Attachment1-TechnicalSpecifications.pdf
PDF 6 MB Posted
- Attached to
- Timberline Lodge Waterline Emergency Replacement Federal contract opportunity
- Solicitation number
- 1240BH23R0030
About this file
This solicitation is for the Timberline Lodge Waterline Emergency Replacement project. The Forest Service is seeking to replace all existing polypropylene and specialty pipes with new copper piping and specialties at the Timberline Lodge located in Mount Hood National Forest. Bids are due by June 15, 2023. The awarded contract will require the contractor to demolish the existing polypropylene piping installed in 2010 and replace it with new copper piping following the same routes and sizes. Associated work will include wall and ceiling demolition and reconstruction. The project is intended to restore domestic water distribution to the historic lodge.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment2.pdf | ||
| Amendment1.pdf | ||
| CompleteSolicitation.pdf | ||
| Attachment2-ProjectDrawings.pdf | ||
| Attachment3-WageDetermination.pdf | ||
| Attachment4-BidBond.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Timberline Lodge Waterline Emergency Replacement
Mt. Hood National Forest
100% CONSTRUCTION DOCUMENTS
March 03, 2023
03/03/2023 Timberline Lodge Waterline Emergency Replacement T.O.C. - 1
SUMMARY
TIMBERLINE LODGE POTABLE PLUMBING
REPLACEMENT PROJECT MANUAL
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 SUMMARY
01 30 00 01 33 00
ADMINISTRATIVE REQUIREMENTS
SUBMITTAL PROCEDURES
01 35 91 HISTORIC TREATMENT PROCEDURES
HISTORIC BUILDING PRESERVATION
PLAN
01 40 00 QUALITY REQUIREMENTS
01 42 19 REFERENCE STANDARDS
01 50 00 TEMPORARY FACILITIES AND
CONTROLS
01 60 00 PRODUCT REQUIREMENTS
01 70 00 EXECUTION AND CLOSEOUT
REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 01 30.75 CONCRETE AND MASONRY REPAIR
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 FIRESTOPPING
DIVISION 08 - OPENINGS
08 31 00 ACCESS DOORS AND PANELS
DIVISION 09 - FINISHES
09 21 16 GYPSUM BOARD
ASSEMBLIES
03/03/2023 Timberline Lodge Waterline Emergency Replacement T.O.C. - 2
09 51 00 ACOUSTICAL CEILINGS
09 90 00 PAINTING AND COATING
DIVISION 22 -
PLUMBING
22 05 00 COMMON WORK RESULTS FOR PLUMBING
22 05 23 GENERAL DUTY VALVES FOR PLUMBING PIPING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND
EQUIPMENT
22 05 53 22 07 00
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
PLUMBING INSULATION
22 10 06 PLUMBING PIPING SPECIALTIES
22 11 17 FACILITY POTABLE WATER DISTRIBUTION PIPING
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 10 00. - 1
SECTION 01 10 00
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.02 PROJECT
A. Project Name: Timberline Lodge Potable Plumbing Replacement.
B. The Project consists of the replacement of the all-existing polypropylene (PP-R) and specialty pipes with copper piping and specialties as specified in Division 22. All previously installed PP-R piping will be replaced.
C. Attached PP-R piping construction drawings of 2010 show the existing PP-R piping routes and sizes. Prior to 2010, all domestic water piping were copper. Current scope of work is to demo the 2010 PP-R piping and reinstall copper piping. New copper piping routes and sizes will be the sane as PP-R piping routes and sizes as shown in attached 2010 construction drawings.
D. Non-PP-R piping such as PEX piping in guest rooms and public rest rooms will remain.
E. Piping hangers and support will meet the following requirements:
1. ASCE 7-10, Minimum Design Loads for Buildings and Other Structures.
2. Hanger spacing installation and attachment to meet all manufacturers requirements and Code requirements.
3. Terminology: As defined in MSS SP-90 "Guidelines on Terminology for Pipe Hangers and Supports".
4. Per SMACNA's requirements.
5. Engineering Responsibility: Design and preparation of Shop Drawings and calculations for each multiple pipe support, trapeze, equipment hangers/supports, and seismic restraint calculations performed by a professional structural engineer.
