B08_-_Submittals_-_23-021.pdf
PDF 67 KB Posted
- Attached to
- CO-NATL EAGLE & WPR-BATHROOM FLOOR DRAIN Federal contract opportunity
- Solicitation number
- 140FC123Q0023
About this file
This document outlines a projected submittal list for a bathroom floor drain replacement project at the National Eagle and Wildlife Property Repository. Key details include a requirement for contractors to submit construction schedules, materials for drain pipes and floor drains, concrete mix designs, tile and grout samples, water pipe materials for trap primers, and closeout documents. Review and approval of submittals will be indicated using designations A through E, denoting either approval, approval with notes, no action taken with comments, or disapproval with comments. The related federal contract opportunity is solicitation number 140FC123Q0023 from the Department of the Interior Fish and Wildlife Service for bathroom floor drain replacements at the National Eagle and Wildlife Property Repository.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FC123Q0023_Amd_0001.pdf | ||
| B08_-_Existing_Conditions_Photos_(Compressed).pdf | ||
| B08_-_USFWS_Eagle_Repository_Drawings_(Compressed).pdf | ||
| B08_-_Bid_Schedule_-_23-021.pdf | ||
| B08_-_Statement_of_Work_23-021.pdf | ||
| B03_-_DOL_Wage_Determination_(7-18-23).pdf | ||
| Sol_140FC123Q0023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET 1 OF 1
PROJECT NAME: BATHROOM FLOOR DRAIN REPLACEMENTS ENGR. PROJECT NO.: 23-021
LOCATION: NATIONAL EAGLE AND WILDLIFE PROPERTY REPOSITORY CONTRACT NO.:
CONTRACTOR:
Spec.
Section Number
Spec.
Paragraph No. Comments
SOW VI.E
SOW VIII
SOW VIII
SOW VIII
SOW VIII
SOW VIII
SOW XI.A
Water Pipe Materials for Trap Primer
Tile and Grout Concrete Mix Closeout documents
PROJECTED SUBMITTAL LIST
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)
Construction schedule Drain Pipe Materials
Floor Drain
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
D - No Action Taken. See Comments. Resubmission Required.
E - disapproved. See Comments. Resubmission Required.