Attachment 1 Statement of Work 25R0001.pdf

PDF 4 MB Posted

Attached to
Boiler Platform Repair Federal contract opportunity
Solicitation number
12505B25R0001
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

This document is a Statement of Work (SOW) for the Boiler House - Boiler #3 Work Platform Improvements project at the National Center for Agricultural Utilization Research (NCAUR) facility operated by the USDA Agricultural Research Service in Peoria, Illinois.

The SOW describes the scope of work to modify the existing work platform on Boiler #3 to comply with OSHA safety guidelines. The project requires the contractor to provide field verification, shop drawings, material procurement, fabrication, delivery, and installation services. The work must be sequenced and scheduled to minimize impacts to the facility's daily operations, as the site has two operational boilers and only one can be taken offline at a time. The contractor must also participate in the NCAUR Temporary Credentialing Program for site access. The contract will be a firm fixed price, with a base bid for the boiler framing plan and an optional bid for an alternate boiler framing plan. The contractor will be required to provide technical experience and past project performance details as part of the evaluation criteria.

View the file

Other files for this federal contract opportunity

Other files attached to Boiler Platform Repair, newest first.
File Type Posted
Attachment 3 Wage Determination IL20240003.pdf PDF
Attachment 2 Sources Sought Response Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Boiler House – Boiler #3 Work Platform Improvements National Center for Agricultural Utilization Research (NCAUR) USDA-ARS, Peoria, IL

DATE: September 17, 2024

Boiler House – Boiler #3 Work Platform Improvements

USDA-ARS, Peoria, IL

TABLE OF CONTENTS

Scope of Work Description

General Requirements:

DIVISION 01 – GENERAL REQUIREMENTS

01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 50 00 Temporary Facilities and Controls 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 23 Operations and Maintenance Data 01 78 39 Project Record Documents

Project Specifications:

DIVISION 09 – FINISHES

09 90 00 Painting & Coatings

NOTE: Additional specifications included with project drawings.

Project Drawings:

NCAUR Shipping/Receiving Improvements bid package as designed by Bailey Edward dated July 11, 2024

Attachments:

NCAUR Temporary Credentialing Program

AD-107 form Material Approval Submittal form

Schedule of Material Submittals Recently Replaced Component Form

Additional Reference Documents:

END OF TABLE OF CONTENTS

Boiler House – Boiler #3 Platform Improvements

SWD-1

Scope of Work Description

SWD-2

Scope of Work Description:

1. Project Location: Boiler House

National Center for Agricultural Utilization Research

USDA-ARS

1815 N. University Street Peoria, IL 61604

2. Point of Contact at Location: Craig Tiezzi

Facility Engineer / EPM (309)-681-6697 Craig.tiezzi@usda.gov

3) Project Background:

a) Boiler #3 has an integrated working platform which provides access to boiler system components that are only accessible from the top side of the unit. The platform system is commonly utilized by maintenance personnel and 3rd party boiler technicians for preventative maintenance and troubleshooting activities. It has been identified this platform does not comply with OSHA guidelines and has been deemed a safety risk.

4) The general requirement of this project shall include:

a) The modification of the working platform on Boiler #3 shall be in accordance with this Statement of Work and the FAR Solicitation and Contract clauses that are identified in the complete Solicitation package. This Statement of Work (SOW) shall consist of this “Scope of Work Description”, Attachments, General Requirements, Project Specifications, and Project Drawings:

i) Contractor will provide all field verification, shop drawings, material procurement, shop fabrication services, delivery, material handling, and field installation services for all platform modifications as identified in the Statement of Work.

b) The repair/replacement shall be performed in a neat, workmanlike manner to provide code-compliant, complete, properly functioning installation.

c) Contractor shall be responsible for all project waste including hauling away, directing waste to recycle, and legally disposing of remaining waste.

d) Demolition / new installation activities shall be sequenced and scheduled to minimize its impact to daily facility operations.

i) Contractor will coordinate with EPM/COR and boiler operation staff prior to the beginning of construction activities to identify a logistics plan for maintaining boiler operation and service delivery during construction.

ii) Any shutdowns of electrical / water /steam distribution at the facility shall be thoroughly coordinated with the Owner and shall occur during time periods acceptable to the Owner.

mailto:Craig.tiezzi@usda.gov

SWD-3

(1) In order to accomplish this requirement, the Contractor shall have new equipment in place and functional to the greatest extent possible; and shall have utility infrastructure installations in place to the greatest extent possible.

