B08_Synopsis_Solicitation_(Attachment_1_Specifications).pdf
PDF 284 KB Posted
- Attached to
- PRECAST CONCRETE SHOWER HOUSE BIG SPRING Federal contract opportunity
- Solicitation number
- 140P6222Q0043
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Synopsis_Solicitation_140P6222Q0043_0002_0002.docx | DOCX document | |
| Sol_140P6222Q0043_Amd_0002.pdf | ||
| B11_Solicitation_Q_A_0001.docx | DOCX document | |
| B09_Solicitation_Amendment_(Pic_3)_0001.jpg | JPG image | |
| Sol_140P6222Q0043_Amd_0001.pdf | ||
| B09_Solicitation_Amendment_(Pic_2)_0001.jpg | JPG image | |
| B09_Solicitation_Amendment_(Pic_4)_0001.jpg | JPG image | |
| B09_Solicitation_Amendment_(Pic_1)_0001.jpg | JPG image | |
| Sol_140P6222Q0043.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications
All product/materials contained in the below sections are subject FAR Clause 52.211-6 Brand Name or Equal.
Despite a manufacturer and product being listed, it is a suggested product, but all products/materials are brand name or “or equal”. “Or equal” products must be presented with adequate technical drawings showing interior layout and dimensions.
Brand name or equivalent product must use manufacturer’s instructions and recommendations for product installation/application.
SPECIFICATIONS
Santiago BUILDING STYLE CXT Incorporated Santiago Flush/Shower Building Specifications
1.0 SPECIFICATIONS
ASTM C33 Concrete Aggregates ASTM C39 Method of Test for Compressive Strength of Cylindrical Concrete Specimens ASTM C94 Standard Specification for Ready-Mixed Concrete ASTM C143 Method of Test for Slump of Concrete ASTM C150 Standard Specification for Portland Cement ASTM C172 Standard Practice for Sampling Freshly Mixed Concrete ASTM A185 Standard Specification for Steel Welded Wire Reinforcement, Plain, or Concrete ASTM C192 Method of Making and Curing Test Specimens in the Laboratory ASTM C231 Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C309 Standard Specifications for Liquid Membrane-Forming Compounds for Curing Concrete ASTM C494 Standard Specification for Chemical Admixtures for Concrete ASTM A615 Standard Specification for Deformed and Plain Carbon-Steel Bar for Concrete Reinforcement ASTM C618 Standard Specification for Coal Fly Ash and Raw or Calcine Natural Pozzolan for Use in Concrete ASTM C979 Standard Specification for Pigments for Integrally Colored Concrete ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort ACI 211.1 Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete ACI 306 Cold Weather Concreting ACI 318 Building Code Requirements Structural Concrete and Commentary (includes Errata)
PCI MNL 116 Quality Control for Plants and Production of Precast Prestressed Concrete Products
2.0 MANUFACTURER CRITERIA
The manufacturer supplying the requested precast concrete flush facility must meet the following:
A. Manufacturer must be ISO 9001 certified at the time of bid.
B. Manufacturing plant must be PCI certified at the time of bid.
C. Manufacturer must not have defaulted on any contract within the last five (5) years.
D. Manufacturer must provide stamped, engineered drawings prior to acceptance.
E. Manufacturer must be pre-approved prior to bidding.
Flush/Shower Building Specifications F. Manufacturer must show four (4) examples of precast concrete flush facilities produced, installed and in use as an example of their ability to perform this contract.
G. Manufacturer shall provide a warranty against defects in material and workmanship for a period of one (1) year on all concrete components. The warranty is valid only when concrete is used within the specified loadings. Furthermore, said warranty includes only the related material necessary for the construction and fabrication of said concrete components.
H. UL 752 Bullet Resistance on 4” thick concrete samples.
3.0 DESIGN CRITERIA
The flush building must be designed to individually meet the following criteria. The design criteria are to ensure that the flush building not only will withstand the forces of nature listed below, but to provide protection from vandalism and other unforeseen hazards. Building’s structural and foundation design must be relevant to the region and properties associated with its final placement. Design must also meet all applicable accessibility and building code requirements. Buildings must also meet various structural loads such as below, but not limited to/or restricted by them.
A. Roof Snow Load
1. The flush building is designed to withstand a 250 PSF snow load.
B. Floor Load
1. The flush building is designed to withstand 400 PSF floor load.
C. Wind Load
1. The flush building will withstand the effects of 150 miles per hour (3-second gust) wind exposure C.
D. Earthquake
1. The flush building will withstand the effects of a seismic group 1 design category E earthquake.
E. Additional Design Standards
1. The flush building is designed to meet the accessibility requirements put forth by federal, state, and local statutes.
