B08_ATTACHMENT_3_SOW_PMIS_322235_-_Statement_of_Work.pdf
PDF 852 KB Posted
- Attached to
- OLYM-KALALOCH DORM ROOF REPLACEMENT Federal contract opportunity
- Solicitation number
- 140P8322Q0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Amendment_Revised_Wage_Determination_WA20220022_SAM_0001.pdf | ||
| B09_Amended_SF-30_140P8322Q0010_0001.pdf | ||
| Sol_140P8322Q0010_Amd_0001.pdf | ||
| B08_ATTACHMENT_4_Wage_Determination.pdf | ||
| B08_ATTACHMENT_2_Solicitation_Terms_and_Conditions_140P8322Q0010.pdf | ||
| Sol_140P8322Q0010.pdf | ||
| B08_ATTACHMENT_7_Kalaloch_Dorm_Roof_As_Builts.pdf | ||
| B08_ATTACHMENT_6_Kalaloch_Dorm_Bldg_Floor_and_Roof_Plan.pdf | ||
| B08_ATTACHMENT_5_Kalaloch_Dormitory_Building_-_Exterior_Photos.pdf | ||
| B08_ATTACHMENT_1_SF-1442_Solicitation_140P8322Q0010.pdf | ||
| B08_ATTACHMENT_8_Experience_and_Past_Performance.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Statement of Work
Kalaloch Dormitory Building Replace Standing Seem Roof, Underlayment and Gutters/Downspouts
December 21, 2021
Developed By
Olympic National Park Facility Management 600 East Park Ave Port Angeles, WA
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 00 20 00-1 Table of Contents
TABLE OF CONTENTS
Number Title ........................................................................................................... Number of Pages
00 20 00 Table of Contents 00 30 00 Index of Drawings
DIVISION 1 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Meetings 01 33 23 Submittal Procedures 01 35 23 Accident Prevention 01 51 13 Temporary Services 01 53 00 Barriers 01 56 00 Temporary Controls 01 59 00 Field Offices and Sheds 01 60 00 Material and Equipment 01 70 00 Project Closeout
DIVISION 6 – CARPENTRY
06 10 53 Miscellaneous Rough Carpentry (small amounts)
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 41 14 Underlayment for Metal Clad Roofs 07 42 00 Metal Roofing, Flashing and Trim 07 71 23 Gutters and Downspouts
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 00 30 00-1 Index of Drawings
SECTION 00 30 00 INDEX OF DRAWINGS
General
Attachment 1 GENERAL LOCATION MAP – Kalaloch Attachment 2 AERIAL MAP - Kalaloch Attachment 3 KALALOCH DORM BUILDING FLOOR PLAN Attachment 4 KALALOCH DORM BUILDING EXERIOR PHOTOS
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
DIVISION 01
GENERAL REQUIREMENTS
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 11 00-1 Summary of Work
SECTION 01 11 00 SUMMARY OF WORK
PART 1: GENERAL
1.1 DESCRIPTION:
1. The work of this contract consists of the replacement of standing seam steel roof;
underlayment; ridge cap; trim; flashing; and gutters and downspouts on the Kalaloch Dormitory building within Olympic National Park, located in Forks, WA. Work includes the removal and disposal of the existing steel roof, all flashing, drip edge, ridge cap, gutters and downspouts and all underlayment. OPTIONAL WORK (if needed during construction): Repair and/or replace existing damage to sheathing and eave/rake fascia. Any existing damage shall be photo documented and the approximate location notated on a hard copy of the building’s as-built drawings.
Work shall include:
A. Removal and disposal of existing steel roof, underlayment, flashing/drip edge and ridge cap/trim pieces. Materials shall be disposed of/recycled outside the park. Care shall be taken to mitigate damage to building and landscaping from construction/demolition debris by use of tarps and/or other means.
B. Removal and disposal of existing gutters and downspouts. Materials shall be recycled outside the park.
C. Installation of new 26-ga Standing Seam steel roof, ridge cap, drip edge, trim and flashing in color “Tahoe Blue”. Work includes installation of approximately 3,800 square-feet high performance vapor-permeable underlayment with adhered airgap; self-adhered Ice and Water protection underlayment at eaves and gables; All fasteners must be 304 stainless steel, minimum and must be concealed. Installation of three (3) permanent D-Ring ridge anchors in locations determined in field during construction. Anchors shall be approved for fall protection under ANSI 359.1 (2020). D-rings shall eb galvanized or stainless, and anchor bands shall be stainless.
D. Installation of new K-style 5” aluminum gutters and downspouts, in color “Tahoe Blue” as direct replacement to existing system. Downspout locations are not to change.
E. Thorough clean-up of construction debris (fasteners, roof panel/trim off-cuts, etc.) shall be performed using magnet rollers around the perimeter of the building and subject to final inspection punch list.
