This document contains bid schedules for telecommunication tower repair work at multiple sites within Nevada. The schedules provide itemized estimates for materials, labor, and total costs for tasks such as installing grounding systems, replacing equipment, and upgrading electrical and antenna infrastructure. Relevant work includes installing ground rods and conductors, trenching, bonding equipment, and procuring backup power systems. The solicitation was issued by the Bureau of Land Management National Office as opportunity number 140L0621R0029 for Nevada Telecommunication Tower Repairs. Costs are estimated at the item level by site, with summaries of material, labor, overhead, and total projected expenses.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L0621R0029_Amd_0001.pdf | ||
| Attch_15_Contractor_Q_and_A_0001.pdf | ||
| Attch_2_WD_Churchill_County.pdf | ||
| Sol_140L0621R0029.pdf | ||
| Attch_11_WD_Washoe_County.pdf | ||
| Attch_9_WD_Lincoln_County.pdf | ||
| Attch_6_WD_Eureka_County.pdf | ||
| Attch_1_Specifications_and_Drawings.pdf | ||
| Attch_14_Government_Furnished_Property.pdf | ||
| Attch_8_WD_Lander_County.pdf | ||
| Attch_4_WD_Elko_County.pdf | ||
| Attch_13_Order_of_Precedence.pdf | ||
| Attch_10_WD_Nye_County.pdf | ||
| Attch_7_WD_Humboldt_County.pdf | ||
| Attch_5_WD_Esmeralda_County.pdf | ||
| Attch_3_WD_Clark_County.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEVADA STATEWIDE TELECOMMUNICATION SAFETY REPAIRS
BID SCHEDULES
BATTLE MOUNTAIN AIR TANKER BASE – BID SCHEDULE
BID ITEM SOW
REF
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $ Electrical One‐Line for Modification to Existing Electrical Service 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.5 COMMERCIAL ELECTRIC
Electrical Service‐Entrance Grounding 3.5 each 1 $ $ $
3.5 ‐ Subtotal $ $ $
3.9 RADIO EQUIPMENT WORKSTATION
Subsystem Ground Bus Bar (SSGB) installed at Workstation (2"x12"x¼” minimum) 3.9 Lump Sum 1 $ $ $ Equipotential Bonding of Radio Equipment and Ancillary Devices located within 5 feet Horizontal and 8 feet Vertical from each Dispatch Operator Workstation. 3.9 4 $ $ $
3.7 ‐ Subtotal $ $ $
3.10 ELECTRICAL SURGE PROTECTION DEVICE
Primary Surge Protection Device (SPD) at Electrical Service‐Entrance ‐ Type 1 3.10 1 $ $ $
3.11 ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Rod: (minimum 3/4" diameter, 10‐foot long) 3.14 each 3 $ $ $ External Ground Bus Bar (EGB) Installation ‐ Remote Facilities 3.14 each 1 $ $ $ External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper (with trench) for Interconnection of Ground Rods 3.14 per lineal foot 140 $ $ $
External Ancillary Device Grounding ‐ H‐Frame Support Posts 3.14 each 2 $ $ $ RF Cables Grounded at Base of Tower 3.14 each 2 $ $ $ RF Cable Grounding Prior to Entering the Building 3.14 each 2 $ $ $ RF Cable Surge Protection 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Master Ground Bus Bar (MGB) at the Electrical Service‐Entrance (Occupied): 3.15 each 1 $ $ $ Subsystem Ground Bus Bar at RF Entrance (SSGB): (2"x12"x¼” minimum) 3.15 each 1 $ $ $ RF Cable Surge Protection 3.14 each 2 $ $ $
3.15 ‐ Subtotal $ $ $
LABOR AND MATERIALS ‐ TOTAL $ $ $
COST SUMMARY MATERIALS LABOR TOTAL
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
PROFIT $ $ $
TOTAL ESTIMATED COST $ $ $
FORT SAGE– BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Site Access Via Helicopter ‐ Personnel 1.4 Per Rotor Hour 12 $ $ $
Site Access Via Helicopter ‐ Haul Equipment and Materials 1.4 Per Rotor Hour 6 $ $ $
The Contractor shall hire a Third‐party Inspector 1.5 Lump Sum 1 $ $ $ Civil Improvement Plans 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Existing Tower Ground Bus Bar (TGB) to New Ground Ring 3.14 each 1 $ $ $ Three 20 ft. Radials ‐ Each Includes One 10 ft. Long, 3/4 in. Diameter Ground Rod Installed Horizontal Interconnected to Ground Ring with 10 ft. #2 AWG in 30 in. Deep x 12 in. wide Trench Embedded in 2 inches of GEM = 27 Bags Includes Two Exothermic Welds Ea. (6 total) and 30 ft. #2 AWG
3.14 Lump Sum 3 $ $ $
Trenching for Ground Ring (80 ft.) and Radials (60 ft.) 3.14 per lineal foot 140 $ $ $
Shelter Ground Ring (SGR): Four 10 ft. Long, 3/4 in. Diameter Ground Rods Installed Horizontal, Spaced 14 ft.