(2) The Location has two operational boilers to service the steam and hot water loads for the whole facility. Work activities on Boiler #3 shall be coordinated with the Owner and take place only when the load requirements for the site are suitable for single boiler operation. Boiler #1 will continue to operate under normal conditions to service load requirements and Boiler #3 will be taken offline for work activities to commence.

e) Contractor shall provide all labor, equipment, and materials needed for the indicated replacement. Contractor shall provide a material approval submittal of product data (cut sheets) and shop drawings on materials and components as indicated in the Project Specifications and Schedule of Material Submittals (see Attachments). See Note 10 for additional information.

f) Contractor personnel shall review and participate in the NCAUR Temporary Credentialing Program for security clearance and access to the site. See Attachments for additional information.

5) Contractor(s) are strongly encouraged to visit the site of the proposed work and review the existing conditions there relating to construction and labor, and to be fully informed as to the facilities involved, and the difficulties and restrictions that may affect the performance of the Contract. Failure to visit the site will not disqualify those submitting a proposal. However, change order requests for items that could have been reasonably ascertainable from a site visit (and included in a proposal) will be reviewed by the CO and evaluated accordingly.

6) After project award, the Contractor shall confirm all existing conditions and dimensions prior to proceeding with any project activities; identify all existing conditions that may impact the work; and alert the CO and EPM immediately if conditions are discovered that differ from the SOW. Contractor shall point out discrepancies between work identified in this SOW and actual field-verified conditions--if they exist, prior to performing work.

7) Period of performance shall be as indicated in the Contract Documents and begins after Notice to Proceed is issued by CO.

8) Basis-of-design products are indicated in this SOW to convey a specified standard of quality and salient characteristics desired but are not to be considered a single source specification. Contractor-proposed equals will be considered.

a) The Contractor must compare and validate that quality and salient characteristics are equal and approve the proposed equal products prior to submission for Government review and approval. Additional work required to incorporate Contractor-proposed equals shall be at the Contractor’s expense.

SWD-4

b) Owner will review all Contractor-proposed equal equipment, materials, manufacturers, or installation. It shall be the Contractor’s burden to furnish all documentation and / or samples to show equality with specified items. Owner’s decision on equality is final. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the shop drawing process, not during bidding.

9) Submittals including product data shall be submitted as indicated in the Project

Specifications. See “Schedule of Material Submittals” for required submittals.

Submittals shall be reviewed by the Government for general conformance with the Contract Documents. Markings for comments and approval of the submittals by USDA shall not be construed as releasing the Contractor from compliance with the specified requirements.

a) Use ARS submittal/transmittal form included with this SOW for each submittal.

b) All submittals shall be distributed to and reviewed by the Government prior to commencing work at the site. Purchase of materials prior to submittal approvals are at the Contractor’s risk.

10) See Project Specifications for requirements on construction progress documentation including, but not limited to; daily reports, construction schedule(s), etc.

a) Daily reports documenting construction activities shall include workers present, weather conditions, differing site conditions encountered, etc. Photographs of construction activities and conditions shall be taken daily and shall be submitted with daily reports. Daily reports shall be submitted on daily basis to project personnel as indicated in Project Specifications.

11) The Contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, supervision, *safety equipment, and incidentals for all elements of the work to provide a complete and properly functioning installation in accordance with this Statement of Work. The installation shall be ready for use by Final Completion date.

* Note: Contractor is solely responsible for safety measures and conformance to applicable requirements in accordance with FAR clauses referenced in Solicitation package.

a) Contractor shall provide all means and methods to protect the facility and its installations from all project activities, including protecting the facility from environmental elements as the improvements are completed.

