B.08.03_FTW 420_AM#03_20R0007.pdf

PDF 388 KB Posted

Attached to
FTW420 Repair Building 3448 Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

This document is an amendment to a solicitation for the repair of Building 3448 at Fort Wainwright in Alaska. The amendment extends the proposal due date from the original deadline to February 7, 2020 at 2:00 PM Alaska Standard Time. It also provides replacement drawings and sections as well as additional as-built files for the project. The opportunity involves the design and construction of repairs to Building 3448 and related utilities. The four offerors selected for Phase 2 of the selection process are listed. The estimated period of performance is indicated in the revised summary schedule, with design beginning in February 2020, construction starting in March 2020, and project turnover planned to be complete by the end of the estimated contract duration.

View the file

Other files for this federal contract opportunity

Other files attached to FTW420 Repair Building 3448, newest first.
File Type Posted
B.08.02_W91KB20R0007_AM#06.pdf PDF
B.08.03_FTW420_AM#04_20R0007.pdf PDF
B.08.03_FTW 420_AM#05_20R0007.pdf PDF
B.08.03_FTW 420_AM#02_20R0007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION: FTW420 Repair Building 3448, Fort Wainw right, Alaska

a. This amendment provides changes to the solicitation as indicated on the continuation pages of this document

b. PROPOSAL DUE DATE HAS BEEN EXTENDED TO 7 FEBRUARY 2020, 2:00PM AST. Proposals shall be submitted in accordance w ith Section 00 21 00, Para 1.9, Proposal Submittals.

c. YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THIS STANDARD FOR 1442.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Dec-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB20R0007

X 9B. DATED (SEE ITEM 11)

11-Oct-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Dec-2019

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911KB20R0007

AM#03

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. The following drawing is substituted for the superseded documents/sections:

NONE

b. The following revised documents/sections are substituted for the superseded documents/sections.

SECTION 00 11 00 – STANDARD FORM 1442, BLOCK 13

-The required response date/time has changed to 7 February 2020 at 02:00 PM

SECTION 00 22 20 PHASE 2 DESIGN-BUILD SELECTION PROCEDURES AND

BASIS OF AWARD

-Paragraph 5.4.1.2 – Changed NTP date to 12 Mar 2020 (Reissuing page 13 of the section)

NOTE: Revisions within the following documents do not contain the above referenced identifiers:

c. The following sections are deleted:

d. The following documents are added:

-FTW420 As-Builts Bldg 3448

(6 separate files sent via DoD Secure Access File Exchange (SAFE)

e. The following revisions are incorporated:

f. Other:

(End of Summary of Changes)

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME.

Section 00 22 20 W911KB20R0007

FTW420

5.4.1.2 Summary Schedule: Submit a summary level schedule for integrated design and construction.

Schedules or diagrams may be provided separately in a size that is easily read, but shall be bound and clearly labeled as Tab D. This summary schedule will, after contract award, be replaced with a project schedule as required by Section 01 32

01.00 29: Project Schedule. The summary schedule shall be task-oriented, indicating the number of calendar days, after notice to proceed, by which milestones are to be achieved. For proposal purposes, utilize a Notice to Proceed date of 16 Feb 2020 12 Mar 2020. This date is solely to assist in evaluation of offeror’s proposals and shall not be construed as a contractual NTP date. Offeror may use a critical path or other method of his choice; however, schedules shall be graphically represented. The proposed project schedule shall reflect the proposed contract duration. Give attention to the following features but limit narrative information to no more than three (3) pages total:

(1) Narrative:

(a) Provide the proposed contract duration.

(b) Provide a narrative, describing the design packaging plan for separate design packages, based on the Offeror’s plan for fast tracking. Describe all design and construction to be “fast-tracked” (See Section 01 33 16.00 29 Design After Award). If long lead item equipment must be ordered prior to completion of a design phase, describe the requirement in the narrative and show the required ordering date in the schedule.

Complete the following matrix summarizing the proposed design package review schedule

(not included in schedule narrative page limit).

Submittal Package Name (e.g.

Site/Utilities)

Stage (Interim, Final, Design Complete)

Submittal Date

Review Start Date

Review End Date

Review Conference Date (if applicable)

(2) Summary Schedule:

(a) Show the design phase, including events associated with coordinating the interim and final design submittals for each package and the proper handling of the review comments for each design package (See Section 01 33 16.00 29). For each submittal package noted in 5.5.1.2. (1)(b) above, show date submitted to Government, Government review period and Review Conference on summary schedule.

(b) Show the overall construction phase for the facility and for utilities. Show fast track starts for design packages but it isn’t necessary to show the detailed breakdown construction (e.g., by trades) of the facility and utilities.

(c) Show commissioning activities.

(d) Show turnover of the facility. Identify any proposed phased turnovers. The