Apart On Center in 30 in. Deep x 12 in. wide Trench Interconnected with #2 AWG Embedded in 2 inches of GEM = 34 Bags Includes Two Exothermic Welds Ea. (8 total) and 20 ft. #2 AWG
3.14 Lump Sum 1 $ $ $
Grounding Enhancement Material (GEM) ‐ GEM25A or Equivalent 3.14 Per Bag 61 $ $ $
Backfilling for Grounding System 3.14 per cubic yard 47 $ $ $
External Ancillary Device Grounding including Shelter Tabs x 2 and Outriggers x 4 3.14 each 6 $ $ $ RF Cables Grounded at Base of Mast 3.14 each 2 $ $ $ RF Cable Grounding at Entry Port using PEPRO proprietary stainless steel grounding strap 3.14 each 2 $ $ $ RF Cable Surge Protection 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Ground Rack‐Mounted Equipment ‐ 2 VHF Radios and Two Duplexers 3.16 each 4 $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
GOOSEY – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $ Civil Improvement Plan 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.4 CIVIL DEVELOPMENT AND DEMOLITION
Remove Existing Grounding System Components 3.4 Lump Sum 1 $ $ $
3.4 ‐ Subtotal $ $ $
3.5.1 PHOTOVOLTAIC POWER AND BATTERY BACKUP SYSTEM
Procure and Install DC Power Surge Protection 3.5.1 each 2 $ $ $
3.5.1 ‐ Subtotal $ $ $
3.12 TOWER AND ANTENNA SYSTEMS
Service Existing Safety Climb Cable 3.12 each 1 $ $ $ Install Anti‐Climb Panels 3.12 each 1 $ $ $
3.12 ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Rod: (minimum 3/4" diameter, 10‐foot long) 3.14 each 4 $ $ $ Ground Polyphaser Earthed Entrance panel to Ground Ring 3.14 each 1 $ $ $ Ground Existing Tower Ground Bus Bar (TGB) to Ground Ring 3.14 each 1 $ $ $ External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper (with trench) for Interconnection of Ground Rods 3.14 per lineal foot 60 $ $ $
Tower Ground Ring (TGR) Installation 3.14 Lump Sum 1 $ $ $ Self‐Supporting Tower Leg Grounding 3.14 each 3 External Ancillary Device Grounding ‐ Bollards x 4 and HVAC 3.14 each 5 $ $ $ Self‐Supporting Ice‐Bridge Grounding 3.14 Lump Sum 1 $ $ $
3.14 ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
30‐inch Deep x 12‐inch Wide Trench for Ground Ring and Radials 3.14 per lineal foot 160 $ $ $