12) Contractor shall coordinate all work activities with the Owner prior to beginning any work. All work shall be scheduled in a manner such that ongoing research is not jeopardized, and facility’s ongoing day-to day operations are not affected negatively, including air quality.

a) Project shall be left broom-clean at the end of each workday.

SWD-5

b) During pre-construction meeting, Contractor shall verify all parking, security, health requirements, laydown, and staging areas with the USDA staff.

13) Applicable Codes and Standards:

a) National Fire Protection Association (NFPA)

i) NFPA 101 – Safety to Life from Fire in Building and Structures

ii) NFPA 1 – Uniform Fire Code

iii) NFPA 5000 – Building Construction and Safety Code

iv) NFPA 72 – National Fire Alarm and Signaling Code

b) Underwriters Laboratories, Inc. (U.L.)

i) Appropriate UL standards

c) State and Local Building Codes as adopted by the Authority Having Jurisdiction

(AHJ)

d) Occupational Safety and Health Administration (OSHA)

e) Equipment Manufacturer Printed Instructions

f) National Electrical Code (NEC) – latest edition in force.

g) National Plumbing Code – latest edition in force

h) Office of Illinois State Fire Marshal

i) Title 41, Chapter 3, Section 2120 as applicable to the work.

14) Project Bid Requirements:

a) Firm fixed price contract:

i) Base Bid – Boiler Framing Plan (see drawings)

ii) Option Bid – Boiler Framing Plan Alternate (see drawings)

b) Proposal Cost Breakdown Requirements for Base Bid:

i) General Conditions

(1) Labor

(2) Material

ii) Division 5 - Metals

(1) Labor

(2) Material

(3) Equipment

iii) Division 9 – Finishes (Paint)

(1) Base Bid:

(a) Labor

(b) Material

(2) Optional Paint Bid:

(a) Labor

(b) Material

iv) Lump Sum Total

c) Proposal Cost Breakdown Requirements for Option Bid:

i) General Conditions

SWD-6

(1) Labor

(2) Material

ii) Division 3 – Concrete

(1) Labor

(2) Material

iii) Division 5 - Metals

(1) Labor

(2) Material

(3) Equipment

iv) Division 9 – Finishes (Paint)

(1) Base Bid (Paint):

(a) Labor

(b) Material

(2) Optional Bid (Paint)

(a) Labor

(b) Material

v) Lump Sum Total

d) Technical Experience

i) Refer to Evaluation Criteria for additional details.

e) Past Project Performance

i) Refer to Evaluation Criteria for additional details.

END OF SCOPE OF WORK

GR-1

General Requirements

01 32 00 - 1 Construction Progress Documentation

01 32 00 – CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1. RELATED DOCUMENTS

a. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

2. SUMMARY

a. Section includes administrative and procedural requirements for documenting the pro-gress of construction during performance of the Work, including the following:

i. Startup construction schedule.

ii. Contractor's construction schedule.

iii. Construction schedule updating reports.

iv. Daily construction reports.

v. Material location reports.

vi. Site condition reports.

vii. Special reports.

b. Related Requirements:

i. Section 013300 "Submittal Procedures" for submitting schedules and reports.

3. DEFINITIONS

a. Activity: A discrete part of a project that can be identified for planning, scheduling, moni-toring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

i. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

ii. Predecessor Activity: An activity that precedes another activity in the network.

iii. Successor Activity: An activity that follows another activity in the network.

b. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

c. Critical Path: The longest connected chain of interdependent activities through the net-work schedule that establishes the minimum overall Project duration and contains no float.

d. Event: The starting or ending point of an activity.

e. Float: The measure of leeway in starting and completing an activity.

i. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

01 32 00 - 2 Construction Progress Documentation

ii. Free float is the amount of time an activity can be delayed without adversely af-fecting the early start of the successor activity.

iii. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

f. Resource Loading: The allocation of manpower and equipment necessary for the com-pletion of an activity as scheduled.