F. Plumbing work will include the integration of existing recirculation pumps with associated piping and electrical items for a hot water return loop from the West Wing and East Wing attics to the Boiler Room.
G. Project work will also include the demolition and construction of wall and ceiling framing and finishes for removal of the existing piping and installation/concealment of replacement piping.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 10 00. - 2
1.03 BACKGROUND INFORMATION
A. The main Timberline Lodge is a historic structure built in the 1930’s. It is a National Historic Landmark and is included on the National Register of Historic Places. All work in the Lodge has the potential to impact this historic building.
B. A “Programmatic Agreement Among the United States Forest Service, the Advisory Council on Historic Preservation and the Oregon State Historic Preservation Office regarding the Implementation of the Historic Building Preservation Plan for Timberline Lodge” is included.
1. The Programmatic Agreement divided the Main Lodge into 49 spatial zones based on their use, design, and historic integrity. Each zone was assigned one of five preservation strategies, dependent on its historic significance.
1.04 USE OF PREMISES
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site within the buildings to the areas receiving work. Work in each location shall be fully completed before moving to the next location. Do not disturb portions of Project site beyond areas in which the Work is indicated.
C. A staging area will be designated outside of the buildings. Its location will be coordinated with the Government.
D. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Timberline’s employees and guests, and to emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances by construction operations.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Condition of Existing Building: Repair damage caused by construction operations in a way that maintains its historical character.
F. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.05 COORDINATION WITH OCCUPANTS
A. Timberline Lodge will be in full operation during entire construction period. Cooperate with the Government during construction operations to minimize conflicts and facilitate site operations. Perform the Work so as not to interfere with day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Provide a proposed work schedule at the pre-work meeting complete with dates.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 10 00. - 3
Update the schedule as needed and provide a minimum of 2-week notification of any changes.
2. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer.
B. Government Limited Occupancy of Completed Areas of Construction: The Government reserves the right to occupy completed portions of the Work, prior to Substantial Completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Contracting Officer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Government acceptance of the completed Work.
2. Before occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
3. On occupancy, the Government will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.06 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
B. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to occupancy with the Contracting Officer.
1. Notify Contracting Officer not less than two weeks in advance of proposed disruptive operations. Update the Contracting Officer as soon as possible if changes need to be made within that two week window.
2. Obtain Contracting Officer’s written permission before proceeding with disruptive operations.
C. On-Site Work Hours, Utility Interruptions and Noise Restrictions:
1. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the Government or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
i. Notify Contracting Officer not less than two weeks in advance of proposed utility interruptions. Update the Contracting Officer as soon as possible if changes need to be made within that two week window.
ii. Obtain Contracting Officer’s written permission before proceeding with utility interruptions.
D. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
1.07 SPECIFICATION AND DRAWING CONVENTIONS
A. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 10 00. - 4
B. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications.
END OF SECTION
03/03/2023March, 23Timberline Lodge Waterline Emergency Replacement 01 30 00. - 1
ADMINISTRATIVE REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.02 SECTION INCLUDES
A. Preconstruction meeting.
B. Site mobilization meeting.
C. Progress meetings.
D. Construction progress schedule.
E. Submittals for review, information, and project closeout.
F. Submittal procedures.
G. Obtain required permits from regulating agencies.
1.03 PROJECT COORDINATION
A. Cooperate with the Contracting Officer in allocation of mobilization areas of site; for field offices and sheds, for delivery and material access, traffic, and parking facilities.
B. During construction, coordinate use of site and facilities through the Contracting Officer.
C. Comply with Contracting Officer’s procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.
D. Comply with Contracting Officer’s instructions for use of temporary utilities and construction facilities.
E. Coordinate field engineering and layout work under instructions of the Contracting Officer.
F. Make the following types of submittals to the Contracting Officer:
1. Requests for interpretation.
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Manufacturer's instructions and field reports.
