This document is a technical questionnaire for a solicitation to replace the HVAC system at the Visitor Center building of the Lincoln Home National Historic Site in Springfield, Illinois. Offerors are asked to provide details on their technical approach, key personnel, relevant project experience, and proposed construction schedule. The technical approach section requires a five-page narrative describing the offeror's means and methods for completing the HVAC system replacement work according to the project specifications and drawings within the proposed contract period and budget. Key personnel resumes should be submitted for positions including project manager, superintendent, construction management staff, on-site quality control specialist, and on-site safety specialist/manager. The project experience section asks for a minimum of three and maximum of five relevant HVAC system replacement projects completed in the last seven years. A proposed construction schedule for this specific project showing completion within the required period of performance must also be submitted along with a supporting narrative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6222R0004_Amd_0001.pdf | ||
| B08_-_Solicitation_140P6222R0004_Attachment_7_Certification_of_Vaccination_Form.pdf | ||
| B08_-_Solicitation_140P6222R0004_Attachment_1_Specifications.pdf | ||
| B08_-_Solicitation_140P6222R0004_Attachment_3_Wage_Determination.pdf | ||
| B08_-_Solicitation_140P6222R0004_Attachment_6_Vaccination_Certification.pdf | ||
| B08_-_Solicitation_140P6222R0004__Attachment_4_PPQ.pdf | ||
| B08_-_Solicitation_140P6222R0004_Attachment_2_Drawings.pdf | ||
| Sol_140P6222R0004.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONNAIRE
Visitor Center HVAC System Replacement
Lincoln Home National Historic Site
OFFEROR:
SOLICITATION #:
DATE:
PLEASE NOTE: IN ADDITION TO PRICING PROVIDED ON THE BID/PRICE SCHEDULE, YOUR
RESPONSES ON THIS QUESTIONNAIRE (AND YOUR RESPONSES ON THE PAST PERFORMANCE
QUESTIONNAIRE) ARE CRITICAL TO THE SELECTION OFFICIAL WHEN EVALUATING A
PROPOSAL FOR AWARD. INADEQUATE OR VAGUE RESPONSES MAY RESULT IN A LOWER
RATING (PLEASE SEE SECTION M OF THE SOLICITATION FOR EVALUATION INFORMATION).
YOU MAY USE ADDITIONAL PAGES FOR YOUR RESPONSES, IF NEEDED.
SUBFACTOR #1 – Technical Approach
Technical approach is your means and methods to complete the technical aspect of required work in HVAC System Replacement as described in the project specifications. Submit a written narrative limited to 5 pages describing your technical approach to the specific aspects below. Additional pages will not be evaluated. Pictures can be included and will not be counted towards the page limitation.
• Approach to Critical Contract Requirements: Describe your approach to successfully accomplish constructing residential housing in accordance with requirements outlined in the Project Specifications and Drawings within proposed contract performance period and budget.
Technical approaches that comply with applicable contract requirements; are realistic, appropriate, efficient; and demonstrate clear logic and scope understanding present lower levels of risk and will be more favorably rated.
Approaches not demonstrating these attributes present higher levels of risk and will be less favorably rated.
140P6222R0004 Attachment 5
SUBFACTOR #2 – Key Personnel
Submit resumes for key personnel as identified below with experience in HVAC System Replacement. All personnel proposed are subject to substitution requirements contained in this solicitation.
• Project Manager
• Superintendent
• Construction Management (field staff)
• On-Site Quality Control Specialist
• On-Site Safety Specialist/Manager
Key Personnel experience demonstrating (1) capability in same or similar key personnel positions on successful relevant projects of similar scope and magnitude to this solicitation; (2) strong technical knowledge and skill required for this solicitation; and (3) effective organization present lower levels of risk and will be more favorably rated. Those not demonstrating these attributes present higher levels of risk and will be less favorably rated.
SUBFACTOR #3 – Project Experience
Submit "Project Experience" addressing specific experience working in HVAC System Replacement in the below section/box, preferably a minimum of 3 and/or a maximum of 5, relevant projects completed in the last 7 years.
Project experience demonstrating (1) capability to successfully complete relevant projects of similar scope and magnitude to this solicitation; (2) strong technical knowledge and skill required for this solicitation; and (3) effective management, problem solving, communication, coordination, and organization present lower levels of risk and will be more favorably rated. Those not demonstrating these attributes present higher levels of risk and will be less favorably rated.
NOTE: The same projects evaluated for experience under this factor shall also be evaluated for Past Performance.
Projects determined more relevant under this factor will be given more weight in the Past Performance evaluation.
SUBFACTOR #4 – Schedule
Submit your proposed construction schedule for THIS SPECIFIC PROJECT showing completion within the required period of performance contained in this solicitation with accompanying schedule narrative. Submit your schedule so that it is clear and concise, addressing the following: major milestones, explain schedule logic, critical path activities, procurement lead-times and key considerations and constraints. There is no preprinted form for this submittal.
Construction schedules and narrative descriptions documenting (1) clear and efficient critical path and logical sequencing; (2) account for procurement lead-time, subcontractor/trade coordination, resource and time constraints;