Ground Rod: (minimum 3/4" diameter, 10‐foot long) For Ground Ring and Radial Grounds 3.14 each 8 $ $ $ Ground Existing Polyphaser Earthed Entrance Panel to Ground Ring 3.14 each 1 $ $ $ Tower Ground Bus Bar (TGB) Installation ‐ Remote Facilities 3.14 each 1 $ $ $ Install Radial Ground Conductors # 2 AWG, bare, solid, tinned, copper using Exothermic Welds to Ground Rods 3.14 per lineal foot 80 $ $ $
Grounding Enhancement Material 3.14 each 68 $ $ $
Shelter Ground Ring (SGR) Installation Communications Shelter using Exothermic Welds to Ground Rods 3.14 per lineal foot 80 $ $ $
Unit of Measure UNITS MATERIALS LABOR TOTAL
Self‐Supporting Tower Leg Grounding 3.14 each 3 $ $ $ Shelter Frame Corner Grounding for Comm and Gen Shelter 3.14 each 4 $ $ $ Non‐Self‐Supporting Ice‐Bridge Grounding 3.14 each 1 $ $ $ Non‐Self‐Supporting Ice‐Bridge Isolators 3.14 each 1 $ $ $ RF Cables Grounded at Base of Tower 3.14 each 1 $ $ $
3.15 ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Ground Internal Ancillary Devices in Shelter 3.15 each 3 $ $ $ Ground Cable Runway to PEEP 3.15 each 1 $ $ $ Ground Door and Doorframe to Halo 3.15 each 1 $ $ $
3.15 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Relocate Standard Equipment Rack to Meet Workspace Requirements 3.16 each 1 $ $ $ Rack Ground Bus Bar (RGB) 3.16 each 1 $ $ $ Ground Rack‐Mounted Equipment (per device to be grounded) 3.16 each 4 $ $ $
3.16 ‐ Subtotal $ $ $
3.17 INTERNAL CABLE INSTALLATION
RF Cabling Installation (Racks and Cabinets) 3.17 Lump Sum 1 $ $ $
3.17 ‐ Subtotal $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
HAYFORD PEAK – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Site Access Via Helicopter ‐ Personnel 1.4 Per Rotor Hour 12 $ $ $
Site Access Via Helicopter ‐ Haul Equipment and Materials 1.4 Per Rotor Hour 6 $ $ $
The Contractor shall hire a Third‐party Inspector 1.5 Lump Sum 1 $ $ $ Civil Improvement Plans 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Existing Tower Ground Bus Bar (TGB) to New Ground Ring 3.14 each 1 $ $ $ Three 20 ft. Radials ‐ Each Includes One 10 ft. Long, 3/4 in. Diameter Ground Rod Installed Horizontal Interconnected to Ground Ring with 10 ft. #2 AWG in 30 in. Deep x 12 in. wide Trench Embedded in 2 inches of GEM = 27 Bags Includes Two Exothermic Welds Ea. (6 total) and 30 ft. #2 AWG
3.14 Lump Sum 3 $ $ $
Trenching for Ground Ring (80 ft.) and Radials (60 ft.) 3.14 per lineal foot 140 $ $ $
Shelter Ground Ring (SGR): Four 10 ft. Long, 3/4 in. Diameter Ground Rods Installed Horizontal, Spaced 14 ft.
