Attachment_1_SOW_140P8324Q0049.pdf
PDF 210 KB Posted
- Attached to
- Replace Exterior & Screen Doors *WOSB* Federal contract opportunity
- Solicitation number
- 140P8324Q0049
About this file
The document provided is an Attachment 1 - Scope of Work for RFQ 140P8324Q0049 to replace seven exterior doors and screen doors at the Big Hole National Battlefield in Wisdom, Montana. The work includes removing and replacing the existing doors with new wood doors with windows and screen doors that meet current energy efficiency ratings. The contractor will be responsible for all labor, equipment, and materials, as well as any necessary siding or trim replacement, painting, and site restoration. Key requirements include submitting a construction schedule, accident prevention plan, quality control plan, and construction waste management plan within 14 days of contract award. The work must be coordinated to avoid disruption to park staff and operations, and follow restrictions on vehicle use, resource protection, and work hours. The contract will be awarded as a Women-Owned Small Business set-aside.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8324Q0049_Amd_0001.pdf | ||
| Sol_140P8324Q0049.pdf | ||
| Attachment_3_Wage_Determination_MT202.pdf | ||
| Attachment_2_Photos___Drawings_140P8324Q0049.pdf | ||
| Attachment_4_Forms_to_Return_with_Quote_140P8324Q0049.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 140P8324Q0049
Attachment 1 Scope of Work
BIHO – FY24
Replace Exterior & Screen Doors
Big Hole National Battlefield
REPLACE SEVEN EXTERIOR DOORS Page 1
Replace Seven Exterior Doors and Screen Door
Combinations in Park Housing, Building 5
FY24
Scope of Work
Park Housing, Building 5.
Units A, B, C, D
Wisdom, MT 59761
March 2024
NATIONAL PARK SERVICE
GENERAL REQUIREMENTS
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 2
PART 1 – SUMMARY OF WORK & DEFINITION OF CLINs
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. General: All work outlined below will be performed under a single contract.
B. Project Location: This project is located at the Big Hole National Battlefield Housing Area, 16425 Highway 43 W, Wisdom, Montana 59761
1. Project Background: The seven (7) exterior doors are at the Big Hole National Battlefield
Park Housing, Building 5 Units A, B, C, D.
C. Project Scope of Work / Definition of Contract Line Items: The Work consists of the following:
1. Contract Line Item 010: This item shall consist of the removal and replacement of seven exterior doors with similar sized, wood doors with windows and screen doors.
This project includes replacing any damaged siding and all trim and paint associated with the door replacement.
Contractor will provide lump sum pricing for contract line items.
D. Contractor Tasks: The Contractor is to provide all labor, equipment, and materials to remove and replace the old doors.
Work shall include but is not limited to:
1. Contractor shall verify the width and the height of the seven exterior doors and screen doors and have the completed doors on site prior to any removal of the existing doors.
2. All new doors shall meet the most current energy efficiency ratings.
3. Contractor shall supply all required doors complete with all required hardware including but not limited to locks, caulk, weather stripping, etc.
4. Contractor shall be responsible to do all work in accordance with the manufacturer's recommendations, approved plans, specification, and performance standards and in accordance with good building practice, following any/all municipal, state, federal and local laws, and codes.
5. Contractor shall remove and replace doors, taking extreme care to avoid any potential structural damage.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 3
6. Contractor shall level and plumb the frame to avoid any deviation or misalignment of the doors.
7. Any gaps present in the wood frame need to be filled using acceptable methods
(insulation, spray foam insulation, etc.). The finishing shall not have any gaps present around the frames or any part of the complete installation.
8. All the painting works, and any finishing works after the replacement shall be done appropriately in both interior and exterior walls using the appropriate weather shield for exterior and interior.
9. Contractor shall be responsible to maintain cleanliness of the owner's property and clean up, remove, and dispose of all debris associated with their work.
10. Contractor shall be responsible for site restoration and damages due to their work.
Furnishings and equipment not removed during the performance shall be adequately protected.
1.2 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:
1. NPS Forms (RFI, CM-16, and QC Daily Report)
2. Site Location Map with Project Area Limits, Preferred Access, Approved Staging and
Storage Area, and Sensitive Avoidance Areas
1.4 PUBLIC / STAFF USE OF THE SITE
A. General: The project site will be open to the staff during construction but closed to the public. The Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.
B. Other Contracts, Work, and Events: During the contract performance period, there may be other contracts, work, or events occurring in the park or within the project area limits that may affect the Contractor’s operations. The Contractor shall conduct his operations in consideration of these other activities. If the other activities are affecting the critical path of the construction schedule, the Contractor shall document the issue in the daily reports and report the issue to the Contracting Officer.