4. INFORMATIONAL SUBMITTALS

a. Format for Submittals: Submit required submittals in the following format:

i. Working electronic copy of schedule file, where indicated.

ii. PDF electronic file.

b. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

c. Construction Schedule Updating Reports: Submit at weekly intervals or as agreed upon with CO/COR.

d. Daily Construction Reports: Submit at daily intervals or as agreed upon with CO/COR.

e. Material Location Reports: Submit as agreed upon with CO/COR.

f. Site Condition Reports: Submit at time of discovery of differing conditions.

g. Special Reports: Submit at time of unusual event.

5. QUALITY ASSURANCE

a. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Owner's request.

6. COORDINATION

a. Coordinate Contractor's construction schedule with the schedule of values, list of subcon-tracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

i. Secure time commitments for performing critical elements of the Work from enti-ties involved.

ii. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

1. CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

a. Time Frame: Extend schedule from date established for the Notice of Award to date of fi-nal completion.

01 32 00 - 3 Construction Progress Documentation

i. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

b. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

i. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by CO/COR.

ii. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as sep-arate activities in schedule. Procurement cycle activities include, but are not lim-ited to, submittals, approvals, purchasing, fabrication, and delivery.

iii. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's construction schedule with submittal schedule.

iv. Startup and Testing Time: Include no fewer than 15 days for startup and testing.

v. Beneficial Occupancy: include date of Beneficial Occupancy.

vi. Substantial Completion: Indicate completion in advance of date established for

Substantial Completion and allow time for CO/COR/EPM administrative proce-dures necessary for certification of Substantial Completion.

vii. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.

c. Constraints: Include constraints and work restrictions indicated in the Contract Docu-ments and as follows in schedule and show how the sequence of the Work is affected.

i. Phasing: Arrange list of activities on schedule by phase.

ii. Work under More Than One Contract: Include a separate activity for each con-tract.

iii. Work by Owner: Include a separate activity for each portion of the Work per-formed by Owner.

iv. Products Ordered in Advance: Include a separate activity for each product includ-ing delivery date(s). Delivery dates indicated stipulate the earliest possible deliv-ery date.

v. Owner-Furnished Products: Include a separate activity for each product including delivery date(s). Delivery dates indicated stipulate the earliest possible delivery date.

vi. Work Restrictions: Show the effect of the following items on the schedule:

1. Coordination with existing construction.

2. Limitations of continued occupancies.

3. Uninterruptible services.

4. Partial occupancy before Substantial Completion.

5. Use of premises restrictions.

6. Provisions for future construction.

7. Seasonal variations.

8. Environmental control.

vii. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:

1. Subcontract awards.

2. Submittals.

3. Purchases.

4. Mockups.

01 32 00 - 4 Construction Progress Documentation

5. Fabrication.

6. Sample testing.

7. Deliveries.

8. Installation.

9. Tests and inspections.

10. Adjusting.

11. Curing.

12. Building flush-out.

13. Startup and placement into final use and operation.

viii. Construction Areas: Identify each major area of construction for each major por-tion of the Work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities to provide for the following:

1. Structural completion.

2. Temporary enclosure and space conditioning.

3. Permanent space enclosure.

4. Completion of mechanical installation.

5. Completion of electrical installation.

6. Substantial Completion.

ix. Other Constraints: NA

d. Milestones: Include milestones indicated in the Contract Documents in schedule, includ-ing, but not limited to, the Notice to Proceed, Substantial Completion, and final comple-tion.

i. Temporary enclosure and space conditioning.

ii. <Insert milestones not indicated elsewhere>.

e. Upcoming Work Summary: Prepare summary report indicating activities scheduled to oc-cur or commence prior to submittal of next schedule update. Summarize the following is-sues:

i. Unresolved issues.

ii. Unanswered Requests for Information.

iii. Rejected or unreturned submittals.

iv. Notations on returned submittals.

v. Pending modifications affecting the Work and Contract Time.

f. Recovery Schedule: When periodic update indicates the Work is 14 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicat-ing means by which Contractor intends to regain compliance with the schedule. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery will be accomplished.