6. Applications for payment and change order requests.
7. Progress schedules.
8. Coordination drawings.
9. Closeout submittals.
PART 2 PRODUCTS - NOT USED
03/03/2023March, 23Timberline Lodge Waterline Emergency Replacement 01 30 00. - 2
PART 3 EXECUTION
3.01 PRECONSTRUCTION MEETING
A. Contracting Officer will schedule a meeting after Notice of Award.
B. Attendance Required:
1. Contracting Officer.
2. Contractor.
C. Agenda:
1. Execution of Contract.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.
5. Designation of personnel representing the parties to Contract.
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
7. Scheduling.
3.02 SITE MOBILIZATION MEETING
A. Contracting Officer will schedule a meeting at the Project site prior to Contractor occupancy.
B. Attendance Required:
1. Contractor.
2. Contracting Officer.
3. Contractor's Superintendent.
4. Major Subcontractors.
C. Agenda:
1. Use of premises by Government and Contractor.
2. Government requirements and occupancy prior to completion.
3. Construction facilities and controls.
4. Temporary utilities.
5. Security and housekeeping procedures.
6. Schedules.
7. Application for payment procedures.
8. Procedures for testing.
9. Procedures for maintaining record documents.
10. Requirements for start-up of equipment.
11. Inspection and acceptance of equipment put into service during construction period.
3.03 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. Attendance Required: Job superintendent, major subcontractors and suppliers, Contracting Officer, as appropriate to agenda topics for each meeting.
C. Agenda:
1. Review minutes of previous meetings.
03/03/2023March, 23Timberline Lodge Waterline Emergency Replacement 01 30 00. - 3
2. Review of Work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Maintenance of progress schedule.
7. Corrective measures to regain projected schedules.
8. Planned progress during succeeding work period.
9. Coordination of projected progress.
10. Maintenance of quality and work standards.
11. Effect of proposed changes on progress schedule and coordination.
12. Other business relating to Work.
3.04 CONSTRUCTION PROGRESS SCHEDULE
A. Within 10 days after date of the Award, submit preliminary schedule defining planned operations for the first 60 days of Work, with a general outline for remainder of Work.
B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
1. Include written certification that major contractors have reviewed and accepted proposed schedule.
D. Within 10 days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
3.05 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Shop drawings.
3. Samples for selection.
4. Samples for verification.
B. Submit to Contracting Officer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.
C. Samples will be reviewed only for aesthetic, color, or finish selection.
D. After review distribute in accordance with Section 01 33 00 – SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 70 00 – EXECUTION AND CLOSEOUT REQUIREMENTS.
3.06 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Design data.
2. Certificates.
3. Test reports.
4. Inspection reports.
03/03/2023March, 23Timberline Lodge Waterline Emergency Replacement 01 30 00. - 4
5. Manufacturer's instructions.
6. Manufacturer's field reports.
7. Other types indicated.
3.07 SUBMITTALS FOR PROJECT CLOSEOUT
A. When the following are specified in individual sections, submit them at project closeout:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
B. Submit for Contracting Officer's benefit during and after project completion.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 1
SUBMITTAL PROCEDURES
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
1.02 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Contracting Officer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not re- quire Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.03 ACTION SUBMITTALS
A. Submittal Schedule: Submit a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Contracting Officer and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, schedule of values, and Contractor's construction schedule.
2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal category: Action or information.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Contracting Officer's final release or approval.
g. Scheduled date of fabrication.
h. Scheduled dates for purchasing.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 2
i. Scheduled dates for installation.
j. Activity or event number.
1.04 SUBMITTAL FORMS
A. Contracting Officer's Digital Data Files: Electronic digital data files of the Contract Drawings will be provided by Contracting Officer for Contractor's use in preparing submittals.