1.5 CONTRACTOR USE OF SITE
A. Construction Camp or use of park housing: Establishment of a camp or the use of housing within the park will not be permitted.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 4
B. Contractor shall always conduct their operations to ensure the least inconvenience to the Park
Staff. Building closures will not be permitted. Work must be coordinated to permit normal use of the building by park staff throughout the term of the project.
C. Site Access: The building must be open to NPS staff. Maintain access and safety standards for National Park Service maintenance functions throughout the construction phase.
D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until
5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires advance approval from the Contracting Officer.
E. Staging and Storage: Confine the staging and storage of equipment and materials to the maintenance yard located north of the maintenance shop designated by the COR. In some circumstances storage may be provided inside the maintenance shop if materials need to be protected from environmental conditions.
F. The Contractor will be responsible for the security of all equipment and materials at the jobsite.
G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to the Park Facility Manager at the first available opportunity at: 406-689-3155
H. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.
Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
PART 2 – WORK RESTRICTIONS
2.1 WORK RESTRICTIONS
A. General: The Contractor must comply with the following work restrictions:
B. Vehicles / Heavy Equipment:
1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as shown on the Site Location Map or as established at the preconstruction meeting.
Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 5
3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify the
Contracting Officer of spills.
6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
C. Resource Protection:
1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
2. Preservation of Natural Features: Prevent damage to natural surroundings.
a. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no additional expense to the government.
PART 3 – PROJECT MANAGEMENT
3. 1 SUBMITTALS
A. Submittal Documents: The following documents shall be submitted no later than 14 calendar days after contract award and a minimum of seven (7) calendar days prior to the
Preconstruction Meeting. If all of these documents have not been received prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed
(NTP) has been issued.
1. Letter designating the Project Superintendent.
2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final (substantially complete) and final (entirely
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 6 complete) inspection dates, and other major milestones. Provide updates to baseline schedule as needed or as requested (when there is a change to the critical path).
3. Accident Prevention Plan (APP) – Submit a “site specific” accident prevention plan with the following information (at a minimum). Refer also to PART 5 Safety Requirements.
a. Name of the supervisor responsible for executing the plan.
b. Emergency contact phone numbers.
c. Map of local area emergency medical facilities relative to the jobsite.
d. First aid and emergency medical procedures / forms.
e. Company safety plan / protocol.
f. Job hazard analysis (JHA) completed for each major work activity.
g. Job specific COVID-19 plan.
4. Quality Control Plan (QCP) – Submit a “site specific” quality control plan with the following information (at a minimum). Refer also to PART 6 Quality Requirements.
a. Name of the supervisor responsible for executing the plan.
b. Organizational flow chart showing key staff / subcontractors.
c. Qualifications of key staff and subcontractors with applicable licenses / certificates.
d. Communications and reporting plan / procedures / forms (include NPS daily report form, RFI form, and CM-16 form along with Contractor forms).
e. Testing and inspection procedures at all phases of the project (i.e. preparatory, initial, follow-up) to ensure quality, with steps for correction of work / re-work.
5. Construction Waste Management Plan – Submit a construction waste management plan that addresses storage, handling, and disposal of all trash, recyclables, non-hazardous construction waste, and hazardous waste generated from the execution of the work.
Refer also to PART 8 Execution.
6. A list of Subcontractors for this project.
7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
9. Hot Work Plan – Complete and submit a hot work management plan that addresses fire prevention for any work involving open flame or grinding metal.
B. Submittal Documents: The following documents shall be submitted to the Contracting Officer prior to construction mobilization. If these documents have not been received and approved by the NPS prior to construction start, the construction start date may be delayed.
1. Product Data – Submit product cut sheets / material data on all products to be used for approval.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 7
3.2 PRECONSTRUCTION AND PROGRESS MEETINGS
A. Preconstruction Meeting: Before the start of construction, the Contracting Officer will arrange for a preconstruction meeting either on site or via teleconference. The meeting agenda will include the following topics:
1. NPS Roles & Responsibilities
2. Key Contractor Personnel
3. Coordination with Subcontractors
4. Correspondence & Submittal Procedures
5. Submittals
6. Park Rules & Regulations
7. Work Hours and Weekend, Holiday, and Night Work
8. Project Information
a. Jobsite Access & Parking
b. Staging, Storage, and Laydown Area(s)
c. Temporary Facilities & Controls
d. Jobsite Restrictions
e. Resource Protection
f. Reference Documents
h. Other Contracts / Ongoing Work
9. Labor Standards Provisions
10. Labor Interviews
11. Payroll Reports
12. Payments to the Contractor
13. Change Orders / Modifications
14. Progress Meetings
15. QC Daily Reports
16. Inspections
17. Acceptance and Rejection of Work
18. Closeout Procedures & Submittals
19. Contract Period of Performance
20. Notice to Proceed
3.3 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit an RFI utilizing the NPS form.