Apart On Center in 30 in. Deep x 12 in. wide Trench Interconnected with #2 AWG Embedded in 2 inches of GEM = 34 Bags Includes Two Exothermic Welds Ea. (8 total) and 20 ft. #2 AWG
3.14 Lump Sum 1 $ $ $
Grounding Enhancement Material (GEM) ‐ GEM25A or Equivalent 3.14 Per Bag 61 $ $ $
Backfilling for Grounding System 3.14 per cubic yard 47 $ $ $
External Ancillary Device Grounding including Shelter Tabs x 2 and Outriggers x 4 3.14 each 6 $ $ $ RF Cables Grounded at Base of Mast 3.14 each 2 $ $ $ RF Cable Grounding at Entry Port using PEPRO proprietary stainless steel grounding strap 3.14 each 2 $ $ $ RF Cable Surge Protection 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Ground Rack‐Mounted Equipment ‐ 2 VHF Radios and Two Duplexers 3.16 each 4 $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
MOHAWK PEAK – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Ground Internal Ancillary Devices in Shelter 3.15 each 2 $ $ $ Ground Cable Runway to Polyphaser Earthed Entrance Panel (PEEP) 3.15 each 1 $ $ $ Ground Door and Doorframe to Halo 3.15 each 1 $ $ $
3.15 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Replace non‐compliant grounding connections used to bond grounding conductors to the rack mounted equipment and Rack Ground Bus Bar 3.16 each 8 $ $ $
Drill Additional Hole in PEEP for RGB Grounding Conductor Two‐Hole Connection and Install Stainless Steel Hardware 3.16 each 1 $ $ $
3.16 ‐ Subtotal $ $ $
3.17 INTERNAL CABLE INSTALLATION
Properly Route, Separate, and Fasten RF Cabling, DC Power Wiring, and Grounding Conductors to Cable Ladder 3.17 Lump Sum 1 $ $ $
Install New Cable Ladder 3.17 Lump Sum 1 $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Warm Springs 01 11 00 ‐ 11 Bid Schedule 5/14/2021
MOUNT IRISH – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Site Access Via Helicopter ‐ Personnel 1.4 Per Rotor Hour 12 $ $ $
Site Access Via Helicopter ‐ Haul Equipment and Materials 1.4 Per Rotor Hour 6 $ $ $
The Contractor shall hire a Third‐party Inspector 1.5 each 1 $ $ $ Civil Improvement Plans 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
2.6 NEW COMMUNICATIONS EQUIPMENT CABINET
Procure New Outdoor Cabinet ‐ 38‐inch W x 45‐inch D x 67‐inch H, Single‐Bay Micro Cabinet with a 20‐ foot articulating pipe‐mast designed by PEPRO, LLC. Includes Delivery to Ely, Nevada 2.6.1 each 1 $ $ $
2.6 ‐ Subtotal $ $ $
3.5.1 PHOTOVOLTAIC POWER AND BATTERY BACKUP SYSTEM
Procure and Install Solar Panels 3.5.1 each 2 $ $ $ Solar Panel Frame 3.5.1 each 1 $ $ $ Procure and Install External Wiring between Solar Panels and Entrance to the Shelter (Above Grade) 3.5.1 Lineal Foot 10 $ $ $ Procure and Install Photovoltaic Charger/Controller (30 ‐ Ampere) including internal wiring 3.5.1 each 1 $ $ $ Procure and Install Batteries 3.5.1 each 4 $ $ $
3.5.1 ‐ Subtotal $ $ $
3.7 COMMUNICATIONS EQUIPMENT CABINET INSTALLATION
Deliver and Install Cabinet 3.7 each 1 $ $ $
3.7 ‐ Subtotal $ $ $
3.11 EXTERNAL RF CABLE & WAVEGUIDE INSTALLATION
RF Cable Routing and Support (Pipe‐Masts) 3.11 each 2 $ $ $ RF Cable Entrance Installation and Sealing 3.11 each 2 $ $ $ Provide and Install New RF Cables for BLM Antenna between Shelter and Tower 3.11 Lineal Foot 40 $ $ $ Provide FDR Testing (Sweeping) for new RF Cables 3.11 each 2 $ $ $