1. Contracting Officer will furnish Contractor one set of digital data drawing files of the Contract Drawings for use in preparing Shop Drawings.
a. Contracting Officer makes no representations as to the accuracy or completeness of digital data drawing files.
B. Submittal Information: Include the following information in each submittal:
1. Contract Name and Number.
2. Date.
3. Name of Contracting Officer.
4. Name of Contractor.
5. Name of firm or entity that prepared submittal.
6. Names of subcontractor, manufacturer, and supplier.
7. Category and type of submittal.
8. Submittal purpose and description.
9. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
10. Drawing number and detail references, as appropriate.
11. Indication of full or partial submittal.
12. Consecutive transmittal number.
13. Submittal and transmittal distribution record.
14. Other necessary identification.
15. Remarks.
C. Options: Identify options requiring selection by Contracting Officer.
D. Deviations and Additional Information: On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Contracting Officer on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal. Include the Contracting Officer on all deviation requests.
1.05 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections as PDF electronic files and as indicated for samples and other physical submittals. Types of submittals are indicated in individual Specification Sections.
B. Identify and incorporate information in each electronic submittal file as follows:
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 3
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form acceptable to Government with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS- 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., LNHS- 061000.01.A).
3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by Contracting Officer.
C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
D. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 working days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Con- tractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process intermediate review in same manner as initial submittal.
3. Resubmittal Review: Allow 15 working days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Contracting Officer's consultants, Government, or other parties is indicated, allow 20 working days for initial review of each submittal.
E. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Indicate date and content of previous submittal.
2. Indicate date and content of revision in label or title block and clearly indicate
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 4 extent of revision.
3. Resubmit submittals until they are marked with approval notation on Contracting Officer's action stamp.
F. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
G. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Contracting Officer's action stamp
1.06 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Clearly mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
5. Submit Product Data in PDF electronic file.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale.
Do not base Shop Drawings on standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of Contracting Officer if specified.
2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.
3. Submit Shop Drawings in PDF electronic file.
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 5 these characteristics with other materials and with actual material or component delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
e. Number and title of applicable Specification Section.
f. Specification paragraph number and generic name of each item.
3. Submit Samples as physical samples with paper transmittal and submit in PDF electronic file including transmittal and digital image illustrating Sample characteristics and identification information.
4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Contracting Officer will return submittal with options selected.
D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:
E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact in- formation of Contracting Officers and
F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations.
Number each page of submittal.
G. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Pro- vide original paper copy where a notarized signature is required.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 6
Documents. Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.
H. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
1.07 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 33 00. - 7
Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Contracting Officer.
B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and three paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically as- signed to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
1.08 CONTRACTOR’S REVIEW
A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Contracting Officer.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1.09 CONTRACTING OFFICER’S REVIEW
A. Action Submittals: Contracting Officer will review each submittal, indicate corrections or revisions required, stamp each submittal with an action stamp marked appropriately to indicate action, and return submittal.
B. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will return it if it does not comply with requirements. Contracting Officer will forward each submittal to appropriate party.
C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Contracting Officer.
D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
E. Submittals not required by the Contract Documents may be returned by Contracting Officer with- out action.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 1
HISTORIC TREATMENT PROCESS
SECTION 01 35 91
HISTORIC TREATMENT PROCEDURES
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes special procedures for historic treatment on Projects including, but not limited to, the following:
1. Storage and protection of existing historic materials;
2. Temporary protection of historic materials during construction;
3. Protection during application of chemicals;
4. Protection during use of heat-generating equipment;
5. Historic treatment procedures; and
6. Compliance with Timberline Lodge Historic Building Preservation Plan (HBPP).
1.02 DEFINITIONS
A. “Preservation”: To apply measures necessary to sustain the existing form, integrity, and materials of a historic property. Work may include preliminary measures to protect and stabilize the property.
B. “Rehabilitation”: To make possible a compatible use for a property through repair, alterations, and additions while preserving those portions or features that convey its historical, cultural, or architectural values.
