B08_-_SolicitationB0003_Atch1Specifications.pdf

PDF 1 MB Posted

Attached to
Replace Peavine and Big Spring Pavilions Federal contract opportunity
Solicitation number
140P6221B0003
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This solicitation package includes specifications for replacing two picnic pavilions at Ozark National Scenic Riverways in Missouri. The project scope involves demolishing existing structures destroyed in a 2017 flood and constructing new pavilions of similar size designed to withstand natural disasters. Specifications cover concrete, structural steel, rough carpentry, exterior finish carpentry, shingles, flashing, staining, electrical systems, and site work including clearing, earthmoving, paving, and turf installation. The period of performance is approximately 120 calendar days. The pre-bid meeting date is not provided. The response due date and award date are not stated.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Peavine and Big Spring Pavilions, newest first.
File Type Posted
B09_-_SolicitationAmendment3_Atch8_B0003_0003.pdf PDF
Sol_140P6221B0003_Amd_0003.pdf PDF
Sol_140P6221B0003_Amd_0002.pdf PDF
Sol_140P6221B0003_Amd_0001.pdf PDF
B09_-_SolicitationAmendment1_Atch7_0001.pdf PDF
B08_-_SolicitationB0003_Atch6CPARS.pdf PDF
B08_-_SolicitationB0003_Atch5SF24BidBond.pdf PDF
B08_-_SolicitationB0003_Atch4OF17.pdf PDF
B08_-_SolicitationB0003_Atch3WageDetermination.pdf PDF
Sol_140P6221B0003.pdf PDF
B08_-_SolicitationB0003_Atch2Drawings.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OZARK NATIONAL SCENIC RIVERWAYS

VAN BUREN, MISSOURI

REPLACE PEAVINE & BIG SPRING SHELTERS

PMIS 253636

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

MARCH 23, 2021

140P6221B0003 Attachment 1 Page 1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements

DIVISION 02 – EXISTING CONDITIONS

Section 02 41 19 – Selective Demolition

DIVISION 03 – CONCRETE

Section 03 30 00 – Cast-In-Place Concrete

DIVISION 05 – METALS

Section 05 12 00 – Structural Steel Framing

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

Section 06 10 63 – Exterior Rough Carpentry Section 06 20 13 – Exterior Finish Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 31 36 – Synthetic Shake Shingles Section 07 62 00 – Sheet Metal Flashing and Trim

DIVISION 09 – FINISHES

Section 09 93 00 – Staining and Transparent Finish

DIVISION 26 – ELECTRICAL

Section 26 05 19 – Low-Voltage Electrical Power Conductors and Cables Section 26 05 33 – Raceways and Boxes for Electrical Systems Section 26 05 53 – Identification for Electrical Systems Section 26 28 16 – Enclosed Switches and Circuit Breakers

DIVISION 31 – EARTHWORK

Section 31 10 00 – Site Clearing Section 31 20 00 – Earth Moving

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 13 00 – Concrete Paving Section 32 17 23 – Pavement Markings Section 32 92 00 – Turf and Grasses

CONSTRUCTION DOCUMENTS

Drawings are provided as a separate pdf document.

Existing site photographs are included in Appendix A of the specifications package.

140P6221B0003 Attachment 1 Page 2

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: This project is to replace two picnic pavilions located in the Big Spring District of the Ozark national Scenic Riverways. Both the Peavine and Big Spring pavilions were destroyed during the devastating April 2017 Flood event. This project will replace the picnic pavilions, which have already been demolished, with a more sustainable designed structure that could withstand the destructive forces of nature to a greater degree. These pavilions will be designed to complement the existing "CCC" era architecture that the Big Spring District is known for. The pavilions built will be approximately the same size as those destroyed. The Peavine Pavilion and the Big Spring Pavilion will be designed as identical structural and architectural design of the shelter with site-specific landscape design to address associate features including a water fountains, barbeque grills, and fire pits.

1.2 Work Covered by the Contract Documents:

A. Project Location: The Peavine (#428) and Big Spring Shelters (#425) are located near Big Spring along the Current River, approximately 5 miles south of Van Buren, Missouri.