2. STARTUP CONSTRUCTION SCHEDULE

a. Bar-Chart Schedule: Submit startup, horizontal, bar-chart-type construction schedule within ten days of date established for the Notice of Award.

b. Preparation: Indicate each significant construction activity separately. Identify first work-day of each week with a continuous vertical line. Outline significant construction activities

01 32 00 - 5 Construction Progress Documentation for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

3. CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)

a. CPM Schedule: Prepare Contractor's construction schedule using a cost- and resource-loaded, time-scaled CPM network analysis diagram for the Work.

i. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 30 days after date established for the Notice to Proceed.

1. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Architect's approval of the schedule.

ii. Establish procedures for monitoring and updating CPM schedule and for report-ing progress. Coordinate procedures with progress meeting and payment request dates.

iii. Use "one workday" as the unit of time for individual activities. Indicate nonwork-ing days and holidays incorporated into the schedule in order to coordinate with the Contract Time.

b. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work.

Using the startup network diagram, prepare a skeleton network to identify probable criti-cal paths.

i. Activities: Indicate the estimated time duration, sequence requirements, and rela-tionship of each activity in relation to other activities. Include estimated time frames for the following activities:

1. Preparation and processing of submittals.

2. Mobilization and demobilization.

3. Purchase of materials.

4. Delivery.

5. Fabrication.

6. Utility interruptions.

7. Installation.

8. Work by Owner that may affect or be affected by Contractor's activities.

9. Testing

10. Punch list and final completion.

11. Activities occurring following final completion.

ii. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

iii. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

iv. Format: Mark the critical path. Locate the critical path near center of network; lo-cate paths with most float near the edges.

1. Subnetworks on separate sheets are permissible for activities clearly off the critical path.

01 32 00 - 6 Construction Progress Documentation

c. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using a network fragment to demonstrate the effect of the proposed change on the overall project schedule.

4. REPORTS

a. Daily Construction Reports: Prepare a daily construction report recording the following in-formation concerning events at Project site:

i. List of subcontractors at Project site.

ii. List of separate contractors at Project site.

iii. Approximate count of personnel at Project site.

iv. Equipment at Project site.

v. Material deliveries.

vi. High and low temperatures and general weather conditions, including presence of rain or snow.

vii. Accidents.

viii. Meetings and significant decisions.

ix. Unusual events (see special reports).

x. Stoppages, delays, shortages, and losses.

xi. Meter readings and similar recordings.

xii. Emergency procedures.

xiii. Orders and requests of authorities having jurisdiction.

xiv. Change Orders received and implemented.

xv. Construction Change Directives received and implemented.

xvi. Services connected and disconnected.

xvii. Equipment or system tests and startups.

xviii. Partial completions and occupancies.

xix. Substantial Completions authorized.

b. Material Location Reports: At weekly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing ma-terials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site. Indicate the following categories for stored materials:

i. Material stored prior to previous report and remaining in storage.

ii. Material stored prior to previous report and since removed from storage and in-stalled.

iii. Material stored following previous report and remaining in storage.

c. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Re-quest for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

5. SPECIAL REPORTS

a. General: Submit special reports directly to Owner within one day(s) of an occurrence.

Distribute copies of report to parties affected by the occurrence.

b. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether related directly to the Work, prepare and submit a special report.

List chain of events, persons participating, response by Contractor's personnel, evalua-

01 32 00 - 7 Construction Progress Documentation tion of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.

PART 3 - EXECUTION

1. CONTRACTOR'S CONSTRUCTION SCHEDULE

a. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and report-ing using CPM scheduling.

i. In-House Option: Owner may waive the requirement to retain a consultant if Con-tractor employs skilled personnel with experience in CPM scheduling and report-ing techniques. Submit qualifications.

ii. Meetings: Scheduling consultant shall attend all meetings related to Project pro-gress, alleged delays, and time impact.

b. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

i. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

ii. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and ac-tivity durations.

iii. As the Work progresses, indicate final completion percentage for each activity.

c. Distribution: Distribute copies of approved schedule to CO/ACO/COR/EPM, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

i. Post copies in Project meeting rooms and temporary field offices.

ii. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have com-pleted their assigned portion of the Work and are no longer involved in perfor-mance of construction activities.