3.11 ‐ Subtotal $ $ $
3.12 ANTENNA SYSTEMS INSTALLATION
Antenna Installation (Secured, Plumb, RF Cable Weather Seal) 3.12 each 2 $ $ $
3.12 ‐ Subtotal $ $ $
Warm Springs 01 11 00 ‐ 12 Bid Schedule
BID ITEM SOW
REF
Unit of Measure UNITS MATERIALS LABOR TOTAL
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Existing Tower Ground Bus Bar (TGB) to New Ground Ring 3.14 each 1 $ $ $ Three 20 ft. Radials ‐ Each Includes One 10 ft. Long, 3/4 in. Diameter Ground Rod Installed Horizontal Interconnected to Ground Ring with 10 ft. #2 AWG in 30 in. Deep x 12 in. wide Trench Embedded in 2 inches of GEM = 27 Bags Includes Two Exothermic Welds Ea. (6 total) and 30 ft. #2 AWG
3.14 Lump Sum 3 $ $ $
Trenching for Ground Ring (80 ft.) and Radials (60 ft.) 3.14 per lineal foot 140 $ $ $
Shelter Ground Ring (SGR): Four 10 ft. Long, 3/4 in. Diameter Ground Rods Installed Horizontal, Spaced 14
ft. Apart On Center in 30 in. Deep x 12 in. wide Trench Interconnected with #2 AWG Embedded in 2 inches of GEM = 34 Bags Includes Two Exothermic Welds Ea. (8 total) and 20 ft. #2 AWG
3.14 Lump Sum 1 $ $ $
Grounding Enhancement Material (GEM) ‐ GEM25A or Equivalent 3.14 Per Bag 61 $ $ $
Backfilling for Grounding System 3.14 per cubic yard 47 $ $ $
External Ancillary Device Grounding including Shelter Tabs x 2 and Outriggers x 4 3.14 each 6 $ $ $ RF Cables Grounded at Base of Mast 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Relocate Rack‐Mounted Equipment from Existing Shelter to new Equipment Cabinet Includes Installation, Power Connection, Grounding, and RF Cable Connections 3.16 each 2 $ $ $
3.16 ‐ Subtotal $ $ $
3.17 INTERNAL CABLE INSTALLATION
RF Cabling Installation between Radio Equipment and RF Cable Entrance (Separation and Grouping) 3.17 each 2
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Warm Springs 01 11 00 ‐ 13 Bid Schedule
FAIRVIEW PEAK– BID SHEDULE
BID ITEM SOW REF Unit of Measure UNITS MATERIALS LABOR TOTAL
2.3 DESIGN DRAWINGS (A&E)
Civil Improvement Plans 2.3 each 1 $ $ $ Electrical One‐Line for Modification to Existing Electrical Service 2.3 each 1 $ $ $ Third Party Inspection Services 3.6 each 1 $ $ $
2.3 DESIGN SERVICES $ $ $
3.5.1 PHOTOVOLTAIC POWER AND BATTERY BACKUP SYSTEM
Procure and Install Solar Panels 3.5.1 each 2 $ $ $ Solar Panel Frame 3.5.1 Lineal Foot 1 $ $ $ Procure and Install External Wiring between Solar Panels and Entrance to the Shelter 3.5.1 Lineal Foot 20 $ $ $ Procure and Install Photovoltaic Charger/Controller (60 ‐ Ampere) including internal wiring 3.5.1 each 1 $ $ $ Procure and Install Batteries 3.5.1 each 4 $ $ $ Install DC Wiring 3.5.1 each 3 $ $ $
3.5.1 Photovoltaic and Battery System ‐ SUBTOTAL $ $ $
3.7 COMMUNICATIONS EQUIPMENT SHELTER INSTALLATION
Deliver, and Install Government Provided Pepro Cabinet with 20‐foot articulating mast 2.6 Lump Sum 1 $ $ $
3.7 Shelter ‐ SUBTOTAL $ ‐ $ ‐ $ ‐
3.11 EXTERNAL RF CABLE & WAVEGUIDE INSTALLATION
RF Cable Routing and Support (Pipe‐Masts) 3.11 1 $ $ $ RF Cable Entrance Installation and Sealing 3.11 each 1 $ $ $ RF Cable Testing and Report 3.17 each 1 $ $ $ Ground RF Cable to Entry Port using Stainless Steel Strap Provided by Pepro 3.11 each 1 $ $ $
3.11 External Cable Installation ‐ SUBTOTAL $ $ $