2. All work shall be performed under a single contract.
1.2 LOCATION: 156954 Highway 101, Forks, WA 98331.
1.3 CONTRACTOR'S USE OF PREMISES:
1. Construction Camp: Establishment of a camp within the Park and at this location will not be permitted.
2. Work Hours: Work hours are from 7:00am to 5:00pm Monday through Friday. Weekend work will normally not be allowed. Special requests may be made through the Contracting Officer.
3. Confine storage of materials to the area as indicated during the pre-construction meeting as part of this contract. Coordinate deliveries so that deliveries fit available storage area.
4. The following conditions shall be followed during the Contractor's work while in the Park:
A. To prevent unnatural attractants to bears, no foods, garbage, drinks, trash, or food and drink containers shall be placed outside trailers or buildings, except during actual use.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 11 00-2 Summary of Work
B. Pets are prohibited.
C. Feeding of any wildlife is prohibited.
D. Any mishandling of garbage, trash, foods, and other potential bear attractants described above will result in the responsible person or Contractor receiving a citation subject to a fine or court appearance before the U.S. Magistrate.
Repetition of mishandling or any case of deliberate feeding will result in loss of in-Park operation privileges.
E. Smoking is prohibited on Job site – all smoking must be done on scheduled breaks in contractor designated area a minimum 25 ft away from job site and National Park Service Employee residences. Cigarette butts shall be disposed of in a designated receptacle. Cigarette butts littered around the perimeter of the building are subject to final inspection punch list.
F. Construction/Demolition debris shall be removed from job site in a timely manner.
If debris will not be removed daily, an appropriate refuse container(s) must be contractor furnished to store materials. Debris shall not be stored on the ground overnight.
5. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings, including any vegetated turf (grass). Protect grass from heavy machinery (e.g., Tele-handler) with use of dispersion pads/plates (plywood) or similar methods.
Restore damaged areas, repair or replace damaged trees and plants (per direction by NPS arborists and horticulturists), at no additional expense to the Government.
6. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the State load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on Park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment or materials
1.4 FIELD VERIFICATION: Contractor shall field verify all new and existing dimensions and utilities affecting the work of this Contract.
1.5 CONTRACTOR-FURNISHED ITEMS: All materials, including borrow and aggregates, shall be Contractor-furnished from outside the Park.
1.6 CONSTRUCTION: Requirements of the drawings and technical sections of this specification will apply to all construction.
1. The Contract Documents indicate general minimum requirements and construction methods anticipated. Other methods, details or materials may be employed if specifically approved by the Contracting Officer. Other methods, details or materials must comply with all applicable building codes and regulations.
2. Contractor is responsible for protection of all exposed building elements during construction.
Exposed elements shall be protected at the end of each shift with temporary protection. Tear off shall not exceed reasonable production rates and forecasts for restoring watertight roof system.
Work shall begin when there is a reasonable expectation of completing the work within a one-month window; a winter shut down will not be allowed.
END OF SECTION 01 11 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 27 00-1 Contract Line Items
SECTION 01 27 00 DEFINITION OF CONTRACT LINE ITEMS
PART 1 GENERAL
1.1 DESCRIPTION
1. The intent of this section is to explain, in general, what is and what is not included in a line item, and the limits or cut-off points where one line item ends and another begins.
2. If no bid item exists for a portion of the work, include the costs in a related line item.
LINE-ITEM NO 1 – BASE: The work of this bid item consists of the installation of new 26-gauge standing seam steel roof with all ridge cap, flashing, drip edge and trim in color “Tahoe Blue”; vapor permeable underlayment with adhered air/gap; ice and water protection (underlayment) at the eaves and gables; 5-inch K-style aluminum gutters and downspouts in color “Tahoe Blue” on the Mora Apartment building.
Work includes the removal and disposal of the existing steel roof, ridge cap, trim, flashing, drip edge, underlayment(s), gutters and downspouts. Photo documentation of damage to sheathing, fascia or other roof framing members that compromise structural integrity or have water damage shall be photo documented and the approximate location of damage noted on a hard copy of the building’s as-built drawings, for submission to the contracting officer. Payment shall be made on a lump sum basis.
OPTION A: The work of this optional line item consists of replacement/repair of deteriorated/damaged sheathing on a square-foot, unit price basis and any deteriorated/damaged eave/rake fascia boards on a lineal foot, unit price basis. Replacement shall be in kind. Any damage to sheathing, rake or eave fascia boards shall be photo documented before being repaired. The unit pricing for these repairs will only be used to determine a contract modification award amount should any damage to the sheathing or fascia be found in the Base Bid Item.