END OF SECTION 01 32 00

01 33 00 - 1 Submittal Procedures

01 33 00 – SUBMITTAL PROCEDURES

b. See Attachments section of SOW for “Material Approved Submittal” form.

c. See Attachments section of SOW for “Schedule of Materials Submittal” form.

d. See Attachments section of SOW for “Recently Replaced Component” form.

e. See Attachments section of SOW for “AD-107” form.

a. Section includes requirements for the submittal schedule and administrative and proce-dural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

i. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

ii. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

iii. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

a. Action Submittals: Written and graphic information and physical samples that require re-sponsive action. Action submittals are those submittals indicated in individual Specifica-tion Sections as "action submittals."

b. Informational Submittals: Written and graphic information and physical samples that do not require responsive action. Submittals may be rejected for not complying with re-quirements. Informational submittals are those submittals indicated in individual Specifi-cation Sections as "informational submittals."

c. Portable Document Format (PDF): An open standard file format licensed by Adobe Sys-tems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

4. ACTION SUBMITTALS

a. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, man-ufacturing, fabrication, and delivery when establishing dates. Include additional time re-

01 33 00 - 2 Submittal Procedures quired for making corrections or revisions to submittals and additional time for handling and reviewing submittals required by those corrections.

i. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

ii. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early be-cause of long lead time for manufacture or fabrication.

iii. Final Submittal: Submit concurrently with the first complete submittal of Contrac-tor's construction schedule.

1. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

iv. Format: Arrange the following information in a tabular format:

1. Scheduled date for first submittal.

2. Specification Section number and title.

3. Submittal category: Action; informational.

4. Name of subcontractor.

5. Description of the Work covered.

6. Scheduled date for final release or approval.

7. Scheduled date of fabrication.

8. Scheduled dates for purchasing.

9. Scheduled dates for installation.

10. Activity or event number.

5. SUBMITTAL ADMINISTRATIVE REQUIREMENTS

a. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

i. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

ii. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved sub-mittal schedule.

iii. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

iv. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

1. Owner reserves the right to withhold action on a submittal requiring co-ordination with other submittals until related submittals are received.

b. Processing Time: Allow time for submittal review, including time for resubmittals, as fol-lows. Time for review shall commence on receipt of submittal. No extension of the Con-tract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

i. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Owner will advise Contractor when a submittal being processed must be delayed for coordination.

01 33 00 - 3 Submittal Procedures

ii. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

iii. Resubmittal Review: Allow 15 days for review of each resubmittal.

c. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

i. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

ii. Name file with submittal number or other unique identifier, including revision identifier.

iii. Provide means for insertion to permanently record Contractor's review and ap-proval markings and action taken by CO/COR.

iv. Transmittal Form for Electronic Submittals: Use electronic form provided by Owner, containing the following information:

1. Project name.

2. Date.

3. Name and address of Architect/Engineer (if applicable)

4. Name of Construction Manager (if applicable)

5. Name of Contractor.

6. Name of firm or entity that prepared submittal.

7. Names of subcontractor, manufacturer, and supplier.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Specification Section number and title.

11. Specification paragraph number or drawing designation and generic name for each of multiple items.

12. Drawing number and detail references, as appropriate.

13. Location(s) where product is to be installed, as appropriate.

14. Related physical samples submitted directly.

15. Indication of full or partial submittal.

16. Transmittal number, numbered consecutively.

17. Submittal and transmittal distribution record.

18. Other necessary identification.

19. Remarks.

d. Options: Identify options requiring selection by CO/COR/EPM.

e. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

i. Note date and content of previous submittal.

ii. Note date and content of revision in label or title block and clearly indicate extent of revision.

iii. Resubmit submittals until they are marked with approval notation from Architect's action stamp.

f. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppli-ers, fabricators, installers, authorities having jurisdiction, and others as necessary for per-formance of construction activities. Show distribution on transmittal forms.

g. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp.

