Attachment_C_SHIL_IGE_Cost_Estimate_Form.xlsx

XLSX spreadsheet 40 KB Posted

Attached to
HAFC SHIL EX FABRICATION Federal contract opportunity
Solicitation number
140P2124R0036
Issued by
Department of the Interior National Park Service

About this file

This document appears to be an Independent Government Estimate (IGE) and Cost Estimate Form for a federal contract opportunity related to the fabrication and installation of exhibits for the Shiloh National Military Park. The IGE provides a detailed breakdown of the anticipated costs for various components of the exhibit fabrication and installation, including project management, fabrication drawings, samples, lighting, exhibit structures, custom elements, graphics, conservation, project closeout, shipping, and installation. The key details include a list of the specific exhibit elements, materials and labor required, and estimated costs for each. However, the document does not directly address the overall requirements, response dates, award dates, pricing terms, set asides, or federal agencies involved in the contract opportunity. The information provided appears to be a template or cost estimation tool rather than a comprehensive description of the contract scope and requirements.

View the file

Other files for this federal contract opportunity

Other files attached to HAFC SHIL EX FABRICATION, newest first.
File Type Posted
Sol_140P2124R0036_Amd_0001.pdf PDF
Sol_140P2124R0036.pdf PDF
Attachment_A_Production_Package.pdf PDF
Attachment_D_Past_Performance_Questionnaire.pdf PDF
Attachment_B_Content_Schedules.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gov't Est

SHIL Rehab : Fabrication Independent Government Estimate
Notice to Bidders : This is not a comprehensive list, and reflectives a best line item assessment of the design. The Bidder is responsible to identifying all components required to complete the exhibit production as refered to in the Attachment Documents.
PROJECT MANAGEMENT$0.00
FABRICATION DRAWINGS$0.00
SAMPLES$0.00
Lighting$0.00
EXHIBIT STRUCTURES$0.00
CUSTOM ELEMENTS$0.00
Audio Description Installation$0.00
Audio Description Equipment$0.00
GRAPHICS$0.00
CONSERVATION$0.00
PROJECT CLOSEOUT$0.00
SHIPPING$0.00
INSTALLATION$0.00
TRAVEL$0.00

Grand Total $0 $0.00

PROJECT MANAGEMENT (excluding travel)
LABORhoursxrateamount
Project Manager0hours @$0.00$0.00

TOTAL ALL LABOR $0.00

TOTAL Project Management $0.00

Fabrication Drawings
MATERIALS:qty.unitunit costamount
Hard copies, Proofs and Templates0job$0.00$0.00
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00
TOTAL ALL MATERIALS$0.00
LABORhoursxrateamount
Detailling0hours @$0.00$0.00

TOTAL ALL LABOR $0.00

TOTAL Fabrication Drawings $0.00

Samples/Mock-ups/Prototypes
MATERIALS:qty.unitunit costamount
graphic samples0job$0.00$0.00
graphic samples-color proofs0job$0.00$0.00
custom elements samples0job$0.00$0.00
prototypes0job$0.00$0.00
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00
TOTAL ALL MATERIALS$0.00
LABORhoursxrateamount
exhibit spec-fabrication0hours @$0.00$0.00
TOTAL ALL LABOR$0.00

TOTAL Samples $0.00

Lighting
MATERIALS:qty.unitunit costamount
0LF$0.00$0.00
0ea$0.00$0.00
SUBTOTAL, AV EQUIPMENT$0.00
MARK-UP on materials0percent$0.00
TOTAL ALL MATERIALS$0.00
LABORhoursxrateamount
0hours @$85.00$0.00
TOTAL ALL LABOR$0.00

TOTAL Lighting $0.00

Exhibit Structures
MATERIALS:qty.unitunit costamount
ST-06.02-120 Curved Rail with Graphic1job$0.00$0.00
ST-08.02-120 Curved Rail with Graphic1job$0.00$0.00
CA-11.03-300 Major John Wiley McFerren Case1Job$0.00$0.00
CA-11.03-200 Maj. Francis Eugene Whitfield Case1Job$0.00$0.00
CA-04.03-100 Stibbs Uniform Case1Job$0.00$0.00
CA-04.04-100 Those who were there, Case Temporary Door1Job$0.00$0.00
CA-09.01-100 First Shots Case, Temporary Door1Job$0.00$0.00
CA-11.01-600 Individual Stories Case. Temporary Door1Job$0.00$0.00
CA-11.03-400 Log with Shot case, Temporary Door1Job$0.00$0.00
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00