END OF SECTION 01 27 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 31 00-1 Project Meetings
SECTION 01 31 00 PROJECT MEETINGS
PART 1: GENERAL
1.1 PRE-CONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange a meeting either to be held in-person at Olympic National Park Headquarters or via teleconference (typically teleconferences are through Microsoft Teams). The meeting agenda will include the following as a minimum:
Correspondence procedures
Designation of responsible personnel
Labor standards provisions
Payroll reports
Changes
Payments to Contractor
Subcontractors
Park rules and regulations
Accident prevention program (including name of responsible supervisor)
Accident reporting
Documents required under the contract
Recycling program
Saturday, Sunday, holiday and night work
Safety program (compliance with the "Accident Prevention “clause of the General Provisions)
Tentative construction schedule
Submittal of shop drawings, project data, and samples
Relationship of Division 1 to other divisions
1.3 PROGRESS MEETINGS: The Contracting Officer’s Representative may schedule periodic meetings with the Contractor and subcontractors. The meeting agenda will include the following as a minimum:
Approval of minutes of previous meetings
Review of work progress
Field observations, problems, and decisions
Identification of problems which impede planned progress
Review of submittals schedule and status of submittals
Effect of proposed changes on progress schedule and coordination
Other business relating to work
END OF SECTION 01 31 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 33 23-1 Submittals
SECTION 01 33 23 SUBMITTAL PROCEDURES
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
1.2 RELATED REQUIREMENTS: Closeout submittals - Section 01700.
1.3 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES:
1. General Procedures:
A. As specified in the individual sections, email all submittals to the Contracting Officer’s Representative and cc: Contracting Officer, at least 15 days before need for approval.
Unless a different number is specified, submit three copies of each shop drawing for NPS use and three specimens of each sample. Submit any additional copies that are to be returned.
B. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review.
C. List submittals on National Park Service form DSC-1(CS). Identify the front of each sheet or item with the submittal and item number.
D. Submittals will not be accepted for review if identification is missing an incorrect number of submittals are submitted, the transmittal form is incorrectly filled out, submittals are not coordinated, or submittals do not show evidence of Contractor's approval.
E. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
2. Specific Procedures:
A. Shop Drawings: Identify each copy of shop drawings with contract drawing number in lower right-hand corner.
B. Samples: Samples shall be large enough to clearly illustrate the functional characteristics and full range of color, texture, or pattern.
C. Manufacturers' Literature: Submit only pertinent pages; mark each copy of standard printed data to identify products referenced in specification section.
3. Contracting Officer's Review:
A. After approving submittals, Contracting Officer’s Representative will return one copy to the Contractor, and cc: Contracting Officer.
B. If submittals are not approved, Contracting Officer’s Representative will return one copy to Contractor with reasons for rejection and cc: Contracting Officer. Resubmit, identifying changes.
C. Any orders placed or work done before approval shall be at Contractor's own risk.
1.6 SIMILAR PRODUCTS OR APPROVED EQUAL:
1. For each item proposed as a "similar product or approved equal," submit items required in each section and additional supporting data, including:
A. Drawings and samples as appropriate.
B. Comparison of the qualities of the proposed item with that specified.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 33 23-2 Submittals
C. Changes required in other elements of the work because of the substitution.
D. Name, address, and telephone number of vendor plus Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
2. No pre-bid approvals will be made. Any submittal of a "similar product" constitutes a representation that the Contractor:
A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
B. Will provide the same warranties for the proposed item as for the item specified.
C. Has determined that the proposed item is compatible with interfacing items.
D. Will coordinate the installation of such item and make all changes required in other elements of the work because of such item.
E. Waives all claims for additional expenses that may be incurred as a result of the use of a "similar product".
3. New Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
END OF SECTION 01 33 23
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
TRANSMITTAL - NATIONAL PARK SERVICE Transmittal No.:
Sheet: 1 of:
Park:
Project:
Contract No.:
Pkg. No.:
Date:
Contractor:
Subcontractor/Supplier:
NPS ACTION
Specification Section No.
Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)
Contractor Signature
Recommended by
Title, Date
Title
Date
I hereby certify that this submittal has been reviewed for accuracy, completeness, and compliance with contract requirements (FAR 52.236-21)
Review Comments
Action By
Date
Contracting Officer’s Representative
Approval of this submittal is subject to the provisions of the contract drawings and specifications. This action is for general concurrence only and the Government is not responsible for errors or omission.
SUBMITTAL LOG DATES: From contractor [__________], To reviewer [__________], From reviewer [__________], To Contractor [__________] Distribution: ( ) Contractor ( ) DSC File ( ) COR ( ) A/E ( ) DSC Interim ( ) COR Interim ( ) Contractor Interim CM-16Rev. 4/00 (Formerly DSC-1(CS)
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
TRANSMITTAL CONTINUATION - NATIONAL PARK SERVICE Transmittal No.:
Sheet: 1 of:
Park:
Project:
Contract No.:
Pkg. No.:
Date:
Contractor:
Subcontractor/Supplier:
NPS ACTION
Specification Section No.
Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)
Review Comments
CM-16 Rev. 4/00 (Formerly DSC-1(CS)
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 35 23-1 Accident Prevention
Section 01 35 23 ACCIDENT PREVENTION
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS:
1. Site Specific Safety & Accident Prevention Plan. Before on-site work begins, submit for approval a site-specific safety & accident prevention plan. The Contracting Officer and Contracting Officer’s Representative will review the proposed plan for compliance with OSHA and project requirements.
If the program requires any revisions or corrections, NPS will work with contractor to turn around corrections as expeditiously as possible so that the approval of the plan won’t hold up start of work since the period of performance is tight on this project. The plan shall include:
A. Name of responsible supervisor to carry out the program.
B. Weekly and monthly safety meetings.
C. First aid procedures.
D. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
E. Training, both initial and continuing.
F. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
G. Housekeeping: Section 01 56 00.
H. Fire Protection: Section 01 51 13.
2. Submit a report of safety meetings and of inspections.
3. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE:
1. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions.
In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project site. Failure to comply with the requirements of this section and related sections may result in suspension of work.
2. Qualifications of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 35 23-2 Accident Prevention
1.4 ACCIDENT REPORTING:
1. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer a DI-134 form, which may be obtained from Contracting Officer.
2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2: PRODUCTS
2.1 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.3 BARRIERS: Section 01 53 00.
PART 3: EXECUTION
3.1 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 ESCAPE ROUTES: Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.
3.3 PROTECTIVE EQUIPMENT:
1. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
2. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS:
1. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
2. Conduct monthly weekly safety meetings for all levels of supervision. Notify the Contracting Officer so that he may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contractor will enter the subject, attendees and results of the meetings into the daily construction log for Contracting Officer review.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS:
1. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
2. It is the Contractor's responsibility to require all those working on the ground (including ladders and scaffolding), inside or on heavy equipment (e.g., tele-handler) or visiting the site to wear hard hats and other necessary protective equipment at all times.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 35 23-3 Accident Prevention
3.6 TRAINING:
1. First Aid: Provide adequate training to ensure prompt and efficient first aid.
2. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01 35 23
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 51 13-1 Temporary Services
SECTION 01 51 13 TEMPORARY SERVICES
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.
PART 2: PRODUCTS
2.1 GENERAL: Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
2.2 FIRE PROTECTION EQUIPMENT: UL Class 2A, 2-1/2-gallon water type, stored-pressure extinguisher and UL Class 10, Type I, 15-pound B:C carbon dioxide extinguisher.
PART 3: EXECUTION
3.1 ELECTRICITY AND LIGHTING:
1. There is commercial electrical power available at the site.
3.2 TELEPHONE:
1. No telephone service is available onsite for Contractor's use. The project sites does have cellular phone coverage.
3.3 WATER:
1. Potable water is available at the site.
3.4 SANITARY FACILITIES:
1. Contractor shall provide temporary restroom facilities.
3.5 FIRE PREVENTION AND PROTECTION:
1. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
2. Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in buildings. Provide adequate ventilation during use of volatile or noxious substances.
3. Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters.
4. Locate internal combustion equipment so that exhausts discharge well away from combustible materials.
5. Locate service areas a minimum of 25 feet from buildings. Shut down equipment before refueling.
6. Smoking: Smoking on the construction site is prohibited. See Section 01 11 00 1.3.4.E. for detail.
3.7 PROTECTION EQUIPMENT REQUIRED:
1. Buildings: Furnish a minimum of one extinguisher for each 1,500 square feet of area or major fraction thereof. Travel distance from any workstation to the nearest extinguisher shall not exceed 75 feet.
2. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
END OF SECTION 01 51 13
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 53 00-1 Barriers
SECTION 01 53 00 BARRIERS
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of furnishing, installing, and maintaining barriers to protect existing facilities and employees from construction operations.
PART 2: PRODUCTS
2.1 GENERAL: Material may be new or used but shall be suitable for intended purpose. Fences and barriers shall be structurally adequate and neat in appearance.
2.2 CONSTRUCTION FENCING: Material shall be orange mesh.
2.2 BARRIER TAPE: Banner Guard, imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef Industries, Inc., Houston, Texas, or similar product.
PART 3: EXECUTION
3.1 PROTECTION OF PUBLIC AND EMPLOYEES:
1. The area will be closed to public vehicles, but there may be incidental visitor and/or employee pedestrian traffic near the site. Immediate construction area shall be marked with high visibility fencing/warning tape.
END OF SECTION 01 53 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 56 00-1 Temporary Controls
SECTION 01 56 00 TEMPORARY CONTROLS
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of providing temporary controls.
PART 2: PRODUCTS Not Used.
PART 3: EXECUTION
3.1 HOUSEKEEPING:
1. Keep project neat, orderly, and in a safe condition at all times.
2. Provide enough containers for collecting construction/demolition debris and construction materials to be recycled. Food storage and disposal must meet Park regulations.
3. The Contractor is encouraged to provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, plastic, corrugated cardboard. These items may be recycled by the Contractor or turned over to the Park recycling committee. Demolished roof material shall be taken to local metal recycling.
4. Keep volatile wastes in covered containers.
5. Routine magnetic sweeps of the vegetated and paved jobsite surroundings are encouraged, to minimize hazard to humans, animals and vehicles. See Section 01 11 00 (1.1.1.E) and (1.3.4.F) for detail.
3.2 DISPOSAL:
1. Immediately remove hazardous construction/demolition debris from project site. Place other construction debris in refuse containers, daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the Park. Do not burn or bury refuse inside the Park. Do not store construction/demolition debris on vegetated/paved surfaces.
3.3 AIR AND WATER POLLUTION CONTROL:
1. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.
2. Do not dispose of volatile wastes or oils in storm or sanitary drains.
3. Do not allow waste materials to be washed into streams or bodies of water.
END OF SECTION 01 56 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 59 00-1 Field Offices
SECTION 01 59 00 FIELD OFFICES AND SHEDS
PART 1: GENERAL
1.1 DESCRIPTION: The requirements of this section consist of furnishing, locating, and removing temporary structures, equipment, and furnishings.
1.2 RELATED REQUIREMENTS: Temporary services - Section 01510.
PART 2: PRODUCTS
2.1 CONTRACTOR'S FIELD OFFICE: Contractor may provide an office for his own use. Size, location and construction shall be subject to approval of the Contracting Officer. The location for these temporary facilities will be decided at the site meeting.
2.2 STORAGE SHEDS: Temporary weather-tight sheds or other covered facilities for storage of materials subject to weather damage. Number, size and location of structures shall be subject to Contracting Officer's approval again decided at the pre-construction meeting.
PART 3: EXECUTION
3.1 STRUCTURES: Locate where directed by Contracting Officer, a minimum of 20 feet from permanent structures.
3.2 REMOVAL: Remove structures, equipment, and furnishings, and terminate services after punch list is 100 percent completed or when directed by Contracting Officer.
END OF SECTION 01 59 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 60 00-1 Material and Equipment
SECTION 01 60 00 MATERIAL AND EQUIPMENT
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.
1.2 TRANSPORTATION AND HANDLING: Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. Contractor is encouraged to obtain materials in biodegradable or recyclable/ reusable packaging which uses the minimum amount of packaging possible.
1.3 LOCATION: Materials and equipment to be used must be stored within the contract limit line, unless specifically approved by the Contracting Officer.
1.4 STORAGE AND PROTECTION: Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection. Conform to specific requirements in individual sections in addition to those listed below.
1. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.
2. Exterior Storage:
A. Store products subject to damage by the elements in weather tight enclosures.
B. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.
C. Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter.
3. Protection After Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction.
PART 2: PRODUCTS Not used.
PART 3: EXECUTION Not used.
END OF SECTION 01 60 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 01 70 00-1 Project Closeout
SECTION 01 70 00 PROJECT CLOSEOUT
PART 1: GENERAL
1.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2: PRODUCTS
2.1 CLEANING MATERIALS: As recommended by the manufacturer of surface to be cleaned.
PART 3: EXECUTION
3.1 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces of existing facilities that are marred, scratched, or damaged due to the work of this contract to match original condition. Remove grease, dirt, stains, foreign materials, and labels from interior and exterior finished surfaces. Sweep paved areas, rake grounds. At time of final inspection, project shall be thoroughly clean and ready for use.
3.2 CLOSEOUT SUBMITTALS: Submit before final inspection request.
1. Guarantees and Bonds: As specified in individual sections.
2. Spare Parts and Materials: As specified in individual sections.
3.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection.
Contracting Officer will inspect within 10 days of receipt of request.
1. When Contracting Officer determines that Work is substantially complete, she will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
2. If Contracting Officer determines that the Work is not substantially complete, she will immediately notify Contractor in writing, stating reasons. After completing Work, Contractor shall resubmit certification and request a new final inspection.
3.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of Acceptance will be issued.
3.5 POST-CONSTRUCTION INSPECTION: Before expiration of warranty period, Contracting Officer will inspect project and notify Contractor in writing of all deficiencies.
END OF SECTION 01 70 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 06 10 53-1 Misc. Rough Carpentry
DIVISION 06
CARPENTRY
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 06 10 53-1 Misc. Rough Carpentry
06 10 53 Miscellaneous Rough Carpentry (small amounts)
PART 1: GENERAL
1.1 DESCRIPTION: The requirements of this section consist of supply and installation of dimensional lumber and/or wood sheathing for any necessary repair work determined in the field.
PART 2: PRODUCTS
2.1 FASCIA: Upon discovery of damaged or compromised wood eave/rake fascia boards, contractor shall repair/replace with in kind products. Any new fascia board installed shall be pre-primed on all sides, in the field, before installation. Any damage to fascia shall be photo documented and the approximate location notated on a hard copy of the building’s as-built drawings before being repaired.
2.2 SHEATHING: Upon discovery of damaged or compromised wood sheathing, contractor shall repair/replace with in kind products. Any new sheathing installed shall be the same material as the existing. Any damage to sheathing shall be photo documented and the approximate location and square footage notated on a hard copy of the building’s as-built drawings before being repaired.
PART 3: EXECUTION
3.1 FASCIA: Fascia boards with minor (less than 4-square inches) surface rot may be repaired by removing rot and filling the void with exterior grade wood filler and finishing per the manufacturer’s specifications, including primer. Boards with more extensive damage shall be replaced, fully, with same material, and pre-primed on all sides before installation.
3.2 SHEATHING: Damaged sheathing shall be evaluated on a case-by case basis for replacement. In General, It is preferred to have an entire section (4’x8’) replaced than to patch in a small section, requiring blocking between trusses in the attic space.
END OF SECTION 06 10 53
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
DIVISION 07
THERMAL AND MOISTURE PROTECTION
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 25 00-1 Underlayment
07 41 14 Underlayment for Metal Roofs
PART 1 GENERAL
1.1 SUMMARY
A. Provide vapor-permeable waterproof underlayment with factory adhered 5/16” structured separation layer, designed for metal-clad roofs.
B. Related Work: Coordinate with the following items which are specified in other sections:
1. Section 07 42 00 – METAL ROOFING, FLASHING AND TRIM for roof assembly.
1.2 SUBMITTALS: (See Section 01 33 23)
A. Product Data: Submit manufacturer’s product data, including installation instructions, detail drawings, test reports on physical and performance properties, and building code compliance reports.
B. Verification Samples: Submit clearly labeled samples of each “or approved equal” material.
C. Warranty at Closeout: Submit manufacturer’s executed warranty form with authorized signatures and endorsements indicating date of Substantial Completion.
1.3 QUALITY ASSURANCE
A. Manufacturer: Minimum of 3 years experience manufacturing similar products.
B. Installer: Minimum of 2 years experience installing similar products and acceptable to the manufacturer.
1.4 DELIVERY, STORAGE AND HANDLING
A. Deliver materials and products in unopened factory labeled packages. Store and handle in strict compliance with manufacturer's instructions and recommendations.
1.5 WARRANTY
A. Manufacturer’s Warranty: Submit manufacturer’s standard limited warranty for defects in materials.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design for underlayment: (DELTA-TRELA) by Dörken Systems Inc., www.dorken.com OR APPROVED EQUAL
1. Underlayment for Metal-Clad Roofs: Provide underlayment with the following characteristics:
a) Material: 0.3 inch (8 mm) thick dimpled spacer mat adhered to 3-ply spun bonded polypropylene breather underlay.
b) Color: Black/gray.
c) Water Vapor Transmission: 820 g/m²/24 h ASTM E96, Proc. A; 472 g/m²/24 h ASTM E96, Proc. B http://www.dorken.com/
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 25 00-2 Underlayment
d) Vapor Permeance: 69 perms [grains/h/ft²/in Hg] ASTM E96, Proc. A; 120 perms [grains/h/ft²/in Hg] ASTM E96, Proc. B.
e) Fire Resistance: Class B2 DIN 4102.
f) Structured Separation Layer Height: Approx. 5/16” (8mm).
g) Temperature Range: -40 °F to +176 °F (-40 °C to +80 °C).
h) Maximum UV (Sunlight) Exposure: Maximum exposure 6 weeks.
2. Accessory Products:
a) Galvanized Wide-Head Nails with EPDM Sealing Gasket
b) Elastic Rubber Compound Sealant and Adhesive
B. SNOW AND ICE MEMBRANE (Eaves and Rakes)
1. Ice and Water Shield by W.R Grace or Jiffy Seal Ice and Water Guard by Protecto Wrap
OR APPROVED EQUAL
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine substrates for compliance with requirements for installation tolerances and other conditions affecting performance. Proceed with installation only after unsatisfactory conditions have been corrected.
B. Clean substrate of dirt and bond breaking substances prior to beginning installation.
3.2 INSTALLATION
A. Install product(s) in strict accordance with manufacturer’s instructions, approved submittals and the following:
3.3 PROTECTION
A. Protect installed underlayment from damage during application and remainder of construction period, according to manufacturer’s written instructions.
