Attachment 02 Contract Specifications Package.pdf
PDF 6 MB Posted
- Attached to
- 127EAS21Q0065 Forest Wide Building Demolition Project Federal contract opportunity
- Solicitation number
- 127EAS21Q0065
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF 30 Amendment 02.pdf | ||
| Amendment 02 Response and Pic.pdf | ||
| BlackRockSta_FS1105_AsbestosInspection.pdf | ||
| SF 30 Amendment 01.pdf | ||
| BattersonWC_FS2617_AsbestosInspection.pdf | ||
| 127EAS21Q0065 Forest Wide Building Demolition Project.pdf | ||
| Attachment 03 Pictures of Building to be Demolished.pdf | ||
| Attachment 01 Schedule of Items.pdf | ||
| Attachment 06 Evaluation Questionnaire.pdf | ||
| Attachment 04 Wage Determination.pdf | ||
| Attachment 05 Fire Plan 2013 (003).pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECS INDEX FORESTWIDE DEMOLITION PROJECT
Division 1 - General Requirements Page No.
SECTION 01010 - Summary of Work 2 SECTION 01040 - Coordination 5 SECTION 01060 - Regulatory Requirements 7 SECTION 01070 - Abbreviation and Symbol 9 SECTION 01315 - Schedules and Reports 11 SECTION 01442 - Quality Control & Quantity Measurement 12 SECTION 01501 - Building Demolition 13 SECTION 01505 - Mobilization 14 SECTION 01505 - Material Sources 15 SECTION 01711 - Cleanup and Disposal 16
Division 2 -Site Work
SECTION 02100 - Clearing and Demolition 18
Miscellaneous
Buildings Demolition List 21
Project Map Location 23
Project Site Locations and Directions 24
Forestwide Buildings Demolition Project Sierra National Forest
SECTION 01010
SUMMARY OF WORK
PART 1 GENERAL
1.01 SCOPE
This project consists of the demolition of 23 structures in the Forest wide Building Demolition Project located within the Sierra National Forest at both Bass Lake and High Sierra Ranger Districts; see list below for building sizes and locations of the buildings. The work consists of conducting hazmat surveys for lead base paint and asbestos as necessary of the 23 structures PRIOR to demolition; removal and abatement of all hazmat if found prior to structure demolition, and demolition and cleanup of 23 structures identified in this contract.
The contractor shall furnish all labor, materials, equipment, supervision, sampling, transportation as necessary to:
• Conduct hazmat surveys to identify all hazmat associated with 23 demolition structures PRIOR to demolition. If hazmat is found:
o Properly remove and dispose all hazmat of prior to demolition of the structures in accordance with all Federal, State, and local laws and regulations. EPA IDs for USDA Sierra National Forest are as follow:
CAL000453789 Bass Lake Ranger District, 57003 Road 225, North Fork, CA 93643.
CAL000022964 High Sierra Ranger District, 29688 Auberry Road, Prather, CA 93651.
• Site Cleanup: Complete total removal, disposal, and site cleanup of all 23 structures identified in this CONTRACT with associated destroyed structures not listed in the buildings list, that includes ALL items STORED INSIDE the buildings and ALL materials related to each structure above the ground surface such as utilities, plumbing, and any concrete slab foundation as necessary.
• Abate and dispose of identified hazardous materials (asbestos, flaking lead-based paint, soil contamination, and/or universal waste) in structures in accordance with all Federal, State, and local laws and regulations.
• Excavation, minor clearing, along with removal of concrete slab, above ground utility hardware for electrical, water and sewer is included in this demolition operation.
Backfill holes and grading back to natural condition.
Forestwide Buildings Demolition Project Sierra National Forest https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000453789&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=4idB07NR2oWGHiuDDGxJXC%2BvBBNlv5d%2BihDXc7hKf80%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000022964&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=xSRcABgehjXbHcz7zIpitq%2FGfmqQw6pRhgOivGWAqzE%3D&reserved=0
• Ground plumbing and utilities to be stubbed 2-feet below ground and capped.
Underground and overhead utility service may be existing at the site. All materials and debris designated by the Government shall be removed from the sites, unless identified for salvage as Government property. Close all septic systems if necessary.
Closure must be completed in accordance with all Federal, State, and local laws and regulations.
All work is to be performed in accordance with Federal, State, and local laws, regulations, and ordinances. Any work that is outside of this contract scope must be approved the Forest Service Contracting Officer before the work can be initiated.