01 33 00 - 4 Submittal Procedures

1. SUBMITTAL PROCEDURES

a. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specifica-tion Sections.

i. Submit electronic submittals via email as PDF electronic files.

ii. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the submittal / shop drawing process and not prior to bidding. Contractor shall be responsible for submitting information to show equivalence.

Determination by CO/COR on equivalence is final.

iii. Each submittal shall include a completed “Material Approval Submittal” form. See “Attachments” section of the SOW for this form.

b. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

i. If information must be specially prepared for submittal because standard pub-lished data are not suitable for use, submit as Shop Drawings, not as Product Data.

ii. Mark each copy of each submittal to show which products and options are appli-cable.

iii. Include the following information, as applicable:

1. Manufacturer's catalog cuts.

2. Manufacturer's product specifications.

3. Standard color charts.

4. Statement of compliance with specified referenced standards.

5. Testing by recognized testing agency.

6. Application of testing agency labels and seals.

7. Notation of coordination requirements.

8. Availability and delivery time information.

iv. For equipment, include the following in addition to the above, as applicable:

1. Wiring diagrams showing factory-installed wiring.

2. Printed performance curves.

3. Operational range diagrams.

4. Clearances required to other construction, if not indicated on accompa-nying Shop Drawings.

v. Submit Product Data before or concurrent with Samples.

vi. Submit Product Data in the following format:

1. PDF electronic file.

c. Shop Drawings: Prepare Project-specific information, drawn accurately to scale.

i. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

1. Identification of products.

2. Schedules.

01 33 00 - 5 Submittal Procedures

3. Compliance with specified standards.

4. Notation of coordination requirements.

5. Notation of dimensions established by field measurement.

6. Relationship and attachment to adjoining construction clearly indicated.

7. Seal and signature of professional engineer if specified.

ii. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit

Shop Drawings on sheets at least 8-1/2 by 11 inches (215 by 280 mm), but no larger than 30 by 42 inches (750 by 1067 mm).

iii. Submit Shop Drawings in the following format:

1. PDF electronic file.

iv. Include one hard copy of each approved shop drawing in the Operations and Maintenance Manual submitted to the Government during Closeout Procedures.

d. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

i. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

ii. Identification: Attach label on unexposed side of Samples that includes the fol-lowing:

1. Generic description of Sample.

2. Product name and name of manufacturer.

3. Sample source.

4. Number and title of applicable Specification Section.

5. Specification paragraph number and generic name of each item.

iii. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.

iv. Disposition: Maintain sets of approved Samples at Project site, available for qual-ity-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

1. Samples that may be incorporated into the Work are indicated in individ-ual Specification Sections. Such Samples must be in an undamaged condition at time of use.

2. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

v. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

1. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be select-ed from manufacturer's product line. CO/COR will return submittal with options selected.

01 33 00 - 6 Submittal Procedures

vi. Samples for Verification: Submit full-size units or Samples of size indicated, pre-pared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets;

and components used for independent testing and inspection.

1. Number of Samples: Submit three sets of Samples. Architect will retain one Sample sets; remainder will be returned. Mark up and retain one re-turned Sample set as a project record sample.

a. Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

b. If variation in color, pattern, texture, or other characteristic is in-herent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

e. Contractor's Construction Schedule: Comply with requirements specified in Section

013200 "Construction Progress Documentation."

f. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Section 017700 "Closeout Procedures."

g. Maintenance Data: Comply with requirements specified in Section 017823 "Operation and Maintenance Data."

h. Qualification Data: Prepare written information that demonstrates capabilities and experi-ence of firm or person. Include lists of completed projects with project names and ad-dresses, contact information of architects and owners, and other information specified.

i. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Proce-dure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

j. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

k. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certify-ing that manufacturer complies with requirements in the Contract Documents. Include ev-idence of manufacturing experience where required.

l. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

m. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

01 33 00 - 7 Submittal Procedures

n. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

o. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agen-cy, or on comprehensive tests performed by a qualified testing agency.

p. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

i. Name of evaluation organization.

ii. Date of evaluation.

iii. Time period when report is in effect.

iv. Product and manufacturers' names.

v. Description of product.

