This is a Quality Assurance Surveillance Plan (QASP) for the 56 Rescue Squadron Functional Check Flight contract (Solicitation #FA5682Q8001) at Aviano Air Base. The QASP establishes procedures for monitoring contractor performance in conducting functional check flights, maintenance test flights, operational check flights, acceptance test profiles, aircraft recovery/delivery, and instructional training.
The surveillance requirements include maintaining qualified personnel present during duty hours 96% of the time (allowing no more than 77 hours of non-coverage annually), responding to flight check requests within one hour of notification, maintaining basic aircraft flight currency and qualifications, and completing 100% of requested sorties. The QASP outlines performance rating definitions from Excellent to Unsatisfactory and includes standard forms for corrective action reports, customer complaints, and performance assessments. The COR is responsible for continuous technical oversight using methods including customer feedback, monthly status reports, higher headquarters inspections, and direct observation. Travel reimbursement invoices must be submitted within 30 days of authorized travel completion.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 - Contract Line Item Number (CLIN) Structure Worksheet.xlsx | XLSX spreadsheet | |
| QA- Functional Check Flight.xlsx | XLSX spreadsheet | |
| Attachment 6 - Contract Line Item Number (CLIN) Structure Worksheet.xlsx | XLSX spreadsheet | |
| Attachment 5 - Special H Clauses.pdf | ||
| Attachment 2 - Addendum to FAR 52.212-1.pdf | ||
| Copy of Attachment 6 - Contract Line Item Number (CLIN) Structure Worksheet.xlsx | XLSX spreadsheet | |
| Attachment 4 - Clauses and Provisions.pdf | ||
| FA568225Q8001 Combined Synopsis Solicitation.pdf | ||
| Attachment 3 - Addendum to FAR 52.212-2.pdf | ||
| Attachment 1 - Performance Work Statement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) for
56 Rescue Squadron
Functional Check Flight
Solicitation #FA5682Q8001
12/20/2024
THIS PAGE IS NOT USED.
Table of Contents
1.0 Purpose
2.0 Authority
3.0 Roles and Responsibilities
4.0 Performance Requirements and Method of Surveillance
4.1 Contract Surveillance
4.2 Surveillance Matrix
5.0 Performance Rating Definitions
6.0 Performance Reporting
6.1 Corrective Action Report (CAR)
6.2 Customer Complaint Record
6.3 Performance Assessment Report (PAR)
7.0 Surveillance Matrix for SIPRNet Engineer Contractor
8.0 Surveillance Matrix for GCCS Administration Contractor
Appendix 1.0 Version Change History
1.0 Purpose
a. This Quality Assurance Surveillance Plan is a government-developed document used to determine if the contractor’s performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the detailed process for a continuous oversight process:
What will be monitored How monitoring will take place Who will conduct the monitoring How monitoring efforts and results will be documented
b. The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QASP provides the structure for the government’s surveillance of the contractor’s performance to assure that it meets contract standards. It is the government’s responsibility to be objective, fair, and consistent in evaluating contractor performance.
c. The QASP is not part of the contract nor is it intended to duplicate the contractor’s quality control plan. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.
d. The government may provide a copy of the QASP to the contractor to facilitate open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor.
e. Bottom line--the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.
2.0 Authority
Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition Regulation, Inspection of Services clauses, which provide for inspection, acceptance and documentation of the service called for in the contract or order. This acceptance is to be executed by the contracting officer or a duly authorized representative.
3.0 Roles and Responsibilities
The following personnel shall oversee and coordinate surveillance activities.
a. Program/Project Manager (PM). The PM provides primary program oversight, nominates the COR, ensures the COR is trained before performing any COR duties and supports the COR’s performance assessment activities. While the PM may serve as a direct conduit to provide Government guidance and feedback to the Contractor on technical matters, they are not empowered to make any contractual commitments or any contract changes on the government’s behalf.
Assigned PM: Major Duvall Brack Organization or Agency: 56 RQS Telephone:632.5603
Email: brack.duvall.1@us.af.mil
b. Contracting Officer (CO). The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Assigned CO:
Organization or Agency:
Telephone:
Email:
c. Contracting Officer’s Representative (COR). The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the CO. The COR is required to provide an annual performance assessment to the CO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government’s behalf.
Primary COR: Capt. Pinzon Shigeta Kenji Organization or Agency: 56RQS Telephone: 632.5649 Email: kenji.pinzon_shigeta.1@us.af.mil
Secondary COR: Lt Col. Rogers Theodore Organization or Agency: 56RQS Telephone: 632.4459 Email: theodore.rogers@us.af.mil
d. Other Key Government Personnel. This may include performance monitors, inspectors, technical experts, or others who provide information that helps the COR monitor contractor performance.
