This document is a Statement of Work (SOW) for a federal contract opportunity to install electrical components and connect a back-up generator to a bunk house at the Planet Ranch Conservation Area (PRCA) in Parker, Arizona.
The key details are: The objective is to acquire contractor services to install a back-up generator, meter panel, breaker panel, automatic transfer switch, and related electrical conduit and wiring at the PRCA bunk house. The work must be completed within 5 days and comply with all applicable federal, state, and local regulations. The government will provide access to the facility, the automatic transfer switch, and steel conduit. Acceptance is contingent on a walk-through by the Contracting Officer's Representative to ensure all work is completed properly and to code. The estimated magnitude of the construction project is between $25,000 and $100,000. A site visit will be held on August 7, 2024 for interested vendors.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_5_-_Main_Single-line_Diagram_0001.pdf | ||
| Attachment_6_-_Questions_and_Answers_0001.pdf | ||
| Attachment_1_-_Revised_Statement_of_Work_with_Track_Changes_0001.pdf | ||
| Sol_140R3024Q0101_Amd_0001.pdf | ||
| Attachment_4_-_Price_Schedule_0001.pdf | ||
| Attachment_7_-_Site_Visit_Sign-In_Sheet_0001.pdf | ||
| Attachment_8_-_Generac_Spec_Sheet_0001.pdf | ||
| Sol_140R3024Q0101.pdf | ||
| 140R3024Q0101.pdf | ||
| Attachment_2_-_Wage_Determination_-_AZ20240029.pdf | ||
| Attachment_3_-_Site_Visit_Maps.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Planet Ranch Conservation Area Back-up Generator Electrical Installation
1. General:
1.1 The objective of this project is to acquire contractor services to install electrical components and connect back-up generator to bunk house (Building 100) at Planet Ranch Conservation Area (PRCA), 3939 Planet Ranch Road, Parker, AZ 85344 (34°14'53.6"N 113°57'05.9"W).
1.2 Purpose/End Application: Planet Ranch Conservation Area (PRCA) is managed by the Lower Colorado River Multi-Species Conservation Program (LCR MSCP). The site is located in a remote area along the Bill Williams River Corridor (see Figure 1). Plans for PRCA involve rearing covered fish species in the four existing refugia ponds. When the ponds are fully operational, personnel will be required to lodge in the bunk houses more consistently to tend to the ponds.
Arizona Public Service (APS) currently provides power to the facilities at the site, but due to concerns about potential power outages, a back-up generator and propane tank have been placed near one of the bunk houses to provide power in case of outages.
Figure 1. Location map of Planet Ranch Conservation Area
1.3 Contractor Qualifications: Licensed Electrician
2. Place of Performance and Period of Performance:
2.1 Work is to be performed at Building 100 of Planet Ranch Conservation Area.
2.2 Period of performance shall be 5 days. The start date is anticipated to be within two months after the contract is awarded. A power outage application must be submitted and approved by APS before work can be completed.
2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Non-duty hours include weeknights, weekends, and Government holidays:
Date Holiday Monday, January 01 New Year’s Day Monday, January 15 Birthday of Martin Luther King, Jr.
Monday, February 19 Washington’s Birthday Monday, May 27 Memorial Day Wednesday, June 19 Juneteenth National Independence Day Thursday, July 04 Independence Day Monday, September 02 Labor Day Monday, October 14 Columbus Day Monday, November 11 Veterans Day Thursday, November 28 Thanksgiving Day Wednesday, December 25 Christmas Day
3. Scope
3.1 The contractor shall complete a walk-through of the site with the COR prior to commencing work to get a thorough understanding of work to be completed.
The Contractor shall furnish and install devices D1A, E1A, and PNL-1 that are shown on the single-line diagram. The Contractor will need to transport laborers and equipment to Planet Ranch Conservation Area to carry out all operations as necessary to accomplish the work. The work shall be performed in accordance with all applicable Federal, State, and local regulations. All work shall comply with codes and standards applicable to each type of work as specified within this contract. The back-up generator system has not been connected to the house, but is currently in place for installation (see Figure 2). There is currently an existing meter panel affixed to the northeastern wall of the bunk house that will be replaced for the back-up generator system (see Figure 3). To complete the installation, a new meter-breaker combo panel, main breaker panel, automatic transfer switch, pull box, and electrical conduit must be connected. Work that has already been completed includes the placement of back-up generator, placement of the propane tank, and trenching of electrical conduit to the bunk house’s wall.
