B08_Quote_Schedule.pdf
PDF 97 KB Posted
- Attached to
- CACO SOLID WASTE REMOVAL & RECYCLING Federal contract opportunity
- Solicitation number
- 140P4323Q0018
About this file
This document contains a quote schedule for solid waste disposal and recycling services for the National Park Service at Cape Cod National Seashore. The quote schedule outlines pricing for pickup of 8-yard dumpsters, 4-yard recycling dumpsters, and 2-yard recycling dumpsters over a base year and four optional periods, including a possible six month extension. Estimated quantities are provided for each item for the base year and optional periods. Offerors are instructed to provide unit pricing and extended totals for all items. The related federal contract opportunity is solicitation number 140P4323Q0018 for CACO SOLID WASTE REMOVAL & RECYCLING through the Department of the Interior Departmental Offices Interior Business Center.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_SOW_Dumpster_Service_at_CACO_Facilities_0003.pdf | ||
| B08_Revised_Combined_Synopsis_0003.pdf | ||
| B03_Wage_Determination_2015-4045_Rev_24_12-27-22_0003.pdf | ||
| Sol_140P4323Q0018_Amd_0003.pdf | ||
| B08_Quote_Schedule__Amendment_003_0003.pdf | ||
| Sol_140P4323Q0018_Amd_0002.pdf | ||
| Sol_140P4323Q0018_Amd_0001.pdf | ||
| A04_SOW_Dumpster_Service_at_CACO_Facilities_0001.pdf | ||
| Sol_140P4323Q0018.pdf | ||
| B08_Schedule_and_Pricing_Sheet.pdf | ||
| B03_Wage_Determination_2015-4045_Rev_24_12-27-22.pdf | ||
| B08_140P4323Q0018_Combined_Synopsis.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLID WASTE DISPOSAL AND RECYCLING SERVICES
FOR THE NATIONAL PARK SERVICE AT
CAPE COD NATIONAL SEASHORE
QUOTE SCHEDULE
Submit quote for all items, failure to do so may render the quote non–responsive. On unit priced items, provide the unit price and the extended amount of quote. In case of error in extension of prices, unit price governs. In case of error in summation, the total of the corrected amounts governs. Unit prices shall be used to calculate progress payments. Quantities below for option years are for estimating purposes only.
Item No. Description of Item Estimated Unit of Unit Total
Quantity Measure Price Amount BASE PERIOD April 1, 2023 – March 31, 2024
Quote Item #1 8-yard dumpster pick-ups 589 Pick-ups $ $
Quote Item #2 4-yard recycling dumpster 42 Pick-ups $ $ pick-ups
Quote Item #3 2-yard recycling dumpster 36 Pick-ups $ $
Base Year Sub Total $
OPTION PERIOD ONE April 1, 2024 – March 31, 2025
Option Year One Sub Total $
OPTION PERIOD TWO April 1, 2025 – March 31, 2026
Option Year Two Sub Total $
OPTION PERIOD THREE April 1, 2026 – March 31, 2027
Option Year Three Sub Total $
OPTION PERIOD FOUR April 1, 2027 – March 31, 2028
Option Year Four Sub Total $
POSSIBLE 6 MONTH EXTENSION April 1, 2028 – September 30, 2028
Quote Item #1 8-yard dumpster pick-ups 294 Pick-ups $ $
Quote Item #2 4-yard recycling dumpster 21 Pick-ups $ $
Quote Item #3 2-yard recycling dumpster 18 Pick-ups $ $
Possible 6 Month Extension Sub Total $
GRAND TOTAL BASE AND ALL OPTION YEARS $
File details come from the government source that posted it. Updated .