B08_RFP_140P8121R0017_.pdf
PDF 473 KB Posted
- Attached to
- Fire Hydrant Replacements for the Death Valley Nat Federal contract opportunity
- Solicitation number
- 140P8121R0017
About this file
This document is a request for proposals for fire hydrant replacements at Death Valley National Park. The National Park Service Pacific West Region is seeking proposals to replace fire hydrants throughout the park. Offerors must submit pricing and technical proposals by August 3, 2021. The technical proposal should include the offeror's technical approach, schedule, safety plan, relevant past experience on similar projects, and resumes for key personnel. The contract will be a firm fixed price award made to the offeror providing the best value based on technical merit and price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B12_Preproposal_Site_Visit_140P8121R0017_DEVA_309189_0001.pdf | ||
| Sol_140P8121R0017_Amd_0001.pdf | ||
| Release_of_Claims.pdf | ||
| DEVA_Area_Map.pdf | ||
| B08_1442_140P8121R0017.pdf | ||
| SF25A-16a.pdf | ||
| SF25-16a.pdf | ||
| SF24-16.pdf | ||
| Cow_Creek_Administrative_Area_Sat_Map.pdf | ||
| B03_WD_CA_Inyo_County_Heavy_Bldg.txt | TXT text file | |
| Sol_140P8121R0017.pdf | ||
| Construction_Invoice_NPS_302-2_(Invoice_Payment_Request).docx | DOCX document | |
| A04_SOW_DEVA_309189_2021_0303.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
This section contains no clauses or information.
A - Solicitation/Contract Form
B - Supplies or Services/Prices
Pricing shall include all costs including materials, labor, tools, testing, insurance, expenses, fees and taxes plus permitting costs, overhead and profit associated with bid items to perform the areas of work in accordance with the contract documents.
See the attached Contract Price Schedule listed in Section J of this procurement for use to propose pricing.
C - Description/Specifications
This solicitation and resulting contract is for a construction project at Death Valley National Park. The scope of work and drawings are located in Section J of this solicitation.
D - Packaging and Marking
This section contains no clauses or information.
E - Inspection and Acceptance
52.246-12 Inspection of Construction. (AUG 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
F - Deliveries or Performance
F.1 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days. The time stated for completion shall include final cleanup of the premises.
52.242-14 Suspension of Work. (APR 1984)
F.2 – Deliverable (Post-Award): Contractor’s Daily Logs Contractor shall prepare a daily log for each day work is performed under this contract. Copies of daily logs shall be submitted to the Contracting Officer, and may be compiled and submitted weekly, with payroll. Time necessary for completion of daily log is approximately 15 to 30 minutes. The contractor may choose to use its own format as long as the following elements are included on the log:
(a) Project Name
(b) Contract number
(c) Date
(d) Prime Contractor and/or Subcontractor
(e) Work performed, including number of employees by job categories (indicate if "prime" or "sub")
(f) Heavy equipment on job, hours worked (indicate if "prime" or "sub")
(g) Materials delivered
(h) Official visitors to site
(i) Inspections performed
(j) Verbal instruction received from government on construction deficiencies
(k) Certification (prime contractor's signature/COR's signature)
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
G - Contract Administration Data
G.1 NOTICE TO CONTRACTORS
Contractor Performance Assessment Reporting System (December 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the
Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the 6.evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should a)provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date).
The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.gov/
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
PST.
G.2 Contracting Officer’s Representative (COR) for this contract will be:
Bradley Harris Death Valley National Park 760-786-3295 Cell 907-440-6074 Bradley_Harris@nps.gov
Specialist responsible for Administration of this contract:
Cris Stubitz Lake Mead National Recreation area 601 Nevada Way Boulder City, NV 89005 702-293-8940 Cris_Stubitz@nps.gov
Contracting Officer responsible for this contract:
Jim Read Lake Mead Major Acquisitions Buying Office 601 Nevada Way Boulder City NV 89005 760-252-6112 Jim_read@nps.gov
G.3 1452.201-70 Authorities and Delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the
Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the
Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.4 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) (FEB 2019) Payment requests by the Contractor shall be submitted for reimbursement in the manner and format described herein.
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in FAR 32.905(b), “Content of Invoices”, and all applicable payment clauses and provisions included in this contract.
Invoices must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP). The IPP website address is: https://www.ipp.gov. If you have multiple contracts with NSF, you cannot reuse the same invoice number when invoicing under different contracts. Each invoice number from your organization must be different.
If you are not already enrolled, please go to https://www.ipp.gov and click on the “Vendors – Enroll Now” button for instructions on how to enroll. Contractor assistance with enrollment can be obtained by contacting the IPP Customer Support Helpdesk via e-mail: IPPCustomerSupport@fiscal.treasury.gov or by phone: (866) 973-3131.
If any contract deliverables are rejected for failure to conform to the technical requirements of the contract or are otherwise unacceptable, the provisions of this clause will apply only to delivery of the acceptable contract deliverables, unless otherwise determined by the Contracting Officer.
All payments for proper invoices will be made via Electronic Fund Transfer (EFT).