B. All work will be performed under a single contract.

C. Period of performance (POP): Work shall be completed within approximately one hundred and twenty (120) calendar days from issuance of the Notice to Proceed. The period of performance includes: Forty (40) days for shop drawings and material delivery, sixty (60) days on site to substantial completion, six (6) weather days, and fourteen (14) days for final completion.

ITEM 2 - EXISTING UTILITIES

2.1 Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

2.3 Water service shall be maintained throughout construction.

2.4 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

140P6221B0003 Attachment 1 Page 3

A. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

B. Hours for Utility Shutdowns: Shut downs shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

A. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Pubic Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the Contracting Officer. Submit requests for work outside of the stated normal business hours to the Contracting Officer for approval at least 48 hours in advance of the work.

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to the immediate project site identified in site plans. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Staging area will be coordinated with COR and identified during pre-construction conference.

C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

D. Limit site disturbance, including earthwork and clearing of vegetation, to:

1. 40 feet beyond pavilion perimeter.

2. 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter.

3. 15 feet beyond primary roadway curbs and main utility branch trenches.

140P6221B0003 Attachment 1 Page 4

4. 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

E. Security and Protection facilities installation:

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR.

4. Site Enclosure: Before construction operations begin, furnish and install flexible orange construction fence in a manner that will prevent people and animals from easily entering site and or storage areas.

a. Extent of Fence: As required to enclose portion determined sufficient to accommodate construction operations and storage

b. Locate vehicular openings to avoid interference with traffic on public thoroughfares.

c. Locate pedestrian entrance openings as required to provide controlled personnel entry.

3.4 Storage - Staging Areas:

A. Confine storage of materials and equipment to the project area. The parking lot will be available for storage. Limits of use and control shall be subject to Contracting Officer’s approval. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Storage and staging areas shall be identified by COR during preconstruction conference.

3.5 Preservation of Natural Features: NOT USED

3.6 Hauling Restrictions: Match State and County road requirements for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all

140P6221B0003 Attachment 1 Page 5 hazardous rubbish. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work.

B. Dispose of waste materials legally using Contractor provided dumpsters.

3.8 Occupancy Requirements for Buildings: NOT USED

3.9 Photo Documentation: All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

A. Existing Condition Images: Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

B. Construction Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with enough overall field view to show location and then details.

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety: As a minimum, conduct one weekly 15-minute "toolbox" safety meetings.

These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

B. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the COR.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management:

A. Noise Control: Perform demolition and re-roof operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer.

B. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.

140P6221B0003 Attachment 1 Page 6

1. Do not exceed the following dB(A) limitations at 50 feet:

Sound Level in dB(A) Time Duration of Impact Noise 70 More than 12 minutes in any hour 80 More than 3 minutes in any hour

2. Maximum permissible construction equipment noise levels at 50 feet:

EARTHMOVING dB(A) MATERIALS HANDLING dB(A) Compressors 75 Pneumatic Tools 80 Pumps 75 Saws 75 Generators 75 Vibrators 75

C. Ambient Noise:

1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:

a. Residential receiving area :

Daytime: 65 dB Nighttime: 45 dB

b. Commercial/Industrial receiving area:

Daytime: 67 dB Nighttime: 65 dB

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract. (Block 11 of the SF 1442 or relevant section of the award document)

ITEM 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

All bidders will be held to have the same knowledge concerning the site and the on ground conditions as if they had inspected the job site. No change orders will be approved for work obvious during a site visit. Please see FAR 52.236-27 - Site Visit (Construction).

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, which may be used in the Construction Specifications or Special Provisions, refer to the organizations and specifications of the organizations may be found at the following link: https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.

A. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment in good repair at all times.

As a minimum, maintain four hard hats and all other APP required equipment.

7.2 Submittals:

140P6221B0003 Attachment 1 Page 7 https://www.nps.gov/orgs/1671/do-business-with-us.htm

A. Accident Prevention Program: At the preconstruction conference submit for approval an accident prevention program. The program shall include:

1. Name of responsible supervisor to carry out the program

2. First aid procedures

3. Training, both initial and continuing

4. Planning for possible emergency situations

5. Contractor to identify nearest location of medical facility for emergencies

6. Recognition that work will be performed in remote areas with limited communication or cell phone coverage

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections. The Contractor shall document the “toolbox” meetings through the daily logs.

