECTION 01 20 00.00 20 - Page 3 of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in
Contract Clause "FAC 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/pre-stressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's
SECTION 01 20 00.00 20 - Page 4 estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored in the Continental United States. Other locations are subject to written approval by the Contracting Officer.
SECTION 01 30 00 - Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
15 CFR 772 Definition of Terms
15 CFR 773 Special Licensing Procedures approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Progress and Completion Pictures; G
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document interior conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 10 digital photographs each week at project building. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
1.4 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 LIABILITY, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.5 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS
SECTION 01 30 00 - Page 2
Accomplish all contract requirements of Section 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS, assigned to the Private Qualified Person, directly with a first tier subcontractor.
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.6.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years of experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 20 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.6.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual
SECTION 01 30 00 - Page 3 understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.8 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the NAVFAC Red Zone (NRZ) process and convene at regularly scheduled NRZ Meetings. Include the following in the facility Turnover effort:
1.8.1 NRZ Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the NRZ Checklist template prior to 75 percent completion.
b. Prior to 75 percent completion add/delete critical activities to the
NRZ Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the NRZ checklist for each critical activity. Present the NRZ Checklist to COTR and review during a regularly scheduled QC Meeting.
1.8.2 Meetings
a. Upon Government acceptance of the NRZ Checklist, the Project Superintendent is required to lead regular NRZ Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.
c. Using the NRZ Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. Coordinate with the COTR any upcoming activities that require
Government involvement.
e. Maintain the NRZ Checklist by documenting the actual completion dates as work is completed and update the NRZ Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current NRZ Checklist to attendees at each NRZ Meeting.
1.9 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the
SECTION 01 30 00 - Page 4
Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.9.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
SECTION 01 31 23.13 20 Page 1
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional or specifically requested in addition to electronic submission. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
List of Contractor's Personnel; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
SECTION 01 31 23.13 20 Page 2
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.4.3 Field Administration
Within 30 days of Contract Award, provide a tablet computer with a Common Access Card (CAC) reader at the job site for Government use only. The tablet computer must have a web-browser, built-in camera, and cellular data connectivity. Provide tablet computer with a rugged case suitable for use in a construction environment. The tablet computer must be fully charged and made available at all times for Government use to facilitate the input of construction data at the job site. After completion of the work, reset the tablet computer to factory default settings. The tablet computer remains the property of the Contractor and must be removed from the site.
There are restrictions on use of WIFI on military bases. Cellular data connectivity and availability, and use of WIFI requires coordination with and approval by the Contracting Officer.
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of Defense Manual 5200.01-V4: DoD Information Security Program: Controlled Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "FOUO - UNCLASSIFIED-FOR OFFICIAL USE ONLY" (FOUO).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
SECTION 01 31 23.13 20 Page 3
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents. This requirement supersedes conflicting requirements in other sections, however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and FOUO designations for various types of project documents.
Construction documents requiring FOUO status must be marked accordingly.
Apply the appropriate markings before any document is uploaded into eCMS.
Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. After uploading documents to the Submittal application, transmit the submittals and attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Construction Permits
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
SECTION 01 31 23.13 20 Page 4
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (Cost-Loaded)
FOUO After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (3-Week Look-a-head)
U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Scheduling App
DD 1354 Transfer of Real Property
U Submittals and Transmittals
Daily Production Reports
FOUO Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
FOUO Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Environmental Protection Plan
(EPP)
FOUO Submittals and
SECTION 01 31 23.13 20 Page 5
Invoice (Supporting Documentation)
FOUO Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals and Transmittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and Transmittals
Meeting Minutes FOUO Meeting Minutes
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Photographs U Subject to base/installation restrictions
Submittals and Transmittals
QCM Initial Phase Checklists
FOUO Checklists (Site Management)
QCM Preparatory Phase Checklists
FOUO Checklists (Site Management)
Quality Control Plans
FOUO Submittals and Transmittals
QC Certifications U Submittals and Transmittals
QC Punch List U Punch Lists (Testing Logs)
Red-Zone Checklist U Checklists (Site Management)
Rework Items List FOUO Punch Lists (Testing Logs)
SECTION 01 31 23.13 20 Page 6
Request for Information (RFI) Post-Award
FOUO RFIs
Safety Plan FOUO Daily Report
Safety - Activity Hazard Analyses
(AHA)
FOUO Daily Report
Safety - Mishap Reports
FOUO Daily Report
SCIF/SAPF
Accreditation Support Documents
FOUO Note: Some Construction Security plans may be classified as Secret. Classified information must not be uploaded into eCMS.
Refer to the Site Security Manager, as applicable.
Submittals and Transmittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Storm Water Pollution Prevention (Notice of Intent
- Notice of Termination)
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Submittals and Submittal Log
U Submittals and Transmittals
Testing Plans, Logs, and Reports
FOUO Submittals and Transmittals
Training/Reference Materials
U Submittals and Transmittals
Training Records (Personnel)
FOUO Submittals and Transmittals
Utility Outage/Tie-In Request/Approval
SECTION 01 31 23.13 20 Page 7
Warranties/BOD Letter
Quality Assurance Reports
FOUO Checklists (Government initiated)
Non-Compliance Notices
FOUO Non-Compliance Notices (Government initiated)
Other Government-prepared documents
FOUO GOV ONLY
All Other Documents
FOUO Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on FOUO documents
a. Only FOUO documents being electronically uploaded into the eCMS (.docx, .xlsx, .pptx and others as appropriate), and associated paper documents described in the paragraph CONTRACT ADMINISTRATION require FOUO markings as indicated in the subparagraphs below.
b. FOUO documents that are originally created within the eCMS application using the web-based forms (RFIs, Daily Reports, and others as appropriate) will be automatically watermarked by the eCMS software, and these do not require additional markings.
c. FOUO documents must be marked "UNCLASSIFIED//FOR OFFICIAL USE ONLY" at the bottom of the outside of the front cover (if there is one), the title page, the first page, and the outside of the back cover (if there is one).
d. FOUO documents must be marked on the internal pages of the document as
"UNCLASSIFIED//FOR OFFICIAL USE ONLY"' at top and bottom.
e. Where Installations require digital photographs to be designated FOUO, place the markings on the face of the photograph.
f. For visual documentation, other than photographs and audio documentation, mark with either visual or audio statements as appropriate at both the beginning and end of the file.
1.7 QUALITY ASSURANCE
Requested Government response dates on Transmittals and Submittals must be in accordance with the terms and conditions of the Contract. Requesting
SECTION 01 31 23.13 20 Page 8 response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.
Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.
Not Used.
Not Used.
SECTION 01 32 16.00 20 - Page 1
SECTION 01 32 16.00 20
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
02/15
1.1 SUBMITTALS
approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Construction Schedule; G
SD-07 Certificates
Monthly Updates
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.
The acceptance of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet program.
SECTION 01 32 16.00 20 - Page 2
1.3.2 Schedule Submittals and Procedures
Submit Bar Chart Schedules and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
1.4 SCHEDULE MONTHLY UPDATES
Update the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
a. Narrative Report: Provide with schedule updates. Identify and justify;
(1) Progress made in each area of the project
(2) Critical Path
(3) Date/time constraint(s), other than those required by the contract
(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path
(5) Status of Contract Completion Date and interim milestones;
(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
(7) Description of current and future schedule problem areas.
Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.
1.5 3-WEEK LOOK AHEAD SCHEDULE
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.
Key the work plans to activity numbers when a NAS is required and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .