This is a Performance Work Statement (PWS) for the repair and maintenance of stormwater structures and pervious pavement at Rock Creek Park and Fort Reno Park under contract with the National Park Service. The contract covers approximately 4.5 miles of pervious trails and parking lot pavement totaling approximately 228,300 square feet across multiple locations in the parks. The contractor must furnish all equipment, materials, tools, and labor necessary to maintain 100% functionality of the permeable pavement system and stormwater management structures in compliance with Section 3.5.7 of the District Department of Energy & Environment (DOEE) "Stormwater Guidebook Permeable Pavement Systems."
The scope of work includes routine permeable pavement maintenance performed monthly, quarterly, and annually, including visual inspections, removal of leaves and sediment, and moss treatment. Stormwater structure maintenance encompasses debris accumulation removal, entry point and pretreatment area inspection and maintenance, culvert and check dam inspection, established plant and tree management, inlet and outlet inspection, observation port evaluation, mulch replacement, runoff assessment, water infiltration testing, erosion repair, and signage/fencing maintenance. The contractor must maintain detailed maintenance logs recording service dates, personnel, work performed, amounts and types of materials removed, and pavement condition observations. Post-cleaning testing using ASTM C1701 or ASTM C1781 infiltration rate testing is required at minimum three locations spaced evenly across the pervious pavement surface. The contract period is one calendar year with up to four option years from the date of award, with monthly, quarterly, and event-based reporting requirements. Performance standards establish an 85% Acceptable Quality Level for all tasks, with deficiencies requiring correction within 48 hours of written notification by the Contracting Officer's Representative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment_2-SCA_Wage_Determination.pdf | ||
| Sol_140P8526Q0092.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PMIS 320885 ROCR
July 6, 2026
PERFORMANCE WORK STATEMENT (PWS)
for Repair and Maintenance of Stormwater Structures and Pervious Pavement
1.0 Background
1.1 The Contractor shall furnish all equipment, materials, tools, and labor necessary to perform the maintenance tasks for approximately 4.5 miles of pervious trails and parking lot pavement in Rock Creek Park and Fort Reno Park. The pervious surface area of the pavement is approximately 228,300 square feet. The contractor will be responsible under this contract for work to provide maintenance services as described in this document.
1.2 All work shall conform to Section 3.5.7 of the District Department of Energy & Environment (DOEE) “Stormwater Guidebook Permeable Pavement Systems.”
1.3 A Schedule of Tasks will be included in the appendix to indicate the frequency of each task/activity.
1.4 The performance requirement for the work as outlined above is to maintain 100% functionality of the Permeable Pavement System.
2.0 Scope
2.1 The Contractor will provide periodic maintenance services for pervious paving to keep the systems and assemblies operating to original performance specifications.
The work may involve the use of specialized cleaning and debris collection equipment, as well as any other necessary materials needed to perform work under the terms of this PWS.
2.2 This contract will be between the National Park Service and the Contractor. The contractor shall be responsible for assuring that any subcontractor(s) perform the work as stated in this PWS as outlined.
2.3 Contractor shall submit work plan to include means and methods of performing tasks to the Contracting Officer’s Representative (COR) for approval prior to the commencement of any work.
3.0 Work to be Performed – The following are the tasks that will be performed by the contractor on a monthly, seasonal, and annual basis to fulfill this contract, as outlined in the Quality Assurance and Surveillance Plan and Schedule of Tasks in the appendix.
3.1 Permeable Pavement Maintenance
3.1.1 Routine maintenance
3.1.1.1 Inspection: Conduct visual inspection of pavement to
determine that it is clean of debris and sediment and that it is dewatered quarterly, or as needed at least four times annually.
Inspect pavement after any major weather events such as rain or snowstorms of more than 1 inch of precipitation.; these inspections are in addition to the four annual inspections.
3.1.1.2 Maintenance:
3.1.1.2.1 Monthly: Remove leaves and sediment so that it does not become ground down into the surface. Any materials blown off pavement need to be collected by the Contractor, weighed, and taken off site.
3.1.1.2.2 As needed: Dry out any ponding or moist areas of
pavement if moss is observed and use a lime mortar mix to kill the moss and vacuum clean the surface.
3.1.2 The performance requirement for the work as outlined above is to maintain 100% functionality of the Permeable Pavement System.
3.1.3 Locations: See 4.0 as well as Schedule of Locations which is in the appendix for details on the locations of work.
3.1.4 Contractor must maintain a maintenance log that records the following:
• Date of service.
• Name of individual/company performing service.
• Type of maintenance performed.
• Amount (lbs.) and type(s) of sediment/debris/other material removed as result of cleaning.
• General observations and record of pavement condition.
• Name/signature of individual completing the inspection.
• Additionally, if ASTM C1701 is performed (see Section 7.0 of this
Scope of Work), the test results and locations should be included in the report.
• The log must be submitted to the COR each month for approval.
3.2 Permeable Pavement Repairs
3.2.1 If inspections reveal repairs are needed to the pervious pavement, notify the COR within 24 hours of discovery. This contract does not involve repair to the pervious pavement infrastructure; reporting only.
3.3 Inspect, Repair and Maintain Stormwater Structures at all locations shown in Paragraph 4
3.3.1 Debris Accumulation
3.3.1.1 Inspect for fallen leaves, debris, and litter accumulation.
3.3.1.2 Maintain: Remove these foreign materials. Especially before winter and in early spring, remove sediment especially when more than two inches deep of if shown to impact the growth of required vegetation.
3.3.1.3 Scheduled Service: Spring and Fall, Monthly, and after major storm events.
3.3.2 Entry points and Pretreatment Areas
3.3.2.1 Inspect: Area such as filter strips, and Bioswale floor for excessive deposition of sediment, rocks, etc. Inspect monthly for erosion at inflows or ponding areas.
3.3.2.2 Maintain: Remove sediment and stabilize any eroded areas quarterly using methods approved by the and the NPS COR.
Reestablish vegetations that conforms with original plant materials if needed, reseed and restore all filter strips.
3.3.2.3 Scheduled Service: Inspect monthly and after major storm events, and in the spring and fall. Maintain spring and fall, monthly during the growing season, and after major storm events.
3.3.3 Culverts
3.3.3.1 Inspect: All locations where culverts are part of the Bioswale system annually to ensure that erosion has not occurred at the outfall of said culverts.
3.3.3.2 Maintain: Repair eroded areas, replace or move to original locations all stone, grave, and revetment materials. Remove any debris that was not part of the original construction.
3.3.3.3 Scheduled Service: Inspect annually, Maintain When repair is needed as documented by inspections.
3.3.4 Check Dams
3.3.4.1 Inspect: Annual inspection to check dams for excessive deposition of sediment, rocks. Inspect condition of any choker layer materials on the front side of rock checks.
3.3.4.2 Maintain: Clear all debris and bring Check Dams back to original operational specification.
3.3.4.3 Scheduled Service: Inspect Annually, Maintain when
inspection shows repair is required.
3.3.5 Established Plants and Trees
3.3.5.1 Inspect: Plants and Trees for wilted plants, weeds and invasive, non-desired plants or trees leading form the edge of the Bioswales and into the Complete area of the Bioswale monthly.
3.3.5.2 Maintain: Remove undesirable plants, weeds and tree saplings throughout the growing season by pulling, and trimming.
Where invasive plants are removed, bring soil back to the condition level of surrounding areas.
3.3.5.3 Scheduled Service: Inspect Monthly, Maintain annually in the spring and the fall.
3.3.6 Inlets and Outlets
3.3.6.1 Inspect: To ensure mechanical inlets, outlets, and overflows are all free flowing and working properly. Check all outlets and subdrains to see if they are damaged to assure any animal guards or covers are in place. Replace or repair it if needed.
Remove ant restrictions to assure that they are free flowing.
3.3.6.2 Maintain: Remove any sediment and debris. Repair or replace animal guards and remove any restrictions to assure free flow.
3.3.6.3 Scheduled Service: Inspect monthly, Maintain annually in the spring and fall.
3.3.7 Observation Ports
3.3.7.1 Inspect: If applicable, look for evidence of standing water in observation port or outlet structure, standing water may be evidence of hydraulic failure.
3.3.7.2 Maintain: If standing water is observed an evaluation of the Observation Port should be requested to be made by NPS testing or Subject Matter Experts. The Contractor’s sole responsibility in the PWS is to request the inspection and evaluation. The testing and technical evaluation and recommended repair is outside the scope of this work.
3.3.7.3 Scheduled Service: Inspect Annually. Maintain per any findings form NPS study. Costs for this maintenance if over and above routine cleaning are not within the scope of this contract.
3.3.8 Mulch
3.3.8.1 Inspect: Inspect for lack of or displacement of mulch in
Bioswale areas.
3.3.8.2 Maintain: Replace mulch to bring up all mulch to three-inch depth. Coordinate type of mulch with the National Park Service Contracting Officer’s Representative.
3.3.8.3 Scheduled Service: Monthly.
3.3.9 Runoff
3.3.9.1 Inspect: Quarterly inspection to ensure that runoff that flows into the cell as intended.
3.3.9.2 Maintain: Remove any accumulated debris, make sure that surrounding soil is stabilized.
3.3.9.3 Scheduled Service: Inspect quarterly and after storm events, maintain and repair if needed.
3.3.10 Water infiltration
3.3.10.1 Inspect: Ensure that water infiltrates in a timely manner and that ponding does not occur for more than 12-24 hours after a storm event. Conduct simple infiltration tests using a can on the soil surface filled with water and observe drainage.
3.3.10.2 Maintain: If tests show improper drainage, replace any modified soil layers where ponding exceeds drainage time allowed.
3.3.10.3 Scheduled Service: Inspect quarterly and after storm events.
Maintain and repair as required by inspections.
3.3.11 Erosion
3.3.11.1 Inspect: Inspect quarterly for erosion or gullying issues.
3.3.11.2 Maintain: fix any erosion immediately and take measures to re-establish vegetative cover, stabilize erosion along drainage paths using appropriate measures.
3.3.11.3 Service Schedule: Maintain and repair when issues are found.
3.3.12 Signage/Fencing
3.3.12.1 Inspect: Signage and fencing to assure that the required site signage and fencing is in place and in working order.
3.3.12.2 Maintain: Repair or replace as needed.
3.3.12.3 Scheduled Service: Inspect quarterly and after major weather events. Repair and Maintain if needed.
3.3.13 The performance requirement for the work as outlined above is to maintain 100% functionality of the stormwater structure system.
3.4 Contractor must maintain a maintenance log that records the following:
• Date of service.
• Name of individual/company performing service
• Type of maintenance performed.
• Amount (lbs.) and type(s) of sediment/debris/other material removed as result of cleaning.
• General observations and record of pavement condition.
• Name/signature of individual completing the inspection.
4.0 Location of Work – All work will be completed on property owned by the National Park Service. The locations of pervious pavement throughout the park are identified below and further described in the Schedule of Locations which is in the appendix.
Locations of Pervious Pavement for Base Requirement
4.1 Rock Creek Park: Beach Drive NW from Shoreham Drive NW to Picnic Grove 10
4.2 Rock Creek Park Multi-Use Trail: Broad Branch Road NW to P Street NW Ramp
4.3 Fort Reno Park
Locations of Structures:
4.4 Rock Creek Park: Beach Drive NW from Shoreham Drive NW to Picnic Grove 10
4.5 Rock Creek Park Multi-Use Trail: Broad Branch Road NW to P Street NW Ramp
4.6 Fort Reno Park
4.7 Bingham Drive NW, east of Oregon Avenue NW
5.0 Period of Performance – Contract Period: One (base) year from the date of award and up to four option years.
6.0 Performance or Delivery Schedule
6.1 This Contract is for one Calendar year, and four option years, of service from the date of award.
6.1.1 Reporting Schedule:
6.1.1.1 Monthly: The Contractor will deliver monthly, a report detailing all maintenance work and repairs completed for the preceding.
6.1.1.2 Quarterly: Report on all work completed in the preceding quarter outlining maintenance repairs to facilities or systems.
6.1.1.3 Event After Action report: Details work accomplished to bring system to full functionality after major weather events.
7.0 Performance Standards
7.1 For all tasks, performance will be assessed under the conditions described in the Quality Assurance and Surveillance Plan.
7.2 Pervious Pavement:
7.2.1 Post-cleaning testing of the permeable asphalt surface course is required and must conform to the methods of either ASTM C1701: Standard Test Method for Infiltration Rate of In-Place Pervious Concrete or ASTM C1781: Standard Test Method for Surface Infiltration Rate of Permeable Unit Pavement Systems. At least three locations must be used for the test, and they should be spaced evenly across the pervious paving system. Failure to achieve the minimum design infiltration rate of the surface course at one or more location indicates the system has not been cleaned fully and that this condition must be corrected to meet the requirements of this contract. All work shall conform to Section 3.5.7 of the District Department of Energy & Environment (DOEE)
“Stormwater Guidebook Permeable Pavement Systems.”
7.3 Stormwater Management Structures:
7.3.1 Each stormwater management structure is specifically designed for site conditions and are presented in Appendix B. Performance standards include maintaining the state of the facility as designed to ensure maximum performance. All work shall conform to Section 3.5.7 of the District Department of Energy & Environment (DOEE) “Stormwater Guidebook Permeable Pavement Systems.”
8.0 Special Requirements
8.1 Government-furnished Property: The Government will not be providing any property for this work.
8.2 Equipment Staging: The Government will not provide any temporary laydown yard or equipment parking site. Contractor must mobilize all equipment and materials daily.
8.3 Security: There are no known security requirements associated with this contract.
8.4 Travel: All Contractors and staff are to be local to the project. There are no travel requests expected. However, if requests arise any required travel must be authorized by an appropriate official and reimbursements for allowable travel and per diem charges are governed by P.L. 99-234 and FAR Part 31.}
8.5 Work Period: Work should be performed between the hours of 7:00 am and 5:00 pm, Monday through Friday, except for federal holidays when work is not authorized.
8.6 Non-disclosure/Conflict of Interest: There are no non-disclosure agreements required.
8.7 Special Requirements:
8.7.1 Personnel Qualifications: All personnel performing work shall be fully qualified and experienced in the type of work to be executed on this PWS.
When applicable, the personnel shall be certified on the necessary skills for the work being performed. Personnel operating vehicles or heavy equipment shall hold valid licenses and certifications for operation of said equipment. The NPS COR may, at any time, request copies of necessary certifications or licenses.
8.7.1.1 At a minimum, the Contractor must provide one on-site supervisor to direct all contract personnel and maintenance operations. This must be ensured any time work is being performed on the site.
8.7.1.2 The on-site supervisor shall be fluent in the English language to effectively communicate with the Contractor’s employees and/or Subcontractors as well as the COR/POC and other National Park Service personnel.
8.7.1.3 If the on-site supervisor is not on site or absent due to illness or other reasons, the Contractor shall provide an alternate supervisor to be on site managing and directing all contract personnel and maintenance operations. The alternate supervisor shall have similar job qualifications to those required for the designated on-site supervisor.
8.7.1.4 The onsite Supervisor shall be available for phone calls during all working hours.
8.7.2 Work on Site: The work is in National Park Service areas that will be in use by the public during work. Contractors should make all effort not to impede public access and use and should use proper decorum in any interactions. All vehicles, when not in use, must be parked so as not to block free access to the park roads, paths, and parking lots by the public.
8.7.3 Traffic Control Vehicular Access: Contractor should submit for NPS review a plan showing how work will be accessed and where equipment will be parked during work. This plan must be approved by NPS prior to the start of any work.
8.8 Code Compliance/Permits/Standards:
8.8.1 The ICC’s family of codes and their appendices are hereby adopted as the nationally recognized building codes for the NPS. Additionally, The National Electrical Code (NEC, NFPA 70, published by the National Fire Protection Association is adopted as the national code for electrical work.
8.8.2 Contractor will perform all work in accordance with the ICC’s family of codes and submit to the COR as the most recent edition of local, state, and federal guidelines, regulations and standards applicable to performance of these tasks. Amendment of certain ICC codes or the NEC specific to the NPS may be necessary to ensure park service compliance regarding the historical or environmental assets.
8.8.3 The Contractor shall hire a fully licensed third-party inspector for all applicable inspections falling under the ICC for this task. The Contractor shall submit the inspector(s) resumes as part of the pre-submittal for this contract.
8.8.4 Completed and signed inspection reports shall be submitted by the third-party inspector to the CO/COR or their designated representative, for prior review to final acceptance and closeout of the contract period. The CO is final authority for acceptance.
8.8.5 The Contractor is responsible for verifying any additional requirements with the CO, COR, or the designated representative.
8.8.6 The Contractor is responsible for obtaining any permits and holding the up to date business licenses for the jurisdiction where the work is to occur.
9.0 General Items
9.1 Index of Attachments
9.1.1 Attachment A: Quality Assurance and Surveillance Plan showing the required performance standards and service levels.
9.1.2 Attachment B: Schedule of Locations of pervious pavement and stormwater management structures.
9.1.3 Attachment C: Schedule of Tasks showing frequency for which each task should be completed.
9.1.4 Attachment D: District Department of Energy & Environment (DOEE) “Stormwater Guidebook Permeable Pavement Systems.”
Attachment A:
Quality Assurance and Surveillance Plan for the Repair and Maintenance of Stormwater Structures and Pervious Pavement
INTRODUCTION
This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled Repair and Maintenance of Stormwater Structures and Pervious Pavement. This plan sets forth the procedures and guidelines the National Park Service, Rock Creek Park (ROCR), will use in ensuring the required performance standards or services levels are achieved by the contractor.
Purpose
The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s Quality Control Plan (QCP), and to ensure that the Government pays only for the level of services received.
This QASP defines the roles and responsibilities of all members of the Integrated Project Team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.
Performance Management Approach
The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by ROCR to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.
Performance management represents a significant shift from the more traditional Quality Assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints. The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract if the critical outcomes expected are being achieved and/or the desired performance levels are being met.
Performance Management Strategy
The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own Quality Control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated Government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the Government to take advantage of the contractor’s QC program.
The Government representative(s) will monitor performance and review performance reports and maintenance logs furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The Government will make determination regarding incentives based on performance measurement metric data and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.
ROLES AND RESPONSIBILITIES
The Contracting Officer
The contracting officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by WOTR. The CO will designate one full-time Contractor Officer Representative or COR, as the Government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the
CO.
The Contracting Officer Representative
The Contracting Officer’s Representative (COR) is designated in writing by the CO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY
LEVELS
The required performance standards and/or quality levels are outlined in the Performance Requirements Summary. If the contractor meets the required service or performance level, it will be paid as agreed upon in the contract. Failure to meet the required service or performance level will result nonpayment until the work is performed to a satisfactory level.
METHODOLOGIES TO MONITOR PERFORMANCE
Surveillance Monitoring Techniques
To minimize the performance management burden, simplified surveillance methods may be used by the Government to evaluate contractor performance when appropriate. The primary methods of surveillance are:
• File Reviews – The COR will review the completed work from the Schedule of Locations and any other reports submitted by the contractor on a bi-weekly basis.
• Random monitoring, which shall be performed by the COR designated inspector.
• Periodic Inspection – COR typically performs the periodic inspections on a bi-weekly basis.
• Customer Complaints - COR will keep track of customer complaints on a bi-weekly basis.
Customer Feedback
The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction.
Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the CO and COR, as opposed to the contractor.
Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COR. The COR will accept those customer complaints and investigate.
Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.
Acceptable Quality Levels
The Acceptable Quality Levels (AQLs) are outlined throughout the PWS and in the Performance Requirements Summary, where contractor’s performance is structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls.
For certain critical activities such as those involving adherence to all Occupational Safety and Health Administration (OSHA) Regulation, specifically 29 CFR 1910 – General Industry and working closely with and alongside NPS personnel for the desired performance level is established at 90 percent. Other levels of performance are keyed to the relative importance of the task to the overall performance at ROCR.
QUALITY ASSURANCE DOCUMENTATION
The Performance Management Feedback Loop
The performance management feedback loop begins with the communication of expected outcomes. Performance standards are expressed in the performance requirements summary may be assessed using the surveillance monitoring techniques previously identified.
Monitoring Forms
The Government’s QA surveillance shall be reported using the Quality Assurance Monitoring Form or communicated in an email which shall contain the appropriate locations and dates when the work has been reported to be completed. The completed form and/or email will document the Government’s assessment of the contractor’s performance under the contract to ensure that the required service results are being achieved.
The COR will retain a copy of all completed QA surveillance forms.
ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
Determining Performance
Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels.
Reporting
At the end of each month, the COR may prepare a written report for the ACO summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report will become part of the QA documentation. It will enable the Government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.
Reviews and Resolution
The COR may require the contractor’s project manager, or a designated alternate, to meet with the CO, COR, and other Government IPT personnel as deemed necessary to discuss performance evaluation. The COR will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with the COR as often as required or per the contractor’s request. The agenda of the reviews may include:
• Monthly performance assessment data and trend analysis
• Issues and concerns of both parties
• Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis
• Recommendations for improved efficiency and/or effectiveness
• Issues arising from the performance monitoring processes
The Quality Assurance Report must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the CS.
PERFORMANCE REQUIREMENTS SUMMARY
The Government shall inspect the contractor’s performance of the Permeable Pavement Maintenance and the Inspection, Repair and Maintenance of Stormwater Structures under this contract periodically through the service and when the contractor declares the service complete.
The Government must do so to ensure that the contractor has performed in accordance with the performance standards. If the Government should find any performance deficiencies, the Contractor shall correct the deficiencies within 48-hours of written notification by the COR, POC, or CO.
Required
Services/Tasks (from PWS)
Performance Standard
Acceptable Quality Level
(AQL)
Method Used/ Frequency
Incentive (Positive and/or
Negative) (Impact on Contractor Payments)
Inspection:
Conduct visual inspection of pavement to determine that it is clean of debris
Per PWS 3.1.1.1
85% Quarterly No Payment will be made and sediment and that it is dewatered quarterly, or as needed at least four times annually. Inspect pavement after any major weather events such as rain or snowstorms.;
these inspections are in addition to the four annual inspections.
Monthly: Remove leaves and sediment so that it does not become ground down into the surface. Any materials blown off pavement need to be collected by the Contractor, weighed, and taken off site.
Per PWS 3.1.1.2.1
85% Monthly No Payment will be made
As needed: Dry out any ponding or moist areas of pavement if moss is observed and use a lime mortar mix to kill the moss and vacuum clean the surface.
Per PWS 3.1.1.2.2
85% As Needed No Payment will be made
Inspect, Repair and Maintain Stormwater Structures
Per PWS 3.3
85% As Detailed in the Schedule of Tasks
No Payment will be made
Contractor must maintain a maintenance log that records the following:
• Date of service.
• Name of individual/company performing service.
• Type of maintenance performed.
• Amount (lbs.) and type(s) of sediment/debris/other material removed as result of cleaning.
• General observations and record of pavement condition.
• Name/signature of individual completing the inspection.
• Additionally, if ASTM C1701 is performed (see Section 7.0 of this Scope of Work), the test results and locations should be included in the report.
Attachment B
Attachment C:
Description PWS Section Annually Quarterly Monthly As
Needed Fall Spring After Storm Events
BASE
REQUIREMENT
Inspection 3.1.1.1 X X Maintenance:
Monthly 3.1.1.2.1
X
Maintenance:
As Needed 3.1.1.2.2
X
DEBRIS
ACUMULATION 3.3.1
Inspect 3.3.1.1 X Maintain 3.3.1.2 X X X
Scheduled Service 3.3.1.3
X X X X
ENTRY POINTS
PRETREATMENT
AREAS 3.3.2
Inspect 3.3.2.1 X Maintain 3.3.2.2 X
Scheduled Service 3.3.2.3
X
(During growing season)
X
CULVERTS 3.3.3
Inspect 3.3.3.1 X X Maintain 3.3.3.2 X Scheduled Service 3.3.3.3
X
CHECK DAMS 3.3.4
Inspect 3.3.4.1 X Maintain 3.3.4.2 X Scheduled Service 3.3.4.3
X
ESTABLISHED
PLANTS &
TREES 3.3.5
Inspect 3.3.5.1 X Maintain 3.3.5.2 X
Scheduled Service 3.3.5.3
X X
INLETS &
OUTLETS 3.3.6
Inspect 3.3.6.1 X X Maintain 3.3.6.2 Scheduled Service 3.3.6.3
X X
OBSERVATION
PORTS 3.3.7
Inspect 3.3.7.1 X Maintain - N/A 3.3.7.2 Scheduled Service - N/A 3.3.7.3
MULCH 3.3.8
Inspect 3.3.8.1 X Maintain 3.3.8.2 X Scheduled Service 3.3.8.3
X
RUNOFF 3.3.9
Inspect 3.3.9.1 X X Maintain 3.3.9.2 X Scheduled Service 3.3.9.3
X X
WATER
INFILTRATION 3.3.10
Inspect 3.3.10.1 X X Maintain 3.3.10.2 X Scheduled Service 3.3.10.3
X
EROSION 3.3.11
Inspect 3.3.11.1 X Maintain 3.3.11.2 X Scheduled Service 3.3.11.3
X
SIGNAGE &
FENCING 3.3.12
Inspect 3.3.12.1 X X Maintain 3.3.12.2 X Scheduled Service 3.3.12.3
X
Attachment D:
| PERFORMANCE WORK STATEMENT (PWS) |
| for |
| Repair and Maintenance of Stormwater Structures and Pervious Pavement |
| 1.0 Background |
| 2.0 Scope |
| 3.0 Work to be Performed – The following are the tasks that will be performed by the contractor on a monthly, seasonal, and annual basis to fulfill this contract, as outlined in the Quality Assurance and Surveillance Plan and Schedule of Tasks in the ... |
| 3.1 Permeable Pavement Maintenance |
| 3.2 Permeable Pavement Repairs |
| 3.2.1 If inspections reveal repairs are needed to the pervious pavement, notify the COR within 24 hours of discovery. This contract does not involve repair to the pervious pavement infrastructure; reporting only. |
| 3.3 Inspect, Repair and Maintain Stormwater Structures at all locations shown in Paragraph 4 |