7.3 Qualification of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the Contracting Officer or designee as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Protective Equipment: It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

140P6221B0003 Attachment 1 Page 8

ITEM 8 - PRECONSTRUCTION CONFERENCE: See FAR 52.236-26

ITEM 9 - SUBMITTALS

9.1 General Submittal Procedures:

A. General: Prepare and submit submittals required by individual Specification Sections.

Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit all transmittal to Contracting Officer.

B. Submittal List: A submittal list has been attached to the end of this Specification Section.

The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.

C. Preconstruction Conference Submittal: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Indoor Air Quality (IAQ) Management Plan.

12. Contractors Commissioning Plan.

13. Historic Preservation Treatment Plan.

14. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

140P6221B0003 Attachment 1 Page 9

9.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.

A. Shop Drawings: Indicate waterproofing and electrical materials, connection details, anchorage spacing, hardware locations, and installation details.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction, anchorage method, hardware, etc.

1. Submit Product Data according to Part 9.1 of this section to include one digital file

(.PDF or .TIF) to COR.

C. Samples: Submit all samples as specified in each section’s requirements.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer at least 10 days before need for approval.

E. After approving submittals, Contracting Officer will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: Refer to FAR 52.211-6 - If an item in this solicitation is identified as “brand name or equal” or lists more than 3 manufacturers, the purchase description reflects the characteristics and level of quality that will satisfy the Government’s needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

140P6221B0003 Attachment 1 Page 10

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Progress Schedules: As soon as possible after Notice of Award and before beginning any work, submit Progress Schedule. Contracting Officer will review the Progress Schedule for format and content. Submit a digital copy (PDF) of Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted. The following information must accompany submission of progress schedules prior to processing any pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values will be provided by the Contracting Officer.

ITEM 10 – TEMPORARY SERVICES

10.1 Description: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.

10.2 Fire Prevention and Protection:

A. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

10.3 Restroom Facilities: Contractor responsible for providing port-a-john facilities for the project sites. Coordinate with COR for approval of storage location of facilities prior to delivery.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.

11.3 Substantial Completion and Final Inspection: Submit written certification that project is substantially complete, and a final inspection must be requested to the Contracting Officer in

140P6221B0003 Attachment 1 Page 11 writing. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be substantially complete, following the final inspection, the.

Contracting Officer will prepare a Punch List and issue a Letter of Substantial Completion.

B. If the work is not determined to be substantially complete following the final inspection, the Contracting Officer will notify Contractor in writing. Contractor shall request a new final inspection after completing the work. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, documented weather permitting.

D. If Contracting Officer determines that the work is not substantially complete; he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

E. If Contractor completes all items of work on the Punch List and all contractually required items, Contracting Officer will issue Letter of final acceptance of work.

F. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

G. Disposition of any permits and warranties required by the specifications in this section.

11.4 Acceptance of the Work: After all deficiencies have been corrected, a Letter of Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of Substantial Completion.

B. Provide All Warranty information of products installed organized by Division. All contact information, extents and conditions shall be clearly noted as well as date of overall project Substantial Completion.

C. Information shall include operation and maintenance manuals for each warranted material.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

140P6221B0003 Attachment 1 Page 12

SECTION 02 41 19

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected site elements.

2. Salvage of existing items to be reused or recycled.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to NPS that may be uncovered during demolition remain the property of

NPS.

1. Carefully salvage in a manner to prevent damage and promptly return to NPS.

1.3 PREINSTALLATION MEETINGS

A. Pre-demolition Conference: Conduct conference at Project site.

1.4 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, and for environmental protection. Indicate proposed locations and construction of barriers.

B. Schedule of selective demolition activities with starting and ending dates for each activity.

C. Pre-demolition photographs or video.

1.5 CLOSEOUT SUBMITTALS

A. Inventory of items that have been removed and salvaged.

1.6 FIELD CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by NPS as far as practical.

B. Notify COR of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

140P6221B0003 Attachment 1 Page 13

1. If suspected hazardous materials are encountered, do not disturb, immediately notify the COR. Hazardous materials will be removed by NPS under a separate contract.