C. “Restoration”: To accurately depict the form, features, and character of a property as it appeared at a particular period of time by means of the removal of features from other periods in its history and the reconstruction of missing features from the restoration period.
D. “Reconstruction”: To reproduce in the exact form and detail a building, structure, or artifact as it appeared at a specific period in time.
E. “Stabilize”: To apply measures designed to re-establish a weather-resistant enclosure and/or the structural reinforcement of an item or portion of the building while maintaining the essential form as it exists at present.
F. “Repair”: To stabilize, consolidate, or conserve; to retain existing materials and features while employing as little new material as possible. Repair includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials. Within restoration, repair also includes limited replacement in-kind, rehabilitation, and construction, with compatible substitutes materials for deteriorated or missing parts so features that where there are surviving prototypes.
G. “Replace”: To duplicate and replace entire features with new material in kind. Replacement includes the following conditions:
1. Duplicate/Replicate: Includes replacing elements damaged beyond repair or missing. Original material is indicated as the pattern from
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 2 creating new duplicated elements.
2. Recreate: Includes replacing missing or severely deteriorated elements based on historic documentation, historic photos, and existing physical evidence.
3. Replacement with New Materials: Includes replacement with new material when original material or evidence is not available as patterns.
4. Replacement with Substitute Materials: Includes replacement with compatible substitute materials. Substitute materials are not allowed, unless otherwise indicated.
H. “Remove”: To detach items from existing construction and legally dispose of them off-site or recycle unless indicated to be salvaged or reinstalled.
I. “Salvage”: To retain, protect, and store removed items for indicated reuse/reinstallation or delivery to Government.
J. “Reinstall”: To repair and clean removed items for reuse, and reinstall them where indicated.
K. “Existing to Remain” or “Retain”: Existing items that are not to be removed during construction. Indicated treatments to be performed in situ if possible.
Contracting Officer to approve removal if deemed necessary.
L. “Material in Kind”: Material that matches existing materials, as much as possible, in material type, species, cut, grain, color and finish.
M. “Protect in Place”: Existing items to remain in their current location with approved adequate protection methods implemented to protect items from surrounding construction and treatments.
N. “Gentlest Means Possible”: To minimize potential negative impacts to historic features by limiting treatment to the minimum effective level required to achieve indicated results.
O. “Prep and Paint”: To remove loose material, corrosion, and/or dirt, prepare surface to receive finish coatings, and reapply coatings as indicated.
1.03 REFERENCES
A. The Secretary of the Interior’s Standards for the Treatment of Historic Properties with Guidelines for Preserving, Rehabilitating, Restoring, and Reconstructing Historic Buildings, National Park Service, U.S. Dept. of the Interior
B. Preservation Briefs, National Park Service Technical Preservation Services, U.S. Dept. of the Interior, http://www.nps.gov/history/hps/tps/briefs/presbhom.htm
C. Preservation Tech Notes, National Park Service, U.S.
Dept. of the Interior, http://www.nps.gov/history/hps/tps/technotes/tnhome.htm
D. Timberline Lodge Historic Building Preservation Plan (HBPP), United States Forest Service, Department of Agriculture (Attached to this Section).
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 3
1.04 SUBMITTALS
A. Historic Treatment Program: Submit a written plan for approval by Contracting Officer of each phase or process including protection of surrounding materials during operations for work conducted in areas designated as Significance A or B in the HBPP. Describe in detail materials, methods, and equipment to be used for each phase of work.
B. Alternative Methods and Materials: If alternative methods and materials to those indicated are proposed for any phase of work, provide a written description including evidence of successful use on other, comparable projects, and program of testing to determine effectiveness for use on the Project.
C. Photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by historic treatment operations. Submit with Historic Treatment Program before work begins .
D. Salvage Log: Catalog removed and salvaged items with identification number, location removed from, orientation if orientation is not obvious, condition, and storage location. Tag items with identification number, using a durable but non-permanent method, prior to storage. Submit record log.