Contractors that are small businesses under the appropriate NAICS code for this contract are permitted to request accelerated payments in accordance with the OMB Memorandum, Accelerating Payments to Small Businesses for Goods and Services, dated September 14, 2011. Requests for accelerated payments shall be made by typing “Small Business Invoice” in the Comments field of your IPP invoice screen. Per the OMB Memorandum, Accelerating Payments to Small Businesses for Goods and Services, dated September 14, 2011, the accomplishment of accelerated payments to small businesses is a goal and not a guarantee.
If the Contractor is unable to comply with the requirement to use IPP for submission of invoices, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation. The Contractor may submit payment requests using other than IPP only when the Contracting Officer expressly authorizes alternate procedures in writing.
Payment assistance for small businesses is available from the NSF Office of Small and Disadvantaged Business Utilization (OSDBU) https://www.nsf.gov/about/contracting/osdbu.jsp.
H – Special Contract Requirements http://www.ipp.gov/ http://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov http://www.nsf.gov/about/contracting/osdbu.jsp
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
H.1 Contract Work Hours (NOV 2007)
The performance period established for this contract is based upon all work being conducted during regular working hours. Regular working hours are limited to the time between 6:00 AM to 4:30 PM (PST), Monday through Friday, excluding Government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and Government holidays, a request must be submitted to the Contracting Officer Representative in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
H.2 Construction Wage Rates
Wage Rate Requirements (Construction) apply to the work to be performed under this contract and those rates are set out in Section J. The project is located in Inyo County, CA.
H.3– Interpretation of Contract – Notice of Ambiguities
(a) This written contract and any and all identified writings or documents incorporated by reference herein or physically attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify or contradict
it. Any ambiguity in the contract will not be strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.
(b) It shall be the obligation of the Contractor to exercise due diligence to discover and to bring to the attention of the Contracting Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation shall be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.
H.4 Prevention of Non-Native Plants
All equipment shall be thoroughly pressure washed prior to transport to the park to prevent unintentional importation of seed or soil materials. All parts of the equipment shall be cleaned of lodged soil or seeds, paying particular attention to radiators, tires and undercarriages. Examples of equipment are backhoes, tractors, loaders, excavators, dozers, bobcats, wheeled compressors or trucks and trailers that have traveled off-road. Contractor shall allow for the COR to inspect equipment to assure that it is clean prior to entering Park. Vehicles may be turned away if not fully clean.
H.5 Workers Compensation
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of the Labor Code of the State of Nevada. Evidence of coverage is required before commencement of project work.
H.6 Site Specific Safety and Health Plan
A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions. Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.
Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulation, including adherence to any local government health orders in effect to reduce the rate of transmission of Novel Coronavirus Disease 2019 (“Covid-19”). This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
H.7 Alternate Work Hours
Requests for alternate work hours will need to be submitted to the CO and COR, the COR will review and make a recommendation to the CO to approve alternate work hours. Alternate works hours may not be used as a way to accelerate the schedule. Government acceptance of Contractor’s voluntary schedule acceleration does not commit the Government to additional costs that result in Contractor’s acceleration of the schedule. Voluntary acceleration of work needs to be identified in writing and request(s) shall be reviewed by the COR and is subject to final approval by the CO.
(End of Clause)
I - Contract Clauses
52.202-1 Definitions. (JUN 2020)
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government. (JUN 2020)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity.
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (JUN 2020)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights. (JUN 2020)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
(JAN 2017)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards.(JUN 2020)
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.204-14 Service Contract Reporting Requirements. (OCT 2016)
52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)
52.204-19 Incorporation by Reference of Representations and Certifications. (Dec 2014) 52.204-22 Alternative Line Item Proposal. (JAN 2017)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered entities (JUL 2018)
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance
Services or Equipment (AUG 2020)
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (JUN 2020)
52.209-9 Incorporation by Reference of Representations and Certifications. (Oct 2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.215-2 Audit and Records-Negotiation. (JUN 2020) 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020)
52.219-8 Utilization of Small Business Concerns. (Oct 2018)
52.219-14 Limitations on Subcontracting (Mar 2020)
52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside
52.219-28 Post-Award Small Business Program Representation. (NOV 2020)
52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation. (MAY2018)
52.222-6 Construction Wage Rate Requirements. (Aug 2018)
52.222-7 Withholding of Funds. (MAY2014)
52.222-8 Payrolls and Basic Records. (FEB 2021)
52.222-9 Apprentices and Trainees. (JUL2005)
52.222-10 Compliance With Copeland Act Requirements. (FEB1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations.