D. Storage or sale of removed items or materials on site is not permitted.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

F. Arrange selective demolition schedule so as not to interfere with NPS operations.

1.7 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Inventory and record the condition of items to be removed and salvaged.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing: Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing: Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. COR will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove plumbing and components indicated on Drawings to be removed.

140P6221B0003 Attachment 1 Page 14

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

3.3 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Remove temporary barricades and protections where hazards no longer exist.

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Do not use cutting torches until work area is cleared of flammable materials. Maintain portable fire-suppression devices during flame-cutting operations.

2. Maintain fire watch during and for at least 8 hours after flame-cutting operations.

3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on walks, driveways, lawn, etc.

4. Dispose of demolished items and materials promptly. Comply with waste disposal requirements in Section 011000 “Division 01 General Requirements.”

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to NPS.

4. Transport items to NPS storage area designated by COR.

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by COR, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demotion operations are complete.

140P6221B0003 Attachment 1 Page 15

3.5 CLEANING

A. Remove demolition waste materials from Project site and recycle or dispose of them according to, and complying with requirements outlined in Section 011000 “Division 01 General Requirements.”

1. Do not allow demolished materials to accumulate on site.

2. Remove and transport debris in a matter that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

140P6221B0003 Attachment 1 Page 16

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Cast-in-place concrete, including concrete materials, mixture design, placement procedures, and finishes for the following:

a. Footings.

b. Exterior Slabs.

c. Exposed slabs and toppings.

1.2 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, and other pozzolans materials subject to compliance with requirements.

B. Water/Cement Ratio (w/cm): The ratio by weight of water to cementitious materials.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at project site.

1. Before submitting design mixtures, review concrete design mixture and examine procedures for ensuring quality of concrete materials. Require representatives of each entity directly concerned with cast-in-place concrete to attend, including the following:

a. Contractor’s superintendent.

b. Independent testing agency responsible for concrete design mixtures.

c. Ready-mix concrete manufacturer.

d. Concrete subcontractor.

2. Review special inspection and testing and inspecting agency procedures for field quality control, concrete finishes and finishing, cold- and hot-weather concreting procedures, curing procedures, forms and form removal limitations, anchor rod and anchorage device installation tolerances, steel reinforcement installation, floor and slab flatness and levelness measurement and concrete protection.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Prepared by, and signed and sealed by, a qualified professional engineer (licensed in the state of Missouri) responsible for their preparation, detailing, fabrication, assembly, and support of cast-in-place concrete and reinforcements.

140P6221B0003 Attachment 1 Page 17

1. Steel Reinforcement Shop Drawings: Comply with ACI SP-066. Include placing drawings that detail fabrication, bending, and placement. Include bar sizes, lengths material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.

2. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.

a. Location of construction joints is subject to approval of the Architect.

3. Indicate location of waterstops.

C. Design Mixtures: For each concrete mixture, submit the following:

1. Mixture identification.

2. Minimum 28-day compressive strength.

3. Durability exposure class.

4. Maximum w/cm.

5. Calculated equilibrium unit weight, for lightweight concrete.

6. Slump limit.

7. Air content.

8. Nominal maximum aggregate size.

9. Indicate amounts of mixing water to be withheld for later addition at Project site if permitted.

10. Intended placement method.

11. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

D. Samples: For waterstops.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For testing agency.

B. Material Certificates: For each of the following, submit the products to be used and certificates signed by manufacturers:

1. Cementitious materials.

2. Admixtures.

3. Steel reinforcement and accessories.

4. Waterstops.

5. Curing compounds.

6. Bonding agents.

7. Adhesives.

8. Joint-filler strips.

9. Repair materials.

C. Material Test Reports: For the following, from a qualified testing agency:

1. Aggregates.

2. Steel Reinforcement:

a. For reinforcement to be welded, mill test analysis for chemical composition and carbon equivalent of the steel in accordance with ASTM A706/A706M.