1.05 QUALITY ASSURANCE
A. Historic Treatment Specialist Qualifications: An experienced firm regularly engaged in historic treatments similar in nature, materials, design, and extent to this work as specified in each section, and that has completed a minimum of five recent projects with a record of successful in-service performance that demonstrate the firm's qualifications to perform this work.
1. Field Supervisor Qualifications: Full-time supervisors experienced in historic treatment work similar in nature, material, design, and extent to that indicated for this Project. Supervisors shall be on Project site during times that historic treatment work is in progress. Do not change Supervisors during Project except for causes beyond the control of the specialist firm.
B. Worker Qualification: Persons who are experienced in historic treatment work of types they will be performing.
C. Historic Treatment Specialist Qualifications: A firm that employs personnel, including supervisory personnel, experienced and skilled in the processes and operations indicated.
D. Historic Treatment Pre-construction Conference: Conduct conference at Project site prior to any work. This may be combined with the Pre- Construction Conference.
1.06 PROJECT-SITE CONDITIONS
A. Government will occupy space immediately adjacent to this work. Conduct historic treatment so operations will not be disrupted. Provide immediate
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 4 notice to Contracting Officer of activities that will affect operations.
1.07 STORAGE AND PROTECTION OF HISTORIC MATERIALS
A. Removed Historic Materials identified for Reinstallation:
1. Clean and repair historic items to functional condition adequate for intended reuse.
2. Pack or crate items after cleaning and repairing. Mark and log individual items and identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
B. Historic Materials identified to Remain in Place:
1. Protect construction indicated to remain against damage and soiling during historic treatment.
2. When permitted by Contracting Officer, items may be removed to a suitable, protected storage location during historic treatment and cleaned and reinstalled in their original locations after historic treatment operations are complete.
C. Storage and Protection:
1. When removed from their existing location, store historic materials within a weather tight enclosure where they are protected from wetting by rain, snow, humidity, or ground water, and temperature variations. Secure stored materials to protect from theft.
2. Mark removed items in an inconspicuous location with identification number keyed to salvage log.
PART 2 - PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.01 PROTECTION, GENERAL
A. Comply with manufacturer’s written instructions for precautions and effects of products and procedures on adjacent building materials, components, and vegetation.
B. Temporary Protection of Historic Materials during Construction:
1. Protect existing materials during installation of temporary protections and construction. Do not deface or remove existing materials.
2. Attachments of temporary protection to existing construction shall be approved by Contracting Officer prior to installation.
3.02 PROTECTION DURING APPLICATION OF CHEMICALS
A. Protect persons, motor vehicles, surrounding surfaces of building being restored, building site, plants, and surrounding buildings from harm or damage resulting from applications of chemical cleaners and paint removers.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 5
B. Comply with requirements in Division 1, Section 01 50 00 - Temporary Facilities and Controls.
C. Cover adjacent surfaces with materials that are proven to resist chemical cleaners selected for Project unless chemicals being used will not damage adjacent surfaces. Use covering materials that contain only waterproof, UV-resistant adhesives. Apply masking agents to comply with manufacture’s written instructions. Do not apply liquid masking agent to painted or porous surfaces. When no longer needed, promptly remove masking to prevent adhesive staining.
D. Neutralize and collect alkaline and acid wastes and dispose of off Owner’s property in a legal manner.
3.03 PROTECTION DURING USE OF HEAT-GENERATING EQUIPMENT
A. Comply with the following procedures while performing work with heat-generating equipment, including welding, cutting, soldering, brazing, and other operations where open flames or implements utilizing heat are used:
1. Obtain Contracting Officer’s approval for operations involving use of open-flame or welding equipment.
a. Notification shall be given for each occurrence and location of work with heat- generating equipment.
2. As far as practical, use heat-generating equipment in shop areas or outside the building.
3. Before work with heat-generating equipment commences, furnish personnel to serve as a fire watch (or watches) for location(s) where work is to be performed.
4. Do not perform work with heat-generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. Use a combustible gas indicator test to ensure that the area is safe.