(MAY2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of segregated facilities. (APR2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR2015)
52.222-35 Equal Opportunity for Veterans. (OCT 2015)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL2014)
52.222-37 Employment Reports on Veterans. (JUN 2020)
52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC2010)
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
52.222-50 Combating Trafficking in Persons. (OCT 2020)
52.222-54 Employment Eligibility Verification. (OCT 2015)
52.222-62 Paid Sick Leave Under Executive Order 13706. (JAN 2017)
52.222-55 Minimum Wages Under Executive Order 13658. (DEC 2015)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (AUG
2018)
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving. (JUN 2020)
52.225-9 Buy American - Construction Materials. (FEB 2021)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity
Price (dollars)*
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
Item 1
Foreign construction material
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.227-1 Authorization and Consent. (DEC2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020)
52.227-4 Patent Indemnity-Construction Contracts (DEC 2007)
52.228-1 Bid Guarantee. (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g. bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20% of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
52.228-11 Pledges of Assets. (FEB 2021)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
52.228-15 Performance and Payment Bonds - Construction. (JUN 2020)
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
52.232-17 Interest. (MAY 2014)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)
52.232-33 Payment BY Electronic Funds Transfer – System for Award Management (OCT 2018)
52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest After Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-14 Availability and Use of Utility Services. (APR 1984)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-13 Bankruptcy. (JUL 1995)
52.243-4 Changes. (JUN 2007)
52.245-1 Government Property (Jan 2017)
52.244-6 Subcontracts for Commercial Items. (NOV 2020)
52.246-21 Warranty of Construction. (MAR 1994)
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
52.248-3 Value Engineering – Construction (OCT 2020)
52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far
52.253-1 Computer Generated Forms. (JAN 1991)
1452.204-70 Release of Claims (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
1452.203-70 Restriction on endorsements. (NOV 1995) The contractor shall not refer to contracts awarded by the Department of Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The contractor may request a determination as to the propriety of promotional material from the CO.
1452.215-70 Examination of Records by the Department of the Interior. (APR 1984) For purposes of the Examination of Records by the Comptroller General (APR 1984) clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duty authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.
1452.228-70 Liability Insurance (JUL 1996)
(b) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$1,000,000 each person*
$2,000,000 each occurrence*
$1,000,000 property damage*
(c) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
I. 2Archeological Findings
(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in http://www.acquisition.gov/far http://www.farmaster.com/farmaster/data/idx/FAR97/3102050001.htm http://www.farmaster.com/farmaster/data/idx/FAR97/5202140001.htm
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.
(End of Clause)
I.3 Conduct of Operations At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.
(End of Clause)
1452.237-70 Information Collection – Department of the Interior (JUL 1996)
If performance of this contract requires the contractor to collect information on identical items from ten or more public respondents, no action shall be taken or funds expended in the solicitation or collection of such information until the contractor has received from the Contracting Officer written notification that approval has been obtained from the Office of Management and Budget (OMB) pursuant to the Paperwork Reduction Act of 1980. The Contractor agrees to provide all information requested by the Contracting Officer which is necessary to obtain approval from OMB.
J - List of Documents, Exhibits and Other Attachments
Project Specifications General Decision, Inyo County, CA Price Schedule Past Performance Questionnaire
K - Representations, Certifications, and Other Statements of Bidders
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. (SEP 2007)
52.204-8 Annual Representations and Certifications. (March 2020)
(1) The North American Industry Classification System (NAICS) code for this acquisition is 237110.
(2) The small business size standard is $39.5 million in average annual receipts.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)
(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
(i) □ Paragraph (d) applies.
(ii) □ Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)
(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
https://www.acquisition.gov/content/52204-7-system-award-management#i1063838 https://www.acquisition.gov/content/52204-7-system-award-management#i1063838
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless–
(A) The acquisition is to be made under the simplified acquisition procedures in part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that-
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services-Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations-Representation.
(viii) 52.209-5, CertificationRegarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance-Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
https://www.acquisition.gov/content/52203-2-certificate-independent-price-determination#i1063268 https://www.acquisition.gov/content/part-13-simplified-acquisition-procedures#i1112458 https://www.acquisition.gov/content/52203-11-certification-and-disclosure-regarding-payments-influence-certain-federal-transactions#i1063408 https://www.acquisition.gov/content/52203-18-prohibition-contracting-entities-require-certain-internal-confidentiality-agreements-or-statements-representation#i52_203-18 https://www.acquisition.gov/content/52204-3-taxpayer-identification#i1063736 https://www.acquisition.gov/content/52204-7-system-award-management#i1063838 https://www.acquisition.gov/content/52204-5-women-owned-business-other-small-business#i1063796 https://www.acquisition.gov/content/52204-26-covered-telecommunications-equipment-or-services-representation#id19CAC0P0ESS https://www.acquisition.gov/content/52209-2-prohibition-contracting-inverted-domestic-corporations-representation#i1062479 https://www.acquisition.gov/content/52209-5-certification-regarding-responsibility-matters#i1062558 https://www.acquisition.gov/content/52209-11-representation-corporations-regarding-delinquent-tax-liability-or-felony-conviction-under-any-federal-law#id165RA0UH01A https://www.acquisition.gov/content/52214-14-place-performance-sealed-bidding#i1059991 https://www.acquisition.gov/content/52215-6-place-performance#i1059247 https://www.acquisition.gov/content/52219-1-small-business-program-representations#i1057235 https://www.acquisition.gov/content/52219-2-equal-low-bids#i1057302
RFP est issued at 07/01/2021, Site visit est 07/07, questions due 07/13/2021, Proposals 08/03/2021 2:00 PM PST.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA–designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA–designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.
(D) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at…