B. Coordinate with installation of materials which cover the underlayment, to ensure exposure period does not exceed that recommended by the manufacturer.
END OF SECTION 07 25 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 42 00-1 Metal Roofing
07 42 00 Metal Roofing
PART 1 GENERAL
1.1 DESCRIPTION: The work of this section consists of furnishing and installing concealed fastener standing seam metal roofing over wood structure including all flashings and accessories.
1.2 SUBMITTALS: (See Section 01 33 23)
A. Detail Drawings: Submit drawings detailing flashing, anchorage, joining and trim.
B. Samples: Submit one 12x16-inch (approximate) samples of sheet metal roofing material and one 12” long section of gutter and downspout, showing profile and thickness, accompanied by fasteners used for installation. Include a color sample of “Tahoe Blue” color for roofing and gutters.
C. Manufacturer's Installation and Maintenance Instructions: Submit 1 copy.
1.3 INSTALLER'S QUALIFICATIONS: Installer shall be approved by roofing manufacturer in writing.
Submit certification and references immediately after contract award. Approved installer shall have successfully applied five metal roofs of similar size and complexity which reflect a quality and weather-tight installation.
1.4 MANUFACTURER'S QUALIFICATIONS: Shall have minimum of five years experience supplying metal roofing to the region where the work is done and comply with current independent testing and certification as specified.
1.5 TESTING AND CERTIFICATION
A. Wind Uplift: UL 580 Class 90 Wind Uplift rated.
B. UL 790 Class A Fire rated
C. UL 2218 Class 4 Impact (hail) rated
1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING: Protect against damage and discoloration.
Keep panels dry. Do not overload roof structure with stored materials.
1.7 FIELD MEASUREMENTS: Verify prior to fabrication.
1.8 WORK WARRANTY: For warranty terms, refer to contract terms Section I, FAR clause 52.246-21, Warranty of Construction
1.9 MANUFACTURER'S PRODUCT WARRANTY: Manufacturer's standard 40-year coating performance warranty is available for specified installation and environmental conditions.
2.1 APPROVED MANUFACTURER:
A. Champion Metal, 1234 37th /street NW, Auburn, WA T: 800-700-7228 F: 888-797-5618, OR
APPROVED EQUAL.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 42 00-2 Metal Roofing
B. Roof Panel Designation: Snap-Loc Standing Seam Roofing (26-ga, 12-inch panel).
2.4 MATERIALS
A. Panels
1. Base Metal
a. Material: Steel
b. Manufacturing Standard: ASTM A446-87, grade C
c. Minimum Yield Strength: 40,000 psi.
d. Thickness: 26 gauge.
e. Protective Coating: 2-coat Armortech SMP.
f. Protective Coating Thickness: 1.1 mils.
2. Configuration:
a. Pattern: Standing Seam, 1-inch seam height, flat panel.
b. Rib Spacing: 12 inches o.c.
c. Normal Panel Width: 12 inches coverage.
d. Panel Length: Full length of span.
3. Exterior Finish:
a. Primer Coat Material: Baked-on epoxy primer.
b. Minimum Primer Coat Dry Film Thickness: 0.2 mils.
c. Finish Coat Material: Baked-on PVF2/Polyvinylidene Flouride, Kynar 500.
d. Minimum Finish Coat Dry Film Thickness: 0.8 mils.
e. Minimum Total Exterior Finish Dry Film Thickness: 1.0 mils.
f. Color: Standard color "Tahoe Blue” (SRI-25).
4. Interior Finish:
a. Primer Coat Material: Baked-on epoxy primer.
b. Minimum Primer Coat Dry Film Thickness: 0.2 mils.
c. Finish Coat Material: Polyester paint.
d. Minimum Finish Coat Dry Film Thickness: 0.3 mils.
e. Minimum Total Interior Finish Dry Film Thickness: 0.50 mils.
f. Color: Off-White.
C. Fasteners:
1. All exposed fasteners shall be color coated to match roof color and have EPDM gasket for weatherproofing.
2. Panels to substrate: Screws shall be 304 (minimum) STAINLESS STEEL pancake head #10 x ¾” to 1” long with #2 Philips head.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 42 00-3 Metal Roofing
3. Flashings to panels: exposed screws shall be stainless steel with a #14 x 7/8" combination steel and EPDM washer, color to match panel.
4. Drip Edge to substrate: Stainless steel (304 minimum) ring shank nails
4. Pop rivets: #43 stainless steel (304 minimum), color finish to match panel.
E. End Closures:
1. Ridge and hip closures shall be protected and supported by a formed metal closure manufactured from the same material, color, and finish as the panels.