Approximate location of transfer switch and pull box.
Existing SCH80 stub. Connect steel conduit to stub per APS standards.
Meter/breaker panel location.
Figure 2. In-place back-up generator and propane tank
Figure 3. Existing meter and breaker panel on northeastern side of bunk house
The Contractor shall not access any areas other than those necessary to directly reach specific work areas within the Refuge.
The Contractor is solely responsible for the safety and protection of all persons and property at the project site. The Contractor shall strictly comply with all provisions of the Code of Federal Regulations (CFR) 29 CFR 1910 Occupational Safety and Health Standards (OSHA), and 29 CFR 1926 Safety and Health Regulations for Construction.
The Contractor shall, at completion of the project, remove tools and equipment, and leave the premises clean.
If, during construction, public or private property is damaged or destroyed as a result of Contractor’s neglect, the Contractor shall, at their own expense, restore such property to a condition similar or equal to that existing before such damage or injury was done by repairing, rebuilding or replacing it, or otherwise making good such damage or destruction in an acceptable manner.
4. Deliverables
4.1 Quantities shown are approximate and should be verified in the field. All work must be completed per local and APS standards. Component installation must conform to BOR single-line diagram. The contractor shall furnish (if applicable) and install:
Replace existing APS meter panel with “D1A” meter-breaker combo panel.
Replace existing main breaker panel with “PNL-1” main breaker panel.
Install BOR furnished “ATS” automatic transfer switch.
Install “E1A” pull box.
Field verify best location for pull box.
Install approximately 26 feet of BOR furnished steel conduit to the bunk house’s northeastern wall for electrical connection.
Field verify best location and anchoring system for conduit.
Install correct electrical wire and connect entire back-up generator system. Electrical wire will be furnished by BOR.
Be on-site for testing of electrical system during initial start-up of back-up generator.
APS and Ferrell Gas will be present when back-up generator system is initially tested.
All materials furnished by the Contractor shall be new and installed per manufacturer’s recommendations, per applicable local codes and the most recent International Building Code (IBC) and National Electrical Code (NEC). When these work performance criteria, building codes, and application instructions are in conflict, the more stringent requirements shall take precedence.
Existing wiring, switches, and outlet boxes can be reused provided they meet the requirements of the local codes, and NEC.
All demolition and construction debris shall be disposed of according to Federal, State, and local regulations.
4.2 The contractor should provide a written summary of work completed to include details on how improvements meet electrical code.
5. Data Management Plan (DMP) for Science Data Agency Reference. The general criteria is if the contract has a data collection component. Ideally, these requirements are flagged by the different program data stewards. N/A
6. Government-Furnished Equipment (GFE) / Government-Furnished Information (GFI)
6.1 The government will provide access to the facility and will supply the automatic transfer switch and steel conduit.
7. Evaluation and Acceptance
7.1 Government acceptance is contingent upon a walk through by the COR to ensure all aspects of the scope of work and deliverables have been met and are up to code.
8. Quality Control/Quality Assurance:
8.1 Quality Control will be maintained according to industry standards and made available to the agency with the contractor’s proposal.
8.2 A representative of the Government will conduct a walk through to ensure all aspects of the scope of work and deliverables have been met, all electric is functional and safely grounded, and all items are up to code.
9. Points of Contact:
9.1 Aidan Murray
Project Manager and Contracting Officers Representative (COR) Lower Colorado River Multi-Species Conservation Program 500 Date St.
Boulder City, NV 89006 725-277-1914 ammurray@usbr.gov
9.2 Laken Anderson
Restoration Group Manager Lower Colorado River Multi-Species Conservation Program 500 Date St.
Boulder City, NV 89006 725-277-1914 landerson@usbr.gov
9.3 Harris Abellon
Contract Specialist US Bureau of Reclamation PO Box 61470 Boulder City, NV 89006 702-293-8590 habellon@usbr.gov
File details come from the government source that posted it. Updated .