3.12 ANTENNA SYSTEMS INSTALLATION
Antenna Installation (Secured, Plumb, RF Cable Weather Seal) 3.12 each 1 $ $ $
3.12 Antenna Systems ‐ SUBTOTAL $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Trenching for Grounding System 3.14 per lineal foot 120 $ $ $
Provide and Install Ground Rods: (3/4" diameter, 10‐foot long) Includes Exothermic Connections 3.14 each 6 $ $ $ Grounding Enhancement Materials 3.14 Per Bag 51 $ $ $ Provide and Install External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper for Grounding System 3.14 per lineal foot 200 $ $ $
Backfilling for Grounding System 3.14 per Cubic Yard 50 $ $ $
Warm Springs 01 11 00 ‐ 14 Bid Schedule
BID ITEM SOW REF Unit of Measure UNITS MATERIALS LABOR TOTAL
Bond Existing Tower Ground Bus Bar (TGB) to Ground Ring ‐ Remote Facilities 3.14 each 1 $ $ $ Concrete Encased Electrodes in Shelter Foundation Connected to the Shelter Ground Ring 3.14 each 4 $ $ $ Ground Each Grounding Tab on the Cabinet (x3) to the Grounding System 3.14 each 3 $ $ $ Solar Panel and Framework Grounding 3.14 Lump Sum 1 $ $ $ RF Cables Grounded at Base of Pipe Mast 3.14 each 1 $ $ $ Ground RF Cable to Entry Port using Stainless Steel Strap Provided by Pepro 3.14 each 1 $ $ $ RF Cable Surge Protection 3.14 1 $ $ $
3.14 External Grounding ‐ SUBTOTAL $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Radio Equipment Installation in Cabinet 3.16 each 1 $ $ $ Ancillary Equipment Installation in Cabinet 3.16 each 2 $ $ $ Ground Rack‐Mounted Equipment (per device to be grounded) 3.16 each 3 $ $ $
3.16 Equipment Racks and Cabinets ‐ SUBTOTAL $ $ $
LABOR AND MATERIALS ‐ SUBTOTAL $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Warm Springs 01 11 00 ‐ 15 Bid Schedule
PROSPECT PEAK – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $ Civil Improvement Plan 2.3 each 1 $ $ $ Electrical One‐Line for Modification to Existing Electrical Service 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.4 CIVIL DEVELOPMENT AND DEMOLITION
Perimeter Fence Demolition 3.4 Lump Sum 1 $ $ $
3.4 ‐ Subtotal $ $ $
3.5 COMMERCIAL ELECTRIC
Electrical Service Cable Installation (Below Grade ‐ 100 ‐ Ampere) with Conduit in Trench 3.5 per lineal foot 60 $ $ $
Install New H‐Frame and Relocate Electrical Service‐Disconnect/Meter Panel to H‐Frame 3.5 each 1 $ $ $ Neutral‐To‐Ground Bond installed 3.5 each 1 $ $ $ Replace Existing 40‐Amp Electrical Distribution Panel In Shelter with a 100‐Amp Distribution Panel 3.5 each 1 $ $ $
Secondary Electrical Service Below Grade between Service‐Disconnect/Meter and Shelter 3.5 per lineal foot 20 $ $ $
3.5 ‐ Subtotal $ $ $
3.7 SHELTER REMEDIATION
Repair Holes in Exterior Wall of Shelter, Seal Cracks, and Repaint Exterior to Match Existing Color 3.7 Lump Sum 1 $ $ $ Install Screens in Intake and Exhaust Vent Hoods 3.7 each 2
3.7 ‐ Subtotal $ $ $
3.10 ELECTRICAL SURGE PROTECTION DEVICE REQUIREMENTS
Primary Surge Protection Device (SPD) at Electrical Service‐Entrance 3.10 each 1 $ $ $
3.10 ‐ Subtotal $ $ $
3.12 TOWER REMEDIATION
Install Anti‐Climb device on existing Tower Climber Access Ladder 3.12 each 1 $ $ $
3.12 ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground H‐Frame Support Posts and Unistrut to Existing Grounding System 3.14 each 1 $ $ $
