Attachment 2 SOW .pdf
PDF 97 KB Posted
- Attached to
- INSTALL BOILER, FORT COLLINS, CO Federal contract opportunity
- Solicitation number
- 12805B20Q0100
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12805B20Q0100_Amd_0002.pdf | ||
| Sol_12805B20Q0100_Amd_0001.pdf | ||
| Sol_12805B20Q0133_Amd_0001.pdf | ||
| Sol_12805B20Q0100.pdf | ||
| Attachment 3 Mechanical drawing boiler room 63.pdf | ||
| Attachment 1 Wage Determination CO20190024.pdf | ||
| Attachment 6 ARS-372.pdf | ||
| Attachment 4 Roof Architectural drawing over boiler room 63.pdf | ||
| Attachment 5 ARS-371.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Connection of Existing Hot Water Boiler #2 at Crops Research Laboratory
Overview: This project is to complete the installation of the Hamilton EVO Boiler at the Crops Research Laboratory located at 1701 Centre Ave, Fort Collins CO 80526. This unit is located in the east Boiler room.
Scope of Work:
All labor and materials to:
1) Remove the existing 2” natural gas service to the two Hamilton heating water boilers and replace with a 3” service inclusive of 3” natural gas regulator, approximately 16’.
2) Rework hydronic piping to HWB #1 & 2 to allow for boiler #2 to be moved approximately 2” north by the installation of two RFSO flanges in each HWS and HWR boiler headers. Pipes may be removed from site to allow for the installation of flanges.
3) Furnish and install 8” CPVC schedule 80 boiler flue to atmosphere for HWB#2.
4) Furnish and install 8” air intake flue for HWB#2 from atmosphere outside of boiler room. Duct material to be in conformance to manufacturer’s specification.
5) Intake and exhaust flues to routed thru existing intake penetration on NW side of roof, work consists of removing existing damper and above roof deck intake ductwork, install new sheet metal covered plywood over penetration.
6) See attached floor plan and roof plan for locations of connections and equipment.
7) Commission boiler and verify operation controls of HWB #1 to HWB#2 and back.
8) Start up Boiler #2 with Boiler #1 manually off.