Attachment 1 - PWS AALZ Mowing28 Feb 200.docx
DOCX document 4 MB Posted
- Attached to
- AALZ Forestry Mowing AMENDMENT 7 Federal contract opportunity
- Solicitation number
- FA4460-20-Q-0213
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| questions for AALZ revised and answered 30 Apr 20 (003).DOCX | DOCX document | |
| Camp Robinson AALZ Forestry Mowing.pdf | ||
| Camp Robinson AALZ Forestry Mowing contours.pdf | ||
| AALZ Forestry Combo-Solicitation Amendment 5.docx | DOCX document | |
| AALZ Forestry Combo-Solicitation Amendment 4.docx | DOCX document | |
| AALZ Forestry Combo-Solicitation Amendment 3.docx | DOCX document | |
| AALZ Forestry Combo-Solicitation Amendment 2.docx | DOCX document | |
| Attachment 3 - Surveyed Tree Cutting Map.pdf | ||
| Attachment 3 - Tree Cutting Map.pdf | ||
| Attachment 2 - WD 2015-5117 Rev12.pdf | ||
| Attachment 3 - Tree Cutting Map.pdf | ||
| Attachment 4 - AALZ pictures.pdf | ||
| AALZ Forestry Combo-solicitation.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FORESTRY MOWING, WEST END
ALL AMERICAN LANDING ZONE (AALZ)
CAMP JOSEPH T. ROBINSON
NORTH LITTLE ROCK AR 72199
1. DISCRIPTION OF SERVICES
1.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, materials and services required to remove all trees impacting the approach departure surface on the West end of the airfield at All American Landing Zone (AALZ) TA-07, Camp Joseph T. Robinson, Arkansas 72199. Operations continue with the approach with the minimums raised until a contractor can cut the trees down. At this time there is no mission impact. Contractor shall take prompt action to bring the airfield into compliance UFC 3-260-01, Table 3-7. The contractor shall accomplish all services below to meet the requirements of this Performance Work Statement (PWS). Work shall be in compliance with all Federal, State and local regulations, codes and license requirements. Work shall be accomplished within 120 days of award.
1.2. The requirements official has determined that none of the services to be performed are inherently governmental.
2. SAFETY AND REGULATORY REQUIREMENTS
2.1. General work area is located on Camp Joseph T. Robinson Maneuver Training Center in the middle of TA-07. Work will be primarily on the LL-West End 92d 18’ 47.85w 34d 54’ 51.239N of the AALZ airfield, specifically the clear zone and the approach /departure area. This operation may require the contractor to work on weekends to accomplish the task due to operations. Escort shall be provided by the user (as needed).
2.2. Pre-Install Requirements: Before services are commenced, the contractor shall inspect the work site and ascertain all information for the diligent performance of the service(s). The contractor shall notify the ordering agency of any conditions that prevent the suitable completion of these services to include operations that could endanger Government personnel or property and require appropriate abatement action. If the contractor discovers problems associated with the work after starting, he or she shall immediately notify the Contracting Officer (CO) for their approval if the work is to continue. Coordinate with the Government designated representative to have utilities/fire alarms etc…turned on or off during the competition of the task.
2.3. Disposal of waste: All waste disposal are the responsibility of the Little Rock AFB except hazardous material used by the contractor for their equipment. A portable toilet is available for use at the drop zone. Coordinate through your government representative or COR.
2.4. All work shall be accomplished in accordance with all regulations regarding forestry mowing.
3. WORK REQUIREMENTS
3.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, materials, services and incidentals needed to expeditiously accomplish this work. The project requires a tree mower to remove the vegetation in the areas identified in the approach/departure plane. Specifically, there are approximately 46.2 acres total with an estimated 15.3 acres of penetrating obstructions where trees will have to be removed. See Appendix A. Final stump height will be within 3 inches of the existing elevation.
3.1.1. Blade dozer type equipment that removes vegetation and soil will not be used for this project. Vegetation will be mulched in place and not removed from Camp Joseph T. Robinson or AALZ.
3.2. None of the 46.2 acres on the West end are in wetlands that are regulated by the U.S. Army Corp of the Engineers under Section 404 of the Clean Water Act. See Appendix B for supporting documentation.
3.3. The Contractor shall provide schedule for tracking work progress and estimated completion date. Schedule must be provided within 10 days of contract award for approval by the COR, Camp Robinson Range Operations, and 19 OSS/OSAT.
3.4. 19 CES/CEOSS COR will monitor and approve the effectiveness of the contractor’s performance on any planning and execution under this PWS.
4. GOVERNMENT FURNISHED EQUIPMENT OR SERVICE
4.1. Portable toilet on site. Refuse and recycling containers if needed.
5. GENERAL REQUIREMENTS
5.1. Contractor personnel and vehicles must possess appropriate passes. These shall be obtained from Installation Security Forces Pass and ID at the Vehicle Inspection Center.
5.2. The Contractor is subject to all installation fire, safety, security, and traffic regulations.
5.3. The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
5.4. The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. Enforcement of workplace safety laws is the responsibility of the agency specified in the applicable law.
5.5. The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
5.6. Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the designated representative, must be corrected immediately.
5.7. Contractor Employees: While on the installation, the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the organization or by wearing appropriate badges containing the organization's name and the employee's name. Contractor personnel must wear issued base identification cards at all times while on the installation.
5.8. Service contracts shall require contractor employees to identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with government personnel. In addition, contracts shall require contractor personnel to appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
6.0. WARRANTY
6.1. Contractor shall guarantee all material, workmanship and labor from defects for a period of 12 months from the date of acceptance of the work.
7.0. APPENDIXES
APPENDIX A. LOCATION MAP
APPENDIX B. ENVIRONMENTAL CLEARANCES
a. AHPP Concurrence AALZ Clearing
b. IPAC AALZ Tree Clearing
c. RMTC All American DZ LZ Tree Obstruction Removal – REC
d. UFC 3-260-01 Airfield and Heliport Planning and Design Table 3-7
APPENDIX A. West End of AALZ Runway
APPENDIX B. ENVIRONMENTAL CLEARANCES
a. AHPP Concurrence AALZ Clearing
b. IPAC AALZ Tree Clearing
c. RMTC All American DZ LZ Tree Obstruction Removal – REC
d. UFC 3-260-01 Airfield and Heliport Planning and Design Table 3-7
28 February 2020 image1.emf image2.jpeg image3.jpeg image4.png image5.jpeg image6.jpeg image7.jpeg image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png