2. The flush building is an all concrete design with a minimum 3/12 roof pitch. The flush building shall have a minimum 4” wall, 4½” roof, and 5” floor thickness.
3. All wall to floor interior surface seams shall have a minimum 1” radius coving made of high strength grout.
+ Recycled Material + LED Lighting F. Precast shower house must have a total of 7 showers one being ADA and 1 chase door.
Showers are located on each end of the building and has men's bathroom, total of 2 stools, 1 urinal and 2 sinks on one side and women's, 3 stools and 2 sinks on the other side.
Must contain 3 wall heaters and each shower has a ceiling type panel heater along with the chase area containing the water heaters and access to all water/flush valves.
4.0 MATERIALS
A. Concrete – General
1. The concrete mix design must be designed to ACI 211.1 to produce concrete of good workability.
2. Concrete will contain a minimum of 675 pounds of cementitious material per yard. Cement must be a low alkali type I/II or III conforming to ASTM C-150.
3. Coarse aggregates used in the concrete mix design must conform to ASTM C33 with the designated size of coarse aggregate #67.
4. Maximum water/cement ratio will not exceed .45.
5. Air-entraining admixtures will conform to ASTM C260. Water reducing admixtures will conform to ASTM C494, Type A.
6. If Self Compacting Concrete (SCC) is used, it must conform to ASTM C1611.
B. Concrete Reinforcement
1. All reinforcing steel must conform to ASTM A615. All welded wire fabric will conform to
ASTM A185.
2. All reinforcement is new, free of dirt, oil, paint, grease, loose mill scale and loose or thick rust when placed.
3. Details not shown on drawings or specified are to ACI318.
4. Steel reinforcement is centered in the cross-sectional area of the walls and must have at least 1¼” of cover on the under surface of the floor.
5. The maximum allowable variation for center-center spacing of reinforcing steel is ½”.
6. Full lengths of reinforcing steel are used when possible. When splices are necessary on long runs, splices are alternated from opposite sides of the components for adjacent steel bars.
a. Lap bars under #4 a minimum of 12” bar diameters.
b. Lap bars larger than #4 a minimum of 24” bar diameters.
7. Reinforcing bars are bent cold. No bars partially embedded in concrete are field bent unless approved by the customer.
C. Caulking, Grout, Adhesive and Sealer
1. Interior and exterior joints are caulked with a paintable polyurethane sealant.
2. Grout must be a non-shrink type and are painted to match the color of surrounding concrete as nearly as possible.
3. Cement base coating must be formulated with a very fine aggregate system and is a built-in bonding agent.
D. Paint – MUST USE JAVA BROWN FOR ROOF AND DOORs and SAND BEIGE EXTERIOR
WALLS
1. All paints and materials must conform to all federal specifications or be similar “top-of-the-line-components.”
2. Type of paints for toilets.
a. Inside concrete surfaces.
i. Interior floors will be a chemical resistant urethane. The color will be gray.
Flush/Shower Building Specifications
ii. Interior walls and ceilings will be a modified acrylic, water repellent penetrating stain. The color will be white followed by a clear acrylic anti-graffiti sealer.
b. Metal surfaces both inside and out.
i. DTM ALKYD.
c. Exterior concrete surfaces.
i. Exterior slab will be clear sealer.
ii. Exterior walls and roof will be a water repellent penetrating stain in the same color as the walls or roof followed by a clear acrylic anti-graffiti sealer.
E. Grab Bars
1. Grab bars will be 18-gauge, type 304 stainless steel with 1½” clearance. Grab bars will each be able to withstand 300-pound top loading.
F. Toilet Paper Dispenser
1. Dispenser will be constructed of ¼” thick, type 304 stainless steel. Dispenser will be capable of holding three (3) standard rolls of toilet paper. Toilet paper holder fastening system will be able to withstand 300-pound top loading.
G. FRP Doors and Jams
1. Doors will be flush FRP,
2. Door frames FRP. Three (3) rubber door silencers will be provided on latch side of frame.
H. Door Hinges
1. Door hinges will be three (3) per door with dull chrome plating 4½” x 4½”, adjustable tension, and automatic closing for each door.
I. Lockset
1. Lockset will meet ANSI A156.2 Series 4000, Grade 1 cylindrical lockset for exterior door.
MUST USE BEST CORE LOCK SYSTEM
2. Lever handle both inside and out.
3. U.S. 26D finish.
J. Dead Bolt
1. Certified ANSI/BHMA A156.5-2001 Grade 1.
2. Heavy duty tamper resistant.
3. 2¾” backset.