1.02 CONTRACTOR USE OF PREMISES
A. Material storage and equipment will be confined to approved marshalling areas.
Marshalling area will be identified by the CONTRACTING OFFICER. When not in use, equipment shall be stored in a marshalling area or approved sites. During the construction period the Contractor’s use of the premises is limited to storage of equipment and materials. No overnight camping by the Contractor’s personnel will be allowed.
B. Sanitation: Sanitation facilities are to be provided by contractor
C. IF water source is available within the project area, use of it shall be approved by the
CONTRACTING OFFICER.
D. While performing the work the Contractor shall take reasonable precauctions to protect adjacent properties from damage. The Contractor at no additional cost to the Government shall restore any damage or injury caused by the Contractor in the course of this work.
1.03 TRAFFIC
A. Traffic Control: Warning devices, barricades and traffic control signing shall be maintained in the construction area at all times, and shall be in conformance with the Manual on Uniform Traffic Control Devices. The roads shall be made passable to emergency traffic immediately.
B. Traffic Safety: Safety precautions shall be in accordance with all local, State and Federal regulations.
C. Hauling Restrictions: The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads within and outside of the limits of the project.
A special permit will not relieve the Contractor of liability for damage which may result from the moving of equipment or materials.
D. Traffic Speed: The traffic speeds within the project area shall be maintained to conform with the roadway conditions, the maximum safe speed shall be what the road and surface conditions will allow and shall not exceed 15 MPH. These speed limits
Forestwide Buildings Demolition Project shall be strictly adhered to by the Contractor under this contract. Dust abatement and control shall be maintained according to regulations and codes.
E. Administrative and Emergency Traffic: The Contractor shall keep the project area open for administrative and emergency traffic at all times.
F. Equipment Cleaning: All off-road equipment shall be free of noxious weeds, soil, seeds, vegetative matter, or other debris that could contain or hold seeds. The Contractor shall certify in writing that all off-road equipment is free of noxious weeds prior to commencing operations on the project sites. Contractor shall employ whatever cleaning methods that are necessary to ensure that all off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds and other such debris when visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required. Contractor shall at least 5 working days prior to moving each piece of equipment onto the project site, identify the location of the equipment’s most recent operation.
1.04 MAINTAINING UTILITY SERVICE
A. The existing utilities (underground or overhead) have not been identified within the project areas, but this shall not relieve the Contractor from taking preventive measures and being responsible for protecting any utilities that may be encountered during construction operations. The contractor shall be responsible for any repairs to these utilities if damaged during construction operations.
The Contractor shall notify the CONTRACTING OFFICER immediately if any utilities are damaged and need repair
1.05 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this section
1.06 CLOSURES
The project area will be OPEN to all Forest Service Employees, except within the proximity of active Construction operations.
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01040
COORDINATION
PART 1 GENERAL
1.01 SCOPE:
This section identifies Contractor and Government responsibilities for coordinating CONTRACT work with other governmental entities, utility companies, adjacent land users and other contractors.
1.02 RELATED SECTIONS:
General Provisions FAR 52.236-7, Permits and Responsibilities.
General Provisions FAR 52.236-8, Other Contracts.
General Provisions FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
General Provisions FAR 52.236-10, Operations and Storage Areas.
General Provisions FAR 52.236-19, Organization and Direction of the Work.
1.03 GOVERNMENT (FOREST SERVICE) RESPONSIBILITIES:
(a) Notify entities involved of approximate dates of construction under this contract to facilitate initial coordination.
1.04 CONTRACTOR RESPONSIBILITIES:
(a) Submit Work Progress Schedule (see FAR 52.236-15).
(b) Arrange for and bear the cost of temporary utilities and services from public utilities if desired
(c) Obtain and pay for minor, temporary permits and services necessary for construction activities.
(d) Coordinate with public utility companies for protection of existing utilities, including requesting "Blue Stake" location service in advance of any ground-disturbing activities.
(e) Coordinate with utility companies for permanent connection of services constructed under this contract.
(f) Coordinate access and construction activities under this contract with any other contractors working adjacent to the project site.
Forestwide Buildings Demolition Project
(g) Coordinate with Forest Service at the project site during construction activities which disrupt access at the site.
(h) Notify CONTRACTING OFFICER and Forest Service personnel at site 24 hours in advance of any utility interruption to the site.
Additional coordination if needed, shall be brought to the attention of the
CONTRACTING OFFICER.
