Attachment 3 Quote Sheet KMRD Vault Pump.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
KMRD Vault Pumping - Ketchikan, AK Federal contract opportunity
Solicitation number
1240BF24Q0001
Issued by
Department of Agriculture Forest Service

About this file

This document is a bid summary sheet for vault pumping services solicitation 1240BF24Q0001 issued by the Department of Agriculture Forest Service. The solicitation requires vault pumping services for pump vaults located on the Ketchikan Tongass National Road system and at Margaret Bay. The base year period of performance is from the date of award through November 2024 with four optional one-year ordering periods through November 2028. Bidders are asked to provide unit prices for tasks including pumping 14 vaults on the road system and one job at Margaret Bay, as well as over and above work. Pricing is also requested for the optional periods. The document includes estimated quantities for restroom, hard floor, and carpet cleaning of various facility types but notes the quantities are estimates and unit prices will not change with quantities ordered. Required facility types include administrative buildings, child development facilities, and physical fitness centers. The solicitation also includes special, emergency, and bio-hazard cleaning line items.

View the file

Other files for this federal contract opportunity

Other files attached to KMRD Vault Pumping - Ketchikan, AK, newest first.
File Type Posted
1240BF24Q0001 KMRD Vault Pumping.pdf PDF
Attachment 1 PWS for KMRD Vault Pumping.pdf PDF
Attachment 2 SCA WD 2015-5685 R20 2023.07.27.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SUMMARY SHEET

ONLY FILL OUT THE YELLOW HIGHLIGHTED CELLS THROUGHOUT THIS QUOTE SHEET
The quanities in this quote sheet are estimates only. The unit prices will not be changed based on the quantities ordered.
KMRD Vault Pumping Services
SOLICITATION: 1240BF24Q0001
Company Name:
Point of Contact (POC):
CAGE Code:
UEI Number:
Address:
Phone:
E-mail:
Fax:
Base Year - Date of Award - 11/30/2024
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
0001Task 1 - Pump Vault on KTN road system14EACH$0.00
0002Task 2 - Pump Vault at Margaret Bay1Job$0.00
0003Over and Above Work1JobTBN

Estimated Total: $0.00

Option Ordering Period 1: 12/1/2024 - 11/30/2025
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
1001Task 1 - Pump Vault on KTN road system14EACH$0.00
1002Task 2 - Pump Vault at Margaret Bay1Job$0.00
1003Over and Above Work1JobTBN
Estimated Total:$0.00
Option Ordering Period 2: 12/1/2025 - 11/30/2026
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
2001Task 1 - Pump Vault on KTN road system14EACH$0.00
2002Task 2 - Pump Vault at Margaret Bay1Job$0.00
2003Over and Above Work1JobTBN
Estimated Total:$0.00
Option Ordering Period 3: 12/1/2026 - 11/30/2027
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
3001Task 1 - Pump Vault on KTN road system14EACH$0.00
3002Task 2 - Pump Vault at Margaret Bay1Job$0.00
3003Over and Above Work1JobTBN
Estimated Total:$0.00
Option Ordering Period 4: 12/1/2027 - 11/30/2028
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
4001Task 1 - Pump Vault on KTN road system14EACH$0.00
4002Task 2 - Pump Vault at Margaret Bay1Job$0.00
4003Over and Above Work1JobTBN
Estimated Total:$0.00
Grand Total:$0.00

Sheet1

BASE YEAR
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0002Category I Administrative Buildings
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0002AACategory I Administrative Buildings Rest Room Cleans2,620,889sq. ft$ 0.0408$ 106,932.25*55,026x47.63= 2,620,888.58 SF (11month period)55026.0041990342522,861,352.22
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ABCategory I Administrative Buildings Hard Floor Cleans6,586,752sq. ft$ 0.0231$ 152,153.97*94,515x47.63= 4,501,749.45 SF138289.986773042527,191,079.31
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ACCategory I Administrative Buildings Carpet Floor Cleans1,204,420sq. ft$ 0.0192$ 23,124.87*19,831x47.63= 944,550.53 SF25287.0098677304521,314,924.51
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.$ 282,211.100520.00
Period of Performance: 11 months (Base Year)0520.00
0520.00
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST520.00
0003Category II Child Development Facilities520.00
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.52
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0003AACategory II Child Development Facilities Hard Floor Cleans11,485,212sq. ft$ 0.0252$ 289,427.35*390,060x238.15weeks = 9,302,139 SFTOTAL: 11,485,212.42 SF
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*7,639x285.78 weeks = 2,183,073 SF
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0003ABCategory II Child Development Facilities Carpet Floor Cleans685,729sq. ft$ 0.0194$ 13,303.14*1113x238.15 weeks = 265,060.95 SFTOTAL: 685,729.11
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*1472x285.78 weeks = 420,668.16 SF
Period of Performance: 11 months (Base Year)$ 302,730.50
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0004Category III Physical Fitness Centers
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0004AACategory III Physical Fitness Centers Hard Floor Cleans3,010,146sq. ft$ 0.0344$ 103,549.02Bldg 3452(6W) 1,330,305.90 SF1W*Hockey 1,323x17.32 = 22,914.36 SF1,330,305.90
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.Bldg 3709 (7W) 1,416,325.68 SF6W*Hockey 1,323x30.31= 240,600.00 SF1,416,325.68
Period of Performance: 11 months (Base Year).22,914.36
QTYUNITUNIT PRICETOTAL COST240,600.00
0004ABCategory III Continuous Cleaning Physical Fitness Center Bldg 370911monthly$ 4,322.26$ 47,544.86Total Hours 1,657.05Provide locker room cleaning from 13:00-15:30 daily 1Male/1Female 2-1/2 hours each.3,010,145.94
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0005Special /Emergency/Bio-Hazard Cleans
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005AASpecial Cleaning40,538per sq. ft$ 0.28$ 11,472.25
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 20% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ABEmergency Cleaning22,296per sq. ft$ 0.38$ 8,405.59
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Emergency Cleaning CLIN represents 11% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ACBio-Hazard Cleaning10,134per sq. ft$ 1.13$ 11,471.69
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 5% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0006CONTRACT MANPOWER REPORTING1EA$ 100.0000$ 100.0000
Contractor Manpower Reporting Costs: 1 May 2016 to 30 March 2017. The Contractor Manpower Reporting requirement is associated with the Office of the Assistant Secretary of the Army (Manpower and Reserve Affairs) requirement to obtain better visibility of the Contractor service workforce.
The Contractor is required to enter data into the Contractor Manpower Reporting Application (CMRA) system as outlined in local information titled Contractor Manpower Reporting located with the clauses incorporated into the contract. Reporting period will be the period of performance not to exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. Data must be accurate and complete and entered into CMRA during the data gathering period of every year, or part of a year, for which the contract is in force. NOTE: If the reporting of Manpower Equivalents is not separately priced, insert “NSP in the blank shown.
BASE YEAR TOTAL COST:$ 767,485.01