Contract Analyst
Assigned CA:
Organization or Agency:
Contractor Representatives
The following employees of the contractor serve as the contractor’s Program Manager and Task Manager for this contract. (Complete this section after the contract award)
Program Manager: to be named Telephone:
mailto:brack.duvall.1@us.af.mil mailto:kenji.pinzon_shigeta.1@us.af.mil
Other Key Contract Personnel – to be named Title:
4.0 Performance Requirements and Method of Surveillance
4.1 Contract Surveillance
The goal of the QASP is to ensure that contractor performance is effectively monitored and documented. The COR’s contribution is their professional, non-adversarial relationships with the CO, PM, and the contractor, which enables positive, open, and timely communications. The foundation of this relationship is built upon objective, fair, and consistent COR evaluations of contractor performance against contract requirements. The COR uses the methods contained in this QASP to ensure the contractor is following contract requirements. The COR function is responsible for a wide range of surveillance requirements that effectively measure and evaluate the contractor’s performance. Additionally, this QASP is based on the premise that the contractor, not the government, is responsible for management and QC/QA actions to successfully meet the terms of the contract.
4.2 Surveillance Matrix
a. The Surveillance Matrix (Table 7.0) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these performance elements.
Inspection of each element will be documented in the COR file.
b. Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performs surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The Service Summary (SS) should be used to form the foundation of the COR’s inspection checklist.
5.0 Performance Rating Definitions
In evaluating the quality of contractor’s performance, the following performance ratings may be used.
Performance
Rating Criteria
Excellent / Outstanding
Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly effective.
Very Good Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Good Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
6.0 Performance Reporting
The below documents are located on the following pages.
6.1 CORRECTIVE ACTION REPORT (CAR)
Adobe Acrobat Document
6.2 CUSTOMER COMPLAINT RECORD (CCR)
6.3 PERFORMANCE ASSESSMENT REPORT (PAR)
6.1 Corrective Action Report (CAR)
Describes how discrepancies are reported and resolved.
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACTOR 2. CONTRACT NUMBER 3. TYPE OF SERVICES
4. FUNCTIONAL AREA 5. SUSPENSE DATE 6. CONTROL NUMBER
7. DEFICIENCY MAJOR MINOR
FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE
11. COR DETERMINATION
ACCEPTED REJECTED
12. CLOSE DATE
6.2 Customer Complaint Record
CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION BUILDING NUMBER INDIVIDUAL PHONE NUMBER
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
6.3 Performance Assessment Report (PAR)
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACT/TASK ORDER NUMBER 2. CONTRACTOR 3. TYPE OF SERVICES
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE
5. COR PHONE
6. SUSPENSE DATE
I. PERFORMANCE
7. DEFICIENCY (CHECK ALL BOXES THAT APPLY)
NEW
REPEAT
NO DEFICIENCY NOTED
8. SERVICES SUMMARY or PWS PARAGRAPH ITEM REVIEWED
9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY BOX WAS CHECKED) 10. DETAILED PERFORMANCE ASSESSMENT
II. CONTRACTOR VALIDATION
11. CONTRACTOR REPRESENTATIVE CONCUR NON-CONCUR 12. CORRECTIVE ACTION ESTIMATED COMPLETION DATE
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR
CITED DEFICIENCY
III. ACTION CORRECTED
14. CONCUR NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
7.0 Surveillance Matrix for 56 Rescue Squadron Functional Check Flight Contractor
Description of Service PWS Reference Performance Threshold
Methods of Surveillance
Provide fully qualified personnel at each performance location.
Para 1.2 • Fully qualified personnel present during duty hours at each duty location 96% of the time.
• Typical year has 1920 working hour after allowing government holidays; weekends (Sat, Sun); two weeks of vacation. No more than 77 hours of non-coverage is allowed.
• Customer or COR Feedback/Complaints
• Monthly Status Reports
• External or higher-headquarters inspection reports
• Observation by on-site personnel.
Conduct Functional Check Flights, Maintenance Test Flights, Operational Check Flights, Acceptance Test Profiles, Aircraft Recovery/Delivery, and Instructional Training.
Para 2- 2.3 Respond to FCF requests and other flight and training requirements outlined in the PWS to the Flying Operations Supervisor or Productions Supervisor within one hour of notification.
• Customer or COR Feedback/Complaints
• Monthly Status Reports
• External or higher-headquarters inspection reports Observation by on-site personnel.
Maintain Basic aircraft flight currency, ground instruction, and basic functional check flight qualifications.
Para 2.3.1 – 2.3.4 • Customer or COR Feedback/Complaints.
• Monthly Status Reports
• External or higher-headquarters inspection reports
• Observation by on-site personnel.
Able to complete 100% of requested sorties.
Contractor shall submit invoices for reimbursements to the Government upon completion of authorized travel by the Functional Check Flight Contractor.
Para 4.1 - 4.5 • NLT 30 days of completion of authorized travel.
• Monthly Invoices
Appendix 1.0 Version Change History
Section / Page No. Add / Change / Delete
Change No. / Date Explanation
THIS PAGE IS NOT USED.
| 1.0 Purpose |
| 2.0 Authority |
| 3.0 Roles and Responsibilities |
| Contract Analyst |
| Contractor Representatives |
| 4.0 Performance Requirements and Method of Surveillance |
| 4.1 Contract Surveillance |
| 4.2 Surveillance Matrix |
| 5.0 Performance Rating Definitions |
| 6.0 Performance Reporting |
| 6.1 Corrective Action Report (CAR) |
| 6.2 Customer Complaint Record |
| 6.3 Performance Assessment Report (PAR) |
| 7.0 Surveillance Matrix for 56 Rescue Squadron Functional Check Flight Contractor |
| Appendix 1.0 Version Change History |