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01060
REGULATORY REQUIREMENTS
PART 1 GENERAL
1.01 SCOPE
This Section describes the Regulatory Requirements and the Codes and Standards that apply to the work in this contract.
1.02 REGULATORY REQUIREMENTS
A. All laws, ordinances, codes, and regulations of the United States Government shall apply and be implemented into this contract.
B. The following codes and standards shall apply to the work in this CONTRACT.
Where no date is specified, the applicable edition shall be the one in effect on the date of solicitation.
1. American Society for Testing Materials (ASTM).
2. American Water Works Association Standards.
3. Forest Service Handbook 6709.11 health and Safety Code Handbook.
4. Manual on Uniform Traffic Control Devices.
5. Manufacturer's Instructions.
6. National Sanitation Foundation.
7. State of California Construction Safety Orders.
8. Underwriters' Laboratories (UL).
1.03 CODES AND STANDARDS:
Standards and practices set forth by the references mentioned elsewhere in these specifications shall be adhered to unless otherwise noted.
1.04 DUTIES OF THE CONTRACTOR
A. Responsibilities: It is the duty of the Contractor to complete the work covered by this contract in accordance with the approved plans and specifications therefore.
B. Performance of the work: The Contractor shall study carefully the specifications and shall plan their schedule of operations well ahead of time. If at any time it is discovered that work is being done which is not in accordance with the specifications, the Contractor shall correct the work immediately. All inconsistencies or items which appear to be in error in the contract documents shall be promptly called to the attention of the CONTRACTING OFFICER. Local conditions which may affect the scope of this contract shall likewise be brought to the attention of the CONTRACTING OFFICER at once. In no case, however, shall the instruction of the CONTRACTING OFFICER be construed to cause work to be done which is not in conformity with the specifications. The Contractor shall not carry on work except with the knowledge of the CONTRACTING OFFICER. Subcontractors
Forestwide Buildings Demolition Project engaged to do work on the project must be approved by the CONTRACTING
OFFICER.
1.05 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section. See Section 01315.
PART 2 PRODUCTS
2.01 PRODUCTS AND MATERIALS:
All products and materials used in this CONTRACT shall meet the standards and requirements of the codes and standards referenced in Part 1 - General of this Section, and elsewhere herein unless otherwise SHOWN ON THE DRAWINGS, the more stringent requirements shall take precedence over the codes and standards.
All materials, unless specified otherwise, shall be handled, stored, installed, and maintained in accordance with the manufacturer's instructions and recommendations.
PART 3 EXECUTION
3.01 WORK REQUIREMENTS:
All work in the contract shall meet the standards and requirements of the codes and standards referenced in Part 1 - General of this Section and elsewhere herein or as written in the specifications. When more stringent requirements are called out in these specifications, the more stringent requirements shall take precedence over the codes and standards. All work shall be performed in a workman-like manner according to the best practices of the trade and the best standards of the industry.
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01070
ABBREVIATIONS AND SYMBOLS
PART 1 GENERAL
1.01 SCOPE
A. This section decribes and lists some of the abbreviations and symbols used in these specifications. All or none of these abbreviations or symbols may be applicable to this
CONTRACT.
1.02 MEASUREMENT AND PAYMENT
Not applicable.
PART 2 PRODUCTS
Not Applicable.
PART 3 EXECUTION
3.01 REFERENCE
To a technical society, institution, association, standard, code, governing authority or other abbreviations or symbols made in the specifications are in accordance with the following:
AA Aluminum Association.
AAMA Architectural Aluminum Manufacturers Association.
AASHTO American Association of State Highway and Transportation Officials.
ACI American Concrete Institute.
AFI Air Filter Institute.
AGA American Gas Association.
AGC Associated General Contractors of America.
AGMA American Gear Manufacturers Association.
AIA American Institute of Architects.
AIA American Insurance Association (Formerly NBFU).
AIEE American Institute of Electrical Engineers.
AISC American Institute of Steel Construction.
AISI American Iron and Steel Institute.
ALS American Lumber Standards.
AMA Acoustical Materials Association.
AMCA Air Moving and Conditioning Association.
ANSI American National Standards Institute (Formerly USAS).
APA American Plywood Association.
ARI Air Conditioning and Refrigeration Institute.
ASHRAE American Society of Heating, Refrigerating, and Air Conditioning
Engineers.
ASME American Society of Mechanical Engineers.
ASTM American Society for Testing and Materials.
