Attachment 5 Addendum - MOD (signed).pdf

PDF 120 KB Posted

Attached to
Construct and Repair Outfall 9 Culvert at Poorhouse Creek Federal contract opportunity
Solicitation number
FA670320B0002
Issued by
Department of the Air Force Reserve Command

About this file

This addendum to project drawings modifies requirements for a federal contract opportunity to construct and repair an outfall culvert at Dobbins Air Reserve Base in Georgia. The addendum requires inclusion of an additional general construction note on sheet C-100 reminding the contractor to restrict activities to the base property line. It also postpones all work shown in insert "A" of sheet C-400 until further notice from the Contracting Officer and requires contractors to notify the Contracting Officer of any incurred costs from this change. The related federal contract opportunity involves eliminating accumulation of heavy debris at an Anti-Terrorism structure upstream of Outfall Culvert 9 to drain Poorhouse Creek. See attachments one and two for all opportunity requirements. The work is solicited by the Department of the Air Force Reserve Command.

View the file

Other files for this federal contract opportunity

Other files attached to Construct and Repair Outfall 9 Culvert at Poorhouse Creek, newest first.
File Type Posted
Solicitation Amendment FA670320B00020001 SF 30.pdf PDF
PHC Attendance.pdf PDF
Attachment 2 DRAWINGS.pdf PDF
Solicitation - FA670320B0002.pdf PDF
Attachment 3 Wage Determination.pdf PDF
Attachment 4 - Financial Worksheet_Sample.pdf PDF
Attach 6 -DOBBINS DD-1354 Template.pdf PDF
Attachment 1 SPECIFICATIONS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE RESERVE COMMAND

ADDENDUM FOR PROJECT DRAWINGS FOR FGWB 16-0017 POORHOUSE CREEK

FROM: 94 CIVIL ENGINEERING

884 Industrial Drive Dobbins ARB GA 30069-4210

TO: 94 CONF/PK

1538 Atlantic Avenue Dobbins ARB GA 30069

SUBJECT: Required Additional Notes and Retraction of Drawing Detail

1. The following General Construction Note should be included on Sheet C-100:

a. 12. The contractor shall be responsible for restricting construction activities to the

Dobbins ARB property line boundary. Personnel shall not trespass beyond the property line. Equipment and materials shall not to be placed or stored beyond the property line. Provide additional staking, signage, and/or barriers as appropriate for compliance. Notify the contracting officer immediately for compliance violations and potential compliance violations related to constructability.

2. All labor, equipment, materials, and other items required for accomplishment of the work shown on Insert “A” of Sheet C-400 shall be postponed until further notice from the Contracting Officer. Notify the Contracting Officer prior to any incurred costs from the release of this work item.

Devon Mitchell, PE

Civil Engineer Dobbins ARB

2020-07-07T09:00:58-0400
MITCHELL.DEVON.J.1021508566