vi. Test procedures and results.

vii. Limitations of use.

q. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed be-fore installation of product, for compliance with performance requirements in the Contract Documents.

r. Compatibility Test Reports: Submit reports written by a qualified testing agency, on test-ing agency's standard form, indicating and interpreting results of compatibility tests per-formed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

s. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final loca-tion, for compliance with requirements in the Contract Documents.

t. Design Data: Prepare and submit written and graphic information, including, but not lim-ited to, performance and design criteria, list of applicable codes and regulations, and cal-culations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

1. CONTRACTOR'S REVIEW

a. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to

CO/COR/EPM.

b. Project Closeout and Maintenance Material Submittals: See requirements in Section 017700 "Closeout Procedures."

01 33 00 - 8 Submittal Procedures

c. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of re-viewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

2. CO/COR ACTION

a. Action Submittals: CO/COR/EPM will review each submittal, make marks to indicate cor-rections or revisions required, and return it. CO will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

b. Informational Submittals: CO/COR/EPM will review each submittal and will not return it or will return it if it does not comply with requirements. CO/COR/EPM will forward each submittal to appropriate party.

c. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from CO/COR.

d. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

e. Submittals not required by the Contract Documents may be returned by the CO/COR without action.

END OF SECTION 01 33 00

01 50 00 - 1 Temporary Facilities and Controls

01 50 00 – TEMPORARY FACILITIES AND CONTROLS

PART 1 – GENERAL

a. Drawings and general provisions of the Contract, including General and Supplementary Con-ditions and other Division 01 Specification Sections, apply to this Section.

a. Section includes requirements for temporary utilities, support facilities, and security and pro-tection facilities.

3. Related Requirements:

a. Section 015050 – Construction Fencing, Covered Walkways, and Tree Protection

b. Section 017300 – Execution

4. USE CHARGES

a. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary ser-vices and facilities without cost, including, but not limited to, Owner's construction forces, Ar-chitect, occupants of Project, testing agencies, and authorities having jurisdiction.

b. Water and Sewer Service from Existing System: Water from Owner's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

c. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

5. ACTION SUBMITTALS

a. Site Plan (Logistics Plan): Show support facilities, temporary facilities, temporary signage in-cluding sign message, utility hookups, staging areas, and parking areas for construction per-sonnel. Update and submit upon request.

6. INFORMATIONAL SUBMITTALS (As applicable to the Work)

a. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Con-struction General Permit or authorities having jurisdiction, whichever is more stringent.

b. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities hav-ing jurisdiction. Indicate Contractor personnel responsible for management of fire-prevention program.

c. Moisture-Protection Plan: Describe procedures and controls for protecting materials and con-struction from water absorption and damage.

01 50 00 - 2 Temporary Facilities and Controls

i. Describe delivery, handling, and storage provisions for materials subject to water ab-sorption or water damage.

ii. Indicate procedures for discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and replacing water-damaged Work.

iii. Indicate sequencing of work that requires water, such as sprayed fire-resistive mate-rials, plastering, and terrazzo grinding, and describe plans for dealing with water from these operations. Show procedures for verifying that wet construction has dried suffi-ciently to permit installation of finish materials.

d. Dust and HVAC Control Plan: Submit coordination drawing and narrative that indicates the dust and HVAC control measures proposed for use, proposed locations, and proposed time frame for their operation. Identify further options if proposed measures are later determined to be inadequate. Include the following:

i. Locations of dust-control partitions at each phase of work.

ii. HVAC system isolation schematic drawing.

iii. Location of proposed air-filtration system discharge.

iv. Waste handling procedures.

v. Other dust-control measures.

e. Maintenance Records: For each facility, systems or equipment utilized during the construc-tion period, up to the date of Substantial Completion, provide the maintenance records for that facility, system or equipment.

f. Contractor’s Safety Program:

i. Submit Contractor’s Job Safety Program

1. Describe procedures and controls to prevent and/or minimize exposure to potentially hazardous work environments and activities facing Government employees and contractors who maintain our facilities and property.

g. Security Enclosure and…