5. Remove and keep the area free of combustibles, including, rubbish, paper, waste, etc., within area of operations.
a. If combustible material cannot be removed, provide fireproof blankets to cover such materials.
6. Where possible, furnish and use baffles of metal or gypsum board to prevent the spraying of sparks or hot slag into surrounding combustible materials.
7. Prevent the extension of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings.
8. Inspect each location of the day’s work not sooner than 30 minutes after completion of operations to detect hidden or smoldering fires and to ensure that proper housekeeping is maintained.
3.04 HISTORIC TREATMENT PROCEDURES
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 6
A. The principal aim of preservation work is to halt the process of deterioration and stabilize the item’s condition, unless otherwise indicated. Repair is required where specifically indicated. The following procedures shall be followed:
1. Retain as much existing material as possible; repair rather than replace.
2. When replacement is required use in kind materials, unless otherwise noted.
3. Use additional material or structure to reinforce, strengthen, prop, tie, and support existing material or structure.
4. Use reversible processes whenever possible.
5. Use traditional replacement materials and techniques, unless otherwise noted. New work shall be distinguishable to the trained eye, on close inspection, from old work.
6. Record the work before the procedure with preconstruction photos and during the work with periodic construction photos.
B. Obtain Contracting Officer’s review and written approval in the form of a Constructive Change Directive or Supplemental Instruction before making changes or additions to construction or removing historic materials.
C. Notify Contracting Officer of visible changes in the integrity of material or components whether due to environmental causes including biological attack, UV degradation, freezing, or thawing; or due to structural defects including cracks, movement, or distortion.
1. Do not proceed with the work in question until directed by Contracting Officer.
D. Where missing features are indicated to be repaired or replaced, provide features whose designs are based on accurate duplications rather than on conjectural designs, subject to the approval of Contracting Officer.
E. Where Work requires existing features to be removed, cleaned, and reused, perform these operations without damage to the material itself, to adjacent materials, or to the substrate.
F. Identify new or replacement materials and features with inconspicuous, permanent marks to distinguish them from original materials. Record the legend of identification marks and the locations of these marks on Record Drawings.
G. When cleaning, match samples of existing materials that have been cleaned and identified for acceptable cleaning levels. Avoid over cleaning to prevent damage to existing materials during cleaning.
03/03/2023 Timberline Lodge Waterline Emergency Replacement 01 35 91. - 7
TIMBERLINE LODGE HISTORIC BUILDING PRESERVATION PLAN EXECUTIVE SUMMARY
The Mt. Hood National Forest is the administrator of Timberline Lodge, a National Historic Landmark. The Forest has utilized the best knowledge and experience available from historians and historical architects as well as technical guidance from the National Park Service, the Oregon State Historic Preservation Office, and the General Services Administration to develop historic preservation strategies for a Historic Building Preservation Plan (HBPP) for the Lodge. The intent of the Forest Service was to create an instrument which documents the structure, but more importantly, is a living document that will provide managers credible alternatives for routine maintenance, rehabilitation, restoration, and replacement of historic fabric throughout the building;
i.e., treatments for all elements making up the structure and the numerous features within it. The HBPP is a document that is useable, practical, and which enables administrators to fulfill historic preservation objectives.
Rather than a static interpretive piece, or a museum, or visitor center, the Lodge is a working hotel.
Hotel managers and Forest Service administrators must be adaptable and prepared to evolve with changing public demands, increasing wear, new codes, and new laws.
PLAN METHODOLOGY
The HBPP has been written in three general phases. Each phase provides the basis for the next. The first phase identifies the historic building and creates an historical frame of reference. The second phase identifies physical zones of the structure and assigns each zone an appropriate preservation strategy. The third phase identifies significant architectural elements within each zone, assigns each element a specific treatment strategy, and provides approved treatment tactics for preservation, maintenance, repair, and replacement.
Phase I
For the first phase the…
This is the start of the file's text. The full file is on GovTribe.