TOTAL ALL MATERIALS $0.00

LABORhoursxrateamount
shop supervisor0hours @$0.00$0.00
Fab Tech Millwork0hours @$0.00$0.00
TOTAL ALL LABOR0$0.00

TOTAL Exhibit Structures $0.00

Custom Elements
MATERIALS:qty.unitunit costamount
CE-01.02-150 Flat Tactile Orientation Map1job$0.00$0.00
CE-03.01-302 Tactile Bird Print1job$0.00$0.00
CE-03.03-213 Coriinth Element - Tacile Epoxy 3D Casting1job$0.00$0.00
SUBTOTAL MATERIALS$0.00
MARK-UP on materialspercent$0.00
TOTAL ALL MATERIALS$0.00
LABORhoursxrateamount
Fab Tech Modelmaker0hours @$0.00$0.00
TOTAL ALL LABOR$0.00

TOTAL CE $0.00

Electrical/Electronic
MATERIALS - AV EQUIPMENT:qty.unitunit costamount
ADAudio Description0ea$0.00$0.00
Beacons20each0$0.00
Headphone cushion sanitary cover, black, 50 pair1each0$0.00
Headphone cushion sanitary cover, black, Master carton of (12) 50 pair1each0$0.00
Headphones5each0$0.00
Induction neckloop2each0$0.00
iPhone (Minimum Spec capabale Model), 128GB, unlocked sim-free2each0$0.00
Lanyard, 5/8", breakaway, cell phone loop / keyring, dark forest green, NPS text3each0$0.00
Lightning to 3.5 mm Headphone Jack Adapter, 2 pack2each0$0.00
Refresh Kit, replacement cushion and bag5each0$0.00
Ruggedized case for media player3each0$0.00
Sreen Protector for media player3each0$0.00
USB charging station, 6 ports, 6 Apple cables, white1each0$0.00
SUBTOTAL, AV EQUIPMENT$0.00
MARK-UP on materials0percent$0.00
TOTAL ALL MATERIALS$0.00
LABOR (Production)hoursxrateamount
Audio Description, Programing and Installation0$0.00$0.00
TOTAL ALL LABOR (see AV Estimate for Detail)$0.00

TOTAL Electrical/Mechanical/AV $0.00

Graphics
MATERIALS:qty.unitamount
GL-01.03-100 2D Map Panel (Vinyl wrapped sign blank)1ea$0.00$0.00
GL-01.03-200 2D Map Panel (Vinyl wrapped sign blank)1ea$0.00$0.00
GL-01.03-300 2D Map Panel (Vinyl wrapped sign blank)1ea$0.00$0.00
IM-03.04-103 Vinyl wrapped sign blank1ea$0.00$0.00
GL-04.01-100 3M Control tack1ea$0.00$0.00
GL-04.03-100 Vinyl wrapped sign blank1ea$0.00$0.00
GL-04.03-125 Vinyl wrapped sign blank1ea$0.00$0.00
GL-06.02-100 1/16" Phenolic1ea$0.00$0.00
GL-07.01-200 Vinyl wrapped sign blank1ea$0.00$0.00
GL-08.02-100 1/16" Phenolic1ea$0.00$0.00
GL-10.01-100 3M Control Tack/Dreamscape1ea$0.00$0.00
GL-11.01-700 Laminated1ea$0.00$0.00
GL-11.03-100 Vinyl wrapped sign blank double sided, MDF Subsrate1ea$0.00$0.00
GL-11.03-200 Vinyl wrapped sign blank1ea$0.00$0.00
GL-11.03-300 Vinyl wrapped sign blank1ea$0.00$0.00
GL-11.03-325 Vinyl wrapped sign blank1ea$0.00$0.00
GL-11.03-350 Vinyl wrapped sign blank1ea$0.00$0.00
GL-12.01-100 Vinyl wrapped sign blank, kerf core substrate curved wrap1ea$0.00$0.00
GL-13.04-150 Vinyl wrapped sign blank1ea$0.00$0.00
GL-13.05-100 Vinyl1ea$0.00$0.00
0
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00

TOTAL ALL MATERIALS $0.00

LABORhoursxrateamount
Graphic Specialist0hours @$0.00$0.00
Graphic Supervisor0hours @$0.00$0.00