140P6221B0003 Attachment 1 Page 18

D. Field quality-control reports.

E. Minutes of preinstallation conference.

F. Welding certificates.

1. Reinforcement to Be Welded: Welding procedure specification in accordance with AWS D1.4/D1.4M.

2. Contractor must submit a Hot Works permit to COR, providing minimum 24-hour notice of any welding work on site.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: A qualified installer who employs on project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified Concrete Flatwork Technician. Experienced installer shall have also completed concrete work similar in material, design, and extent to that indicated for this project and whose work has resulted in construction with a record of successful in-service performance.

B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94/C94M requirements for production facilities and equipment.

1. Manufacturer certified according to NRMCA’s “Certification of Ready Mixed Concrete Production Facilities.”

C. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing Technician, Grade I, according to ACI CP-1 or an equivalent certification program.

2. Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing Technician and Concrete Laboratory Testing Technician – Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician – Grade II.

D. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer’s plant, obtain aggregate from single source, and obtain admixtures from single source from single manufacturer.

E. Welding Qualifications: Qualify procedures and personnel in accordance with AWS D1.4/D1.4M.

1.7 PRECONSTRUCTION TESTING

A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on each concrete mixture.

1. Include the following information in each test report:

a. Admixture dosage rates.

b. Slump.

c. Air content.

d. Seven-day compressive strength.

e. 28-day compressive strength.

140P6221B0003 Attachment 1 Page 19

1.8 DELIVERY, STORAGE, AND HANDLING

A. Comply with ASTM C94/C94M and ACI 301 (ACI 301M).

B. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage.

C. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.

1.9 FIELD CONDITIONS

A. Cold-Weather Placement: Comply with ACI 301 (ACI 301M) and ACI 306.1.

B. Hot-Weather Placement: Comply with ACI 301 (ACI 301M) and ACI 305.1 (ACI 305.1M).

PART 2 - PRODUCTS

2.1 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

1. Plywood, metal, or other approved panel materials.

2. Exterior-grade plywood panels, suitable for concrete forms, complying with DOC PS 1, and as follows:

a. Medium-density overlay, Class 1 or better; mill-release agent treated and edge sealed.

B. Rough-Formed Finished Concrete: Plywood, lumber, metal or another approved material.

Provide lumber dressed on at least two edges and one side for tight fit.

C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch, minimum.

D. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.

1. Formulate form-release agent with rust-inhibitor for steel form-facing materials.

E. Form Ties: Factor-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.

1. Furnish units that will leave no corrodible metal closer than 1-1/2 inch to the plane of exposed concrete surface.

2. Furnish ties that, when removed, will leave holes no larger than 1 inch in diameter in concrete surface.

140P6221B0003 Attachment 1 Page 20

2.2 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.

B. Low-Alloy Steel Reinforcing Bars: ASTM A 706/A 706M, deformed.

C. Plain-Steel Wire: ASTM A 82/A 82M.

2.3 REINFORCEMENT ACCESSORIES

A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut true to length with ends square and free of burrs.

B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI’s “Manual of Standard Practice,” of greater compressive strength than concrete and as follows:

1. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless steel bar supports.

2.4 CONCRETE, GENERAL

A. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 301 (ACI 301M).

2.5 CONCRETE MATERIALS

A. Cementitious Materials: Use the following cementitious materials, of the same type, brand, and source, throughout Project.

1. Portland Cement: ASTM C150/C150M, Type V. Supplement with the following:

a. Fly Ash: ASTM C618, Class C or F.

B. Normal-Weight Aggregates: ASTM C33/C33M, Class 4S coarse aggregate or better, graded.

Provide aggregates from a single source with documented service record data of at least 10 years’ satisfactory service in similar applications and service conditions using similar aggregates and cementitious materials.

1. Maximum Coarse-Aggregate Size: 1-inch nominal.

2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

C. Air-Entraining Admixture: ASTM C260/C260M.

D. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C494/C494M, Type A.

