This document is a Performance Work Statement (PWS) for a federal contract opportunity to renovate asphalt pavement roadway areas south of Building #1 at the USDA-ARS Northern Great Plains Research Lab in Mandan, ND. The PWS includes a base bid for repairing the existing 20ft x 240ft asphalt roadway, as well as two add alternates to replace additional 20ft x 75ft and 20ft x 150ft sections of the truck route roadway north of Building #1.
The requirements include removing the existing asphalt, repairing the subbase, and installing new 5-inch thick asphalt pavement to match the existing North Dakota mix design. The contractor must also address any drainage issues and provide a smooth transition to the existing roadway. The project should be completed within 365 days after the notice to proceed. Contractors must provide technical and cost proposals for the base bid and add alternates. A site visit is recommended. The related federal contract opportunity has a solicitation number of 12805B24Q0607, a NAICS code of 324121, and a small business size standard of $500K. Quotes are due by August 30, 2024 and the government will award a firm-fixed price purchase order to the responsible offeror whose quote conforms to the specifications and is the most advantageous based on technical acceptance, past performance, and price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ 12805B24Q0607 .08.18.2024.pdf | ||
| Attachment 2 - Service Wage Rates.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
RENOVATE ASPHALT PAVEMENT ROADWAY AREAS SOUTH OF BUILDING 1.
WITH ADD ALTERNATES 1 & 2 BID SEPERATELY PERFORMANCE WORK
STATEMENT
USDA-ARS NORTHERN GREAT PLAINS RESEARCH LAB
1701 10th Ave SW
MANDAN, ND
DATE: June 20, 2024
STATEMENT OF WORK
TABLE OF CONTENTS
1.0 Project Information
2.0 Project Contact Persons
3.0 Scope of Services
4.0 Technical Project Requirements
5.0 Background and Site Description
6.0 Technical Cost Proposal
7.0 Special Requirements
8.0 Performance Schedule
9.0 Government Furnished Equipment
10.0 General Requirements
1.0 Project Information:
A. Project Number: TBD
B. Project Title: Renovate Asphalt Pavement Roadway Areas south of
Building #1. With add alternates.
C. Project Location:
USDA-ARS NORTHERN GREAT PLAINS RESEARCH LAB
1701 10th Ave SW
MANDAN, ND 58554
2.0 Project Contact Persons:
A. ENGINEERING PROJECT MANAGER (EPM):
Mark McWilliams, USDA, ARS, WBSC Phone: 970-631-7513 2150 Avenue, Building D, Suite 300 Fort Collins, CO 80526 Email: mark.mcwilliams@usda.gov
B. RESEARCH PROGRAM REPRESENTATIVES (RPR):
David Archer Phone: 701-667-3048 USDA, ARS, PA, NGPRL Email: David.archer@usda.gov Northern Great Plains Agricultural Research Laboratory 1701 10th Ave SW.
Mandan, ND 58554
C. LOCATION ADMINISTRATIVE OFFICER (LAO):
Jeremy Will Phone: 701-667-3014 USDA, ARS, PA, NGPRL Email: Jeremy.Will@usda.gov Northern Great Plains Agricultural Research Laboratory
D. LOCATION MONITOR (LM):
Mike Eberle Phone:701-667-3075 USDA, ARS, PA, NGPRL Email: Michael.Eberle@usda.gov Northern Great Plains Research Laboratory
E. COLLATERAL DUTY SAFETY OFFICER (CDSO):
Holly Johnson Phone:701-667-3003 USDA, ARS, PA, NGPRL Email: Holly.Johnson@usda.gov Northern Great Plains Agricultural Research Laboratory
3.0 Scope of Services:
The Contractor shall provide all professional services necessary for the accomplishment of each project and such required services shall be in accordance with requirements as described herein.
A. The Contractor shall provide services for the following tasks marked by an
“X”:
[X] Provide a cost proposal and a technical proposal to complete the project as per project requirements.
[X] The contractor shall furnish all the skilled labor, materials, equipment, tools, transportation, and supervision necessary to remove old asphalt, fix the subbase, and resurface the asphalt areas as shown in these documents.
4.0 Technical Project Requirements:
The Contractor will work with site personnel to ensure each task is accomplished in a timely manner.
A. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
B. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.
5.0 Background & Site Description:
A. Existing pavement and Driveway area is approximately 20ft x 240ft. as shown in Roadway Areas south of Bldg.#1.JPG
6.0 Technical Cost Proposal: Provide cost proposals for the Base Bid, Add Alternates 1 and 2 for this contract as shown in file “Roadway Areas South of Bldg. #1.jpg and Truck route roadway pavement”.
7.0 A Site visit is recommended: Contact Mike Eberle @ 701-527-1524 or Scott Jensen @ 701-805-1222.
8.0 Specific Requirements
A. Asphalt Improvements- Base Bid
1. Existing asphalt, 20ft. x 240ft. shall be saw cut straight in at both ends and by drive area shown. All the pavement in the repair area must be removed so that the subbase can be repaired.
2. Existing subbase shall be filled and compacted to create a new stable subbase. Industry standards must be followed to fill, repair, and compact subbase for new asphalt roadway.
3. New surface roadway must be a minimum of 5” thick course asphalt and must meet the pavement overlay mixture as the “State of North Dakota mix design”.
4. Any Drainage issues and any fill-in patch work must be discussed with the Location Monitor before the work is completed. Drainage off roadway is required.
5. Milling into existing roadways sections if needed must be completed to provide a smooth and level transition between the existing pavement and new pavement work.
6. Any materials removed must be hauled off site. Any materials needed for fill must be provided by the contractor. The contractor is responsible for any utility locates if needed.
7. Contractor is responsible to backfill and grade ditch areas back to original condition as to the satisfaction of COR. Any materials needed to fill or grass seed areas must be provided and applied by the Contractor.
B. ADD Alternate 1 and 2 – Truck Route Asphalt Area removal and replacement of pavement.
1. Add Alternate 1: is approximately 20ft. x 75ft roadway area north of
Bldg. #1 on the truck route road. All the pavement in the repair area must be removed totally to the subbase.
2. The removal area must be saw cut to provide a clean transition.
3. The subbase must be repaired, filled, and compacted to industry standards.
4. New pavement must be a State of North Dakota mix design that is a minimum of 5” thick and paved for drainage off the roadway.
5. Any milling required must be completed to ensure a smooth transition for new pavement to meet the existing pavement.
6. Any materials removed must be hauled off site. Any materials needed for fill must be provided by the contractor.
7. Contractor is responsible to backfill and grade ditch areas back to original condition as to the satisfaction of COR. Any materials needed
8. Add Alternate 2: is approximately 20ft. x 150ft. roadway area north of Bldg.#1 on the truck route road. All the pavement in the repair area must be removed totally to the subbase.
9. The removal area must be saw cut to provide a clean transition.
10. The subbase must be repaired, filled, and compacted to industry standards.
11. New pavement must be a State of North Dakota mix design that is a minimum of 5” thick and paved for drainage off the roadway.
12. Any milling required must be completed to ensure a smooth transition for new pavement to meet the existing pavement.
13. Any materials removed must be hauled off site. Any materials needed for fill must be provided by the contractor.
14. Contractor is responsible to backfill and grade ditch areas back to original condition as to the satisfaction of COR. Any materials needed
9.0 Performance Schedule: When weather is appropriate, project should be completed 365 days after the Notice to Proceed or sooner.
10.0 Government Furnished Equipment\Services
A. None provided.
11.0 General Requirements:
A. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Design Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of construction permits, licenses, inspections, etc., are the obligation of the future Construction Contractor.
B. Schedules shall be updated and furnished with each submittal.
C. Submittals shall be made as scheduled in the Special Requirements section. Each submittal shall be distributed electronically in Adobe for review, to the Location Monitor at the facility, Engineering Project Manager, and Contracting Officer. Each submittal shall contain the previous submittal's Excel comment sheet with responses, notes of meetings held with ARS personnel, design notes, calculations, and construction progress bi-weekly meetings during construction.
D. Changes in the scope of work or the task order that affect the level of effort of the Contractor have to be pre-approved by the CO.
E. Disputes or questions that arise after the task order has been negotiated will be resolved by the CO.
Base Bid Area
Add Alternates 1 and 2