4. U.S. 26D finish.
K. Doorstop
1. Doorstop will be a dome style stop meeting ANSI 156.16.
L. Double Coat Hook
1. Coat hook will be 304 stainless steel 16-gauge (1.5mm), formed construction with a satin finish and have ³₁̷₆” x ⅞” nail in anchor. Upper hook will extend at least 2½” from the wall.
Lower hook will extend at least 1¼” from the wall.
M. Door Sweep
1. Door sweep will be provided at the bottom of door and will be an adjustable brush type.
Flush/Shower Building Specifications N. Wall Vent
1. Wall vent will be crank operated allowing the unit to be opened or closed. Crank will be removable. Vent cover will be 14-gauge 304 stainless steel and anchored into the concrete wall with high strength anti-rust tap con fasteners. Vent to come with insect screen. Cover to be recessed a minimum ¾” on exterior walls with a 45-degree bevel. Interior to be flush mounted. Wall vent will not protrude from the wall.
O. Signs
1. Signs to have raised pictograms, letters, and braille to meet ADA.
P. Windows
1. Window frames will be constructed from steel.
2. Window glazing will be ³₁̷₆” thick translucent pebble finished mar-resistant Lexan.
3. Windows to have ¾” recess with 45-degree bevel.
4. Window frames to have vandal resistant fasteners.
Q. Mirrors
1. Mirror to be 18” x 36” frameless 430 18-gauge stainless steel with #8 bright polish.
R. Stall and Stall Doors
1. Stall doors to be solid HDPE in matching white color.
2. Stalls to be made from concrete matching wall finish.
S. Shower Section Benches
1. Shower benches to be heavy duty, type 304 satin finish stainless steel with phenolic slats.
T. Plumbing Flush Section/Room
1. All fixtures to meet ANSI A112.19.2.
2. Plumbing will be concealed in the service area.
3. Flush valve – Concealed closet flush-o-meter constructed of rough brass. Furnish valve with integral vacuum breaker and wall mounted push button. Valve will be of a water saver type.
Water closet with a flow of 1.6 gallons per flush. Urinal with a flow of .5 gallons per flush.
4. Hammer arrester – Installed on water line.
5. Hose bib – Available in the chase area.
6. Lavatory – Vitreous china with back splashguard, front overflow opening, equipped with brass trap and drainpipe without stopper. Sink will be 20” wide x 18” front to back x 5¾” deep with ADA trap cover.
7. Main shut-off valve and drain.
8. Toilet – Constructed of vitreous china, wall hung, with siphon jet action. Toilet will have a back spud for a concealed flush valve connection and will be mounted with the top of the seat 18” above the finished floor. Seat will be heavy duty solid plastic with an open front.
9. Urinals will be constructed of vitreous china, wall hung with siphon jet action. Urinal will have a back spud for a concealed flush valve connection and will be mounted at proper height per code.
10. Trap primer distribution unit.
11. Waste and vent material – ABS or PVC plastic and will be plumbed to meet Uniform Building Codes.
12. Water material – Copper tubing Type L, hard drawn. A gate valve will be provided at the inlet end of the water line. All water lines will be of a size to provide proper flushing action based on a nominal water pressure of 40 psi.
13. Water valve – Self-closing water set with indexed push button.
14. Water heater (80 GAL) – High efficiency commercial grade water heater(s) provided per code.
U. Plumbing Shower Section/Room
1. Shower control unit – 14-gauge, type 304 stainless steel recessed shower panel with 2.5 gpm flow rate, pressure balancing valve, recessed soap dish and integral stainless steel shower head.
2. ADA shower control unit – 14-gauge, type 304 stainless steel recessed shower panel with
2.5 gpm flow rate, pressure balancing valve, recessed soap dish, high low diverter valve, and high low integral stainless steel shower heads.
3. Water heater – High efficiency commercial grade water heater(s) (80GAL) provided per code.
V. Electrical
1. All components must be UL listed.
2. Breaker panel – Sized to meet load requirements and mounted to meet electrical code.
3. Interior lighting – Vandal resistant fixtures with built-in occupancy sensor, energy efficient LED lights.
4. Exterior lighting – Vandal resistant fixtures with built-in photoelectric switch, energy efficient LED lights.
5. Exhaust fans – All wet location motion activated with speed control in chase area to control
CFM.
6. Wiring – Conduit, surface mounted in the service area and concealed in the user compartments. All wire will be copper.