TOTAL ALL LABOR 0 $0.00

TOTAL Graphics $0.00

Conservation (Artifact/Prop Mounting)
MATERIALS:qty.unitunit costamount
AO0403104 Capt. John H. Stibbs' coat1job$0.00$0.00
AO1103206 Whitfield frock coat, seen in the round1job$0.00$0.00
AO1103302 The saddle of Union Major John W. McFerren1job$0.00$0.00
AO1103303 McFerren pistol holsters1job$0.00$0.00
AO1103304 McFerren belt1job$0.00$0.00
AO1103305 McFerren sword1job$0.00$0.00
Pipe
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00
TOTAL ALL MATERIALS$0.00
LABORhoursxrateamount
Mount maker0hours @$0.00$0.00

TOTAL ALL LABOR $0.00

TOTAL Conservation $0.00

PROJECT CLOSEOUT
MATERIALS:qty.unitunit costamount
Digital Media drives and paper printing0$0.00$0.00
SUBTOTAL MATERIALS$0.00
MARK-UP on materials0percent$0.00

TOTAL ALL MATERIALS $0.00

LABORhoursxrateamount
Project Specialist0hours$0.00$0.00
Production Document Manager0hours$0.00$0.00
Project Manager0hours @$0.00$0.00

TOTAL ALL LABOR $0.00

TOTAL Project Closeout $0.00

SHIPPING
MATERIALS:qty.unitunit costamount
00job @$0.00$0.00
00job @$0.00$0.00

TOTAL MATERIALS $0.00

LABORhoursxrateamount
00hours @$0.00$0.00

TOTAL ALL LABOR $0.00

Total Shipping $0.00

INSTALLATION
Project manager
MATERIALS:qty.unitunit costamount
air fare0job @$0.00$0.00
per diem0days @$0.00$0.00
Rental Van and Gas0days @$0.00$0.00
Lodging0days @$0.00$0.00
Total$0.00
LABORhoursxrateamount
Project Manager (1 Person)0hours @$0.00$0.00
Total Travel and Accomodation for: Project Manager$0.00
2 x Fabrication Installers
MATERIALS:qty.unitunit costamount
air fare0job @$0.00$0.00
per diem0days @$0.00$0.00
Lodging0days @$0.00$0.00
$0.00
LABOR
Exhibit Spec - Fabricator0hours @$0.00$0.00
Exhibit Spec - Fabricator0hours @$0.00$0.00
Total$0.00

Total Travel and Accomodation for: Installer $0.00

Lighting
MATERIALS:qty.unitunit costamount
air fare0job @$0.00$0.00
per diem0days @$0.00$0.00
Lodging0days @$0.00$0.00
$0.00
LABOR
Lighting Technician0hours @$0.00$0.00
Lighting Specialist0hours @$0.00$0.00
Ligthing Electrical Specialist0hours @$0.00$0.00
Total$0.00

Total Travel and Accomodation for: Installer $0.00

1 x Exhibit AV integration Specialist
MATERIALS:qty.unitunit costamount
air fare0Each$0.00$0.00
Rental Car and Gas0days@$0.00$0.00
per diem0days @$0.00$0.00
Lodging0days @$0.00$0.00
$0.00
LABOR
AV Technician0hours @$65.00$0.00
Total$0.00

Total Travel and Accomodation for: AV Specialist $0.00

1 x Object Mounter and Installer
MATERIALS:qty.unitunit costamount
air fare0Each$0.00$0.00
Rental Car and gas0days @$0.00$0.00
per diem0days @$0.00$0.00
Lodging0days @$0.00$0.00
$0.00
LABOR
Object Installer and Mount Maker0hours @$0.00$0.00
$0.00

Total Travel and Accomodation for: AV Specialist $0.00

TOTAL ALL MATERIALS: INSTALLATION $0.00

TOTAL ALL LABOR: INSTALLATION $0.00

Total Installation $0.00

TRAVEL
Postaward meeting
MATERIALS:
qty.unitunit costamount
air fare (2 x Round trips)0job @$0.00$0.00
per diem (2 x for 1 days)0days @$0.00$0.00
lodging (2 x for 1 days)0days @$0.00$0.00
Rental car and gas0days @$0.00$0.00
Misc.0job @$0.00$0.00

TOTAL MATERIALS 1 PM $0.00

LABORhoursxrateamount
Project Manager attend meeting (Trip report)0hours @$0.00$0.00
Object Measuring0hours @$0.00$0.00
Object Measuring0hours @$0.00$0.00

TOTAL ALL LABOR $0.00