3.14 ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Warm Springs 01 11 00 ‐ 16 Bid Schedule
BID ITEM SOW
REF
Unit of Measure UNITS MATERIALS LABOR TOTAL
Internal Perimeter Ground in Shelter #2 AWG, green‐jacketed, stranded, copper 3.15 per lineal foot 40 $ $ $
Ground Internal Ancillary Devices in Shelter 3.15 each 3 $ $ $ Ground Cable Runway to SSGB in Shelter 3.15 each 1 $ $ $ Ground Door and Doorframe to IPG in Shelter 3.15 each 1 $ $ $
3.15 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Replace non‐compliant grounding connections used to bond the grounding conductor for the rack ground bus bar to the MGB to with UL 467‐listed two‐hole connectors. 3.16 each 2 $ $ $
Replace two‐hole grounding connections and butted seam connectors used to bond rack mounted equipment grounding conductors to the rack ground bus bar and equipment with UL 467‐listed single‐ hole connectors
3.16 each 8 $ $ $
3.16 ‐ Subtotal $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Warm Springs 01 11 00 ‐ 17 Bid Schedule
RUBY MOUNTAIN HOT SHOTS – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $ Civil Improvement Plans 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Rod: (minimum 3/4" diameter, 10‐foot long) 3.14 each 4 $ $ $ Ground Polyphaser Earthed Entrance panel to Ground Ring 3.14 each 1 $ $ $ Ground Existing Tower Ground Bus Bar (TGB) to Ground Ring 3.14 each 1 $ $ $ External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper (with trench) for Interconnection of Ground Rods 3.14 per lineal foot 60 $ $ $
Tower Ground Ring (TGR) Installation 3.14 Lump Sum 1 $ $ $ Self‐Supporting Tower Leg Grounding 3.14 each 3 $ $ $ External Ancillary Device Grounding ‐ Bollards x 4 and HVAC 3.14 each 5 $ $ $
3.14 ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Replace the noncompliant, yellow, butted‐seam connector used to ground the telephone service entrance module to the subsystem ground bus bar with a UL 467‐listed, single‐hole, irreversible crimp connector 3.15 each 1 $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Warm Springs 01 11 00 ‐ 18 Bid Schedule
WARM SPRINGS – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.15 COMMON INTERNAL GROUNDING
Ground Internal Ancillary Devices in Shelter 3.15 each 3 $ $ $ Ground Cable Runway to Polyphaser Earthed Entrance Panel (PEEP) 3.15 each 1 $ $ $ Ground Door and Doorframe to Halo 3.15 each 1 $ $ $
3.15 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Replace non‐compliant grounding connections used to bond grounding conductors to the rack mounted equipment and Rack Ground Bus Bar 3.16 each 4
3.16 ‐ Subtotal $ $ $
3.17 INTERNAL CABLE INSTALLATION
Properly Route, Separate, and Fasten RF Cabling, DC Power Wiring, and Grounding Conductors to Cable Ladder 3.17 Lump Sum 1 $ $ $
Install New Cable Ladder 3.17 Lump Sum 1 $ $ $
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Wells SEAT Base 01 11 00 ‐ 19 Bid Schedule
WELLS SEAT BASE – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Third Party Inspection Services 1.5 each 1 $ $ $
Civil Improvement Plan 2.3 each 1 $ $ $
Electrical One‐Line for Modification to Existing Electrical Service 2.3 Lump Sum 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.8 RADIO EQUIPMENT WORKSTATION