7. Heaters will be 1500 Watt: 3 - quantity
8. GFI outlets provided per code requirements.
5.0 MANUFACTURE
A. Finishing Concrete
1. All exterior building walls and exterior screen walls will be cast to simulate- Barnwood.
2. All exterior surfaces of the roof panels will be cast to simulate Cedar shake. The underside of the overhang will have a smooth finish.
B. Cracks and Patching
1. Cracks in concrete components which are judged to affect the structural integrity of the building will be rejected.
2. Small holes, depressions, and air voids will be patched with a suitable material. The patch will match the finish and texture of the surrounding surface.
3. Patching will not be allowed on defective areas if the structural integrity of the building is affected.
6.0 FINISHING AND FABRICATION
A. Structural Joints
1. Wall components will be joined together with two (2) welded plate pairs at each joint. Each weld plate will be 6” long and located one (1) pair in the top quarter and one (1) pair in the bottom quarter of the seam. Weld plates will be anchored into the concrete panel and welded together with a continuous weld.
2. The inside seams will be a paintable caulk. The outside seams will use a caulk in a coordinating building color or clear.
3. Walls and roof will be joined with weld plates, 3" x 6" at each building corner.
4. The joint between the floor slab and walls will be joined with a grout mixture on the inside, a matching-colored caulk on the outside and two (2) weld plates 6” long per wall.
B. Painting/Staining
1. An appropriate curing time must be allowed before paint is applied to concrete.
2. Schedule of finishes.
a. Inside concrete surfaces.
i. Inside floors must be one (1) coat of 1-part water based chemical resistant urethane.
ii. Interior walls and ceilings must be two (2) coats of a modified acrylic, water repellent penetrating stain, followed by one (1) coat of clear sealer.
b. Metal surfaces both inside and out.
i. Two (2) coats of DTM ALKYD.
c. Exterior concrete surfaces.
i. Exterior walls must be two (2) coats of water repellent penetrating stain in the same color as the walls or roof followed by 1 coat of clear acrylic anti-graffiti sealer.
7.0 TESTING
Testing must be performed by qualified individuals who have been certified ACI Technician Grade 1. Sampling will be in accordance with
ASTM C172.
A. The air content of the concrete must be checked per ASTM C231 on the first batch of concrete.
The air content will be in the range of 5.0% +/- 2.0%.
B. The compressive strength of the cylinders must be tested to ASTM C39. (1) cylinder for release, one (1) for seven (7) days and one (1) for 28 days. The release must be a minimum strength of 2500 psi, the 7-day must be a minimum of 4500 psi and the 28-day must be a minimum of 5000 psi.
C. A copy of all test reports must be available to the customer as soon as 28-day test results are available.
8.0 INSTALLATION
A. Scope of Work
1. Work specified under this section relates to the placement of the unit by the Supplier on customer prepared foundations. See Installation Specifications or by others.
B. Location
1. It is the responsibility of the customer to:
a. Provide exact location by stakes or other approved method.
b. Provide clear and level site free of overhead and/or underground obstructions. See Installation Questionnaire for details.
c. Provide access to the site for truck delivery and sufficient area for the crane to install and the equipment to perform the contract requirements. See Installation Questionnaire for details.
d. Water, electrical, and sewage site connections to be placed per Manufacturer drawings. Must be placed to easily connect to the building. See Installation Questionnaire for details.
C. Compacting
1. The bottom of the area must be compacted after it has been dug out. After the base has been placed, it must be compacted as well. The bearing of the soil and base should be a minimum of 1,500 pounds per square foot.
D. Base
1. After compacting the bottom of the area, a minimum of 6” thick and consist of ¾” minus crushed rock (i.e. road base material) compacted to 95% of optimal density in accordance with ASTM D1557. Finished surface of sub-base shall be flat and level, with a maximum deviation of -½”, +0” from a true horizontal plane.
2. The base should be placed for support, leveling and drainage purposes, and also to limit frost action. The base must be confined so as to prevent washout, erosion, or any other undermining.
E. Access to Site
1. Delivery to site made on normal highway trucks and trailers. If at the time of delivery conditions of access are hazardous or unsuitable for truck and equipment due to weather, physical constraints, roadway width or grade, Manufacturer may require an alternate site with better access provided to ensure a safe and quality installation. In any such case, additional costs for cranes, trucking, etc. will be charged to the account of the customer. See Installation Questionnaire for details.
9.0 WARRANTY
Manufacturer must provide a one (1) year warranty.
For reference purposes, this photo below shows the suggested Manufacturer Incorporated- “Santiago Shower Restroom”. Brand Name or Equivalent products are acceptable for this solicitation.