1. Contracting Officer will only respond to RFIs submitted by the Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, if applicable.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 8
5. Drawing number and detail references, if applicable.
6. Photographs or sketches, if applicable.
7. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state the impact in the RFI.
C. Response to the RFI: The Contracting Officer will review each RFI, determine the action required, and respond accordingly.
PART 4 – SUBMITTAL PROCEDURES
4.1 SUBMITTAL PROCEDURES
A. CM-16 Transmittal Form: All submittals shall be transmitted using NPS CM-16 form sent via email.. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete all applicable fields, sign the form, and attach all supporting documentation.
B. General Submittal Procedures:
1. Processing Time: Allow 7 days for NPS review of a submittal. When review is complete, an e-mail notification will be sent to the Contractor. No extension of contract time will be authorized because of failure to transmit submittals in a timely manner.
2. Approved Equals: For each item proposed as an “approved equal” submit supporting data including:
a. Comparison of the salient characteristics of the proposed item with that specified.
b. Name, address, and telephone number of vendor.
c. Manufacturer’s literature.
d. Compliance with the Buy American Act.
3. Electronic Submittals: Transmit all submittals except physical samples in PDF format.
4. Physical samples: Deliver physical samples to COR (or onsite POC).
PART 5 – SAFETY REQUIREMENTS
1.1 SAFETY REQUIREMENTS
A. General: The Contractor must comply with the following safety requirements:
1. First Aid Equipment: Provide adequate first aid equipment for all contract employees for the hazards associated with the types of ongoing construction work at the site.
2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 9
3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.
4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturers and OSHA recommendations. Maintain MSDS onsite for each chemical used on the jobsite.
Immediately report all spills of hazardous materials to the contracting officer.
5. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a job superintendent or crew leader and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.
6. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.
7. Emergency Medical & Accident Reporting: In the event of an emergency / medical incident, the Contractor shall Dial 911 as needed.
PART 6 – QUALITY REQUIREMENTS
6.1 QUALITY REQUIREMENTS
A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, codes and standards, and the QC Plan.
B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The daily report shall be typed, legible, and complete and include representative photos. The daily report shall be submitted on a daily basis no later than the day after the work. The NPS prefers that the contractor use the NPS daily report form, but an alternate form will be allowed if it contains all major sections of the NPS form.
PART 7 – TEMPORARY FACILITIES & CONTROLS
7.1 TEMPORARY FACILITIES & CONTROLS
A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.
B. Temporary Utilities: The following utilities / services are available for use at the project site:
Electrical Power Service: Electrical power service is available from facilities at the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations.
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 10
Water Service: potable water service is available from facilities at or near the project site for use on the contract without charge.
Sanitary Facilities: Restrooms are available at the site.
Telephone Cellular Service: The project site does have cellular service.
C. Temporary Storage: The Contractor is responsible for ensuring all materials are new and undamaged from weather, age, or neglect.
PART 8 – EXECUTION
8.1 EXECUTION
A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.
B. Preparation: Take field measurements or conduct surveys to verify quantities and dimensions before procurement and fabrication or installation.
C. Utilities: Existing utilities should not be interrupted by this work. In the event of a necessary interruption notify Contracting Officer and utility companies 48 hours in advance of proposed interruption.
D. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repairs to the utility will be at no additional expense to the Government.
E. Cutting & Patching: Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed. Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
F. Installation: Install all components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations. All components shall be complete and operable.
G. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.
H. Progress Cleaning: Clean the project site and work area on a daily basis. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.
I. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.
PART 9 – CLOSEOUT PROCEDURES
9.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
BIHO – FY24
Replace Exterior & Screen Doors
REPLACE SEVEN EXTERIOR DOORS Page 11
A. When the project, or a designated portion of the project, is substantially complete, the Contractor shall request a pre-final inspection in writing at least fourteen (14) calendar days in advance of the inspection date.
B. If the work is determined to be substantially complete at the pre-final inspection, the
Contracting Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final inspection / acceptance. The Contractor shall complete the work described in the Punch List within thirty (30) calendar days, as weather permits. Once all Punch List work is complete, the Contractor shall request a final inspection in writing to arrange for the confirmation of punchlist completion.
C. If the Contractor fails to complete the Punch List work within this timeframe, the Contracting
Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
D. If the work is determined to be not substantially complete at the time of the pre-final inspection, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new pre-final inspection; however, all re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
E. After all deficiencies have been corrected and the project is complete, a Letter of Final Acceptance will be issued by the Contracting Officer.
9.2 CLOSEOUT SUBMITTALS
A. Submit to the Contracting Officer with all applicable operation and maintenance information including but not limited:
1. Product / material cut sheets (all approved products used on the project).
2. Progress photos showing all phases of the work numbered sequentially.
3. Product warranties for individual products and systems.
4. A one (1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.
File details come from the government source that posted it. Updated .