2. Retarding Admixture: ASTM C494/C494M, Type B.

3. Water-Reducing and -Retarding Admixture: ASTM C494/C494M, Type D.

140P6221B0003 Attachment 1 Page 21

4. High-Range, Water-Reducing Admixture: ASTM C494/C494M, Type F.

E. Water and Water Used to Make Ice: ASTM C94/C94M, potable.

2.6 WATERSTOPS

A. Flexible PVC Waterstops: CE CRD-C 572, for embedding in concrete to prevent passage of fluids through joints. Factory fabricate corners, intersections, and directional changes.

1. Profile(s): Base seal and flat, dumbbell with center bulb.

2. Dimensions: 4 inches by 3/16 inch thick; nontapered.

2.7 CURING MATERIALS

A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) when dry.

C. Moisture-Retaining Cover: ASTM C171, polyethylene film burlap-polyethylene sheet.

1. Color:

a. Ambient Temperature Below 50 deg F (10 deg C): Black.

b. Ambient Temperature between 50 deg F (10 deg C) and 85 deg F (29 deg C): Any color.

c. Ambient Temperature Above 85 deg F (29 deg C): White.

D. Curing Paper: Eight-feet- (2438-mm-) wide paper, consisting of two layers of fibered kraft paper laminated with double coating of asphalt.

E. Water: Potable or complying with ASTM C1602/C1602M.

2.8 RELATED MATERIALS

A. Expansion- and Isolation-Joint-Filler Strips: ASTM D1751, asphalt-saturated cellulosic fiber or ASTM D1752, cork or self-expanding cork.

B. Floor Slab Protective Covering: Eight-feet- (2438-mm-) wide cellulose fabric.

2.9 REPAIR MATERIALS

A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch and that can be feathered at edges to match adjacent floor elevations.

1. Cement Binder: ASTM C 150, Portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

2. Primer: Product of underlayment manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to ¼ inch or coarse sand as recommended by underlayment manufacturer.

4. Compressive Strength: Not less than 4100 psi at 28 days when tested according to

ASTM C 109/C 109M.

140P6221B0003 Attachment 1 Page 22

B. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from ¼ inch and that can be filled in over a scarified surface to match adjacent floor elevations.

1. Cement Binder: ASTM C 150, Portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as recommended by topping manufacturer.

4. Compressive Strength: Not less than 5000 psi at 28 days when tested according to

ASTM C 109/C 109M.

2.10 CONCRETE MIXTURES, GENERAL

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, in accordance with ACI 301.

1. Use a qualified testing agency for preparing and reporting proposed mixture designs, based on laboratory trial mixtures.

B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:

1. Fly Ash or Other Pozzolans: 25 percent by mass.

C. Admixtures: Use admixtures in accordance with manufacturer's written instructions.

1. Use water-reducing admixture in concrete, as required, for placement and workability.

2. Use water-reducing and -retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

3. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, and concrete with a w/cm below 0.50.

2.11 CONCRETE MIXTURES

A. Class A: Normal-weight concrete used for exterior slabs, footings, grade beams, and tie beams.

1. Minimum Compressive Strength: 4500 psi at 28 days.

2. Maximum w/cm: 0.45.

3. Slump Limit: 4 inches, plus or minus 1 inch.

4. Air Content: 6 percent, plus or minus 1.0 percent at point of delivery for nominal maximum aggregate size.

5. Limit water-soluble, chloride-ion content in hardened concrete to 0.06 percent by weight of cement.

2.12 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI’s “Manual of Standard Practice.”

140P6221B0003 Attachment 1 Page 23

2.13 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete in accordance with ASTM C94/C94M and furnish batch ticket information.

1. When air temperature is between 85 and 9 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

PART 3 - EXECUTION

3.1 FORMWORK

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

C. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows:

1. Class A, 1/8 inch for smooth-formed finished surfaces.

D. Construct forms tight enough to prevent loss of concrete mortar.

E. Fabricate forms for easy removal without hammering or prying against concrete surfaces.

Provide crush or wrecking plates where stripping may damage cast concrete surfaces.

Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

1. Install keyways, reglets, recesses, and the like, for easy removal.

2. Do not use rust-stained steel form-facing material.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible.

This is the start of the file's text. The full file is on GovTribe.