2. Metal closures shall be factory-fabricated and field-cut as needed.
F. Sealant Compound:
1. Shall not contain oil, asbestos, or asphalt.
2. Field applied panel end sealant shall be mastic tape sealant.
3. Exposed sealant shall be two-part polyurethane joint sealant. Coordinate color with roof pane.
H. Accessories: Provide all required for complete, secure, and waterproof installation.
I. Fabrication
1. Unless otherwise shown on Drawings or specified herein, fabricate panels in continuous one-piece lengths and fabricate flashings and accessories in longest practicable lengths.
2. Bend ridge end of panels beneath ridge cap for protection of driving rain.
3.1 INSPECTION
A. Existing Conditions:
1. Verify that surface to receive panels is complete, accurately sized and located, in true plane, secure, and otherwise properly prepared. Verify nailing of substrate prior to covering.
2. Prior to starting work, notify Contracting Officer about defects requiring correction.
Do not start work until conditions are satisfactory.
3.2 PREPARATION
A. Protection:
1. Treat any contacting surfaces of dissimilar materials to prevent electrolytic corrosion.
Use asphaltic paint of approved type.
2. Require workers who will be walking on roofing panels to wear clean, soft-soled work shoes that will not pick up stones or other abrasive material which could damage panel surfaces.
3. Protect work of other trades against damage and discoloration caused by work of the section.
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 42 00-4 Metal Roofing
B. Surface Preparation: Clean and dry surfaces prior to applying joint sealant.
3.3 INSTALLATION
1. Conform to the standard set forth in the SMACNA architectural sheet metal manuals and the approved shop drawings detailed for the project.
2. Install panels plumb, level, and straight with the seams parallel, conforming to the design as indicated.
3. Install panel system so it is watertight, without waves, warps, buckles or distortions, and allow for thermal movement considerations.
4. Abrasive devices shall not be used to cut on or near roof panel system.
5. Apply sealant tape or caulking as necessary at flashing and panel joints to prevent water penetration.
6. Remove any strippable film immediately upon exposure to direct sunlight.
7. Underlayment (solid substrate):
a) Provide ice and water shield membrane on lower and outer three feet of roof sheathing (eaves and rakes)
b) Lay parallel to ridge line with 2½" horizontal laps and 6" vertical laps.
8. Underlayment (Delta-Trela):
a) Install vapor permeable underlayment with adhered air gap on roof deck after Ice and Water shield and before installing preformed roofing panels.
Secure by methods acceptable to roof manufacturer. Apply from eaves to ridge in shingle fashion overlapping the horizontal joints and adhering with manufacturer’s adhesive strip.
b) Allowable Erection Tolerance: Maximum Alignment Variation: 1/4 inch in 40 feet.
9. Flashing:
a) Follow manufacturer's directions for eave and rake flashing/trim and drip edge
10. Cutting and Fitting:
a) Neat, square, and true. Torch-cutting prohibited. No openings or penetrations allowed in metal roofing.
b) Touch Up: Touch up damaged paint surfaces with same paint used in shop.
Apply in accordance with paint manufacturer's directions.
11. Cleaning and Repairing:
a) At completion of each day's work and at work completion, sweep panels, flashing clean. Do not allow fasteners, cuttings, fillings, or scraps to accumulate on finish surfaces.
b) Including work of other sections, clean, repair and touch up, or replace when
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 42 00-5 Metal Roofing directed, products which have been soiled, discolored, or damaged by work of this section.
c) Remove debris from project site upon work completion or sooner, if directed.
END OF SECTION 07 42 00
Solicitation (Request for Quotes) no. 140P8321Q0010 Replace Standing Seam Roof and Gutters, OLYM
Re-Roof Kalaloch Dormitory 07 71 23-1 Gutters and Downspouts
07 71 23 Gutters and Downspouts
PART 1 GENERAL
1.1 DESCRIPTION
A. Gutters and downspouts
B. Accessories
1.2 RELATED SECTIONS
A. 07 42 00 Metal Roofing, Flashing and Trim
1.3 REFERENCES
A. American Society for Testing and Materials (ASTM):
1. ASTM B 209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.
B. SMACNA - Architectural Sheet Metal Manual.
1.4 DESIGN / PERFORMANCE REQUIREMENTS
A. Conform to applicable code for size and method of rainwater discharge.
B. American Architectural Manufacturers Association (AAMA) Specification 1405.1 "Specification for Aluminum Rain-carrying Systems".
C. FHA Minimum Property Standard 4900.1 for One- and Two-Family Dwellings.
D. FHA Minimum Property Standard 4910.1 for Multi-Family Dwellings.
1.5 SUBMITTALS
A. Refer to Section 01 33 00
B. Product Data: Submit manufacturer current technical literature for each type of product.
C. Samples: Provide nominal 12-inch-long sample of gutter and downspout and a 3-inch x 5-inch sample of “Tahoe Blue” color if not available in the 12”…