Subsystem Ground Bus Bar (SSGB) at the Radio Equipment Workstation: (2"x12"x¼” minimum) 3.8 each 1 $ $ $ Equipotential Bonding of Dispatch Equipment and Ancillary Devices located within 5 feet Horizontal and 8 feet Vertical from each Dispatch Operator Workstation. 3.8 each 4 $ $ $
Fasten Existing RF Cable Surge Protection Devices to New SSGB 3.8 each 2 $ $ $
3.8 ‐ Subtotal $ $ $
3.10 ELECTRICAL SURGE PROTECTION DEVICE
Primary Surge Protection Device (SPD) at Electrical Service‐Entrance ‐ Type 1 3.10 each 1 $ $ $
3.11 ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Trenching for External Grounding System 3.14 per lineal foot 10 $ $ $
Install additional Ground Rod: (minimum 3/4" diameter, 10‐foot long) 3.14 each 1 $ $ $ External Ground Bus Bar (EGB) Installation ‐ Remote Facilities 3.14 each 2 $ $ $
External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper to Interconnect Ground Rods 3.14 per lineal foot 10 $ $ $
Ground Each Antenna Pipe Mast 3.14 each 2 $ $ $ RF Cable Grounding Prior to Entering the Building 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
Wells SEAT Base 01 11 00 ‐ 20 Bid Schedule
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
Wells SEAT Base 01 11 00 ‐ 21 Bid Schedule
MICA PEAK – BID SCHEDULE
Unit of Measure UNITS MATERIALS LABOR TOTAL
GENERAL
Site Access Via Helicopter ‐ Personnel 1.4 Per Rotor Hour 12 $ $ $
Site Access Via Helicopter ‐ Haul Equipment and Materials 1.4 Per Rotor Hour 6 $ $ $
The Contractor shall hire a Third‐party Inspector 1.5 Lump Sum 1 $ $ $ Civil Improvement Plans 2.3 each 1 $ $ $
GENERAL ‐ Subtotal $ $ $
3.14 COMMON EXTERNAL GROUNDING SYSTEM
Ground Existing Tower Ground Bus Bar (TGB) to New Ground Ring 3.14 each 1 $ $ $ Three 20 ft. Radials ‐ Each Includes One 10 ft. Long, 3/4 in. Diameter Ground Rod Installed Horizontal Interconnected to Ground Ring with 10 ft. #2 AWG in 30 in. Deep x 12 in. wide Trench Embedded in 2 inches of GEM = 27 Bags Includes Two Exothermic Welds Ea. (6 total) and 30 ft. #2 AWG
3.14 Lump Sum 3 $ $ $
Trenching for Ground Ring (80 ft.) and Radials (60 ft.) 3.14 per lineal foot 140 $ $ $
Shelter Ground Ring (SGR): Four 10 ft. Long, 3/4 in. Diameter Ground Rods Installed Horizontal, Spaced 14 ft.
Apart On Center in 30 in. Deep x 12 in. wide Trench Interconnected with #2 AWG Embedded in 2 inches of GEM = 34 Bags Includes Two Exothermic Welds Ea. (8 total) and 20 ft. #2 AWG
3.14 Lump Sum 1 $ $ $
Grounding Enhancement Material (GEM) ‐ GEM25A or Equivalent 3.14 Per Bag 61 $ $ $
Backfilling for Grounding System 3.14 per cubic yard 47 $ $ $
External Ancillary Device Grounding including Shelter Tabs x 2 and Outriggers x 4 3.14 each 6 $ $ $ RF Cables Grounded at Base of Mast 3.14 each 2 $ $ $ RF Cable Grounding at Entry Port using PEPRO proprietary stainless steel grounding strap 3.14 each 2 $ $ $ RF Cable Surge Protection 3.14 each 2 $ $ $
3.14 ‐ Subtotal $ $ $
3.16 EQUIPMENT RACKS AND CABINETS
Ground Rack‐Mounted Equipment ‐ 2 VHF Radios and Two Duplexers 3.16 each 4 $ $ $
Wells SEAT Base 01 11 00 ‐ 22 Bid Schedule
MATERIAL HANDLING AND DELIVERY $ $ $
MOBILIZATION FEES $ $ $
OTHER DIRECT COSTS $ $ $
BOND $ $ $
PROJECT MANAGEMENT FEES $ $ $
OVERHEAD $ $ $
File details come from the government source that posted it. Updated .