AWI Architectural Woodwork Institute.
AWPA American Wood Preservers' Association.
AWPI American Wood Preservers' Institute.
Forestwide Buildings Demolition Project
AWS American Welding Society.
AWWA American Water Works Association.
CABRA Copper and Brass Research Association.
CS Commercial Standard, U.S. Department of Commerce.
CSI Construction Specification Institute.
FGJA Flat Glass Jobbers Association.
FIA Factory Insurance Association.
FM Factory Mutual.
FS Federal Specification.
GA Gypsum Association.
IEEE Institute of Electric and Electronic Engineers.
IES Illuminating Engineering Society.
MIA Marble Institute of America.
MLMA Metal Lath Manufacturers Association.
MS Military Specification.
MSTD Military Standard.
NAAMM National Association of Architectural Metal Manufacturers.
NAFM National Association of Fan Manufacturers.
NBFU National Board of Fire Underwriters (currently American Insurance
Association).
NBS National Bureau of Standards.
NEC National Electric Code.
NEMA National Electrical Manufacturers Association.
NEPA National Electrical Protection Association.
NFC National Fire Code.
NFPA National Fire Protection Association.
NHLA National Hardwood Lumber Association.
NLMA National Lumber Manufacturers Association.
NTMA National Terrazzo and Mosaic Association.
NWMA National Woodwork Manufacturers Association.
OSHA Occupational Safety and Health Association PEI Porcelain Enamel Institute.
PSI Pounds Per Square Inch.
PSF Pounds Per Square Foot.
RTI Resilient Tile Institute.
SBI Steel Boiler Institute.
SCPI Structural Clay Products Institute.
SDI Steel Deck Institute.
SJI Steel Joist Institute.
SMACNA Sheet Metal and Air Conditioning Contractors National Association.
SPR Simplified Practice Recommendation, U.S. Dept. of Commerce.
SSPC Steel Structures Painting Council.
TCA Tile Council of America.
UBC Uniform Building Code.
UFC Uniform Fire Code.
UL Underwriters' Laboratories.
UMC Uniform Mechanical Code.
UPC Uniform Plumbing Code.
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01315
SCHEDULES AND REPORTS
PART 1 GENERAL
Scope: This Section includes the requirements for the submittal of the Contractor's proposed work schedule for the project and a breakdown of the Contractor's bid amount for purposes of making progress payments. The breakdown shall include percent of work completed.
PART 2 PRODUCTS
Submittals: The submittals of the work schedule shall be an electronic copy ONE WEEK prior to start of the project and provide updated changes as necessary to the schedule in a timely manner.
PART 3 EXECUTION
3.01 Work Schedule: Within 15 days of the issuance of the Notice to Proceed, the Contractor shall submit to the Contracting Officer for approval a proposed work schedule for the project. Such schedule shall be in the form of a critical path network or other approved format and shall include the timing for each major phase of the work. The Contractor shall update such approved schedule as necessary when significant changes occur during the progress of the work.
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01442
QUALITY CONTROL & QUANTITY MEASUREMENT
PART 1 GENERAL
1.01 DESCRIPTION
This work shall consist of providing certification that the quality and quantity of demolition conforms to the specifications, and requirements of the CONTRACT.
1.02 MEASUREMENT
No separate measurement or payment will be made for the work in this Section. Please see Section 01315.
PART 2 PRODUCTS
Not Applicable
PART 3 EXECUTION
Not Applicable
END OF SECTION
Forestwide Buildings Demolition Project
SECTION 01501
BUILDING DEMOLITION
PART 1 – GENERAL
1.01 Work covered under this section includes
A. Demolition of designated structures and removal of materials from site.
B. Disconnecting and removal of identified utilities.
1.02 REGULATORY REQUIREMENTS
A. Conform to applicable code for demolition of structures, safety of adjacent structures, dust control, runoff control, and disposal.
B. Obtain required permits from authorities.
C. Notify affected utility companies before starting work and comply with their requirements.
D. Conform to applicable regulatory procedures when hazardous or contaminated materials are discovered.
NOT APPLICABLE
PART 3 EXECUTIONS
3.01 DEMOLITION
A. Sprinkle with water or otherwise maintain demolition areas to minimize dust.
Provide hoses and water connections, or other equipment necessary for this purpose.
B. Disconnect and cap utilities within demolition areas. Remove disconnected utilities.
C. Remove footings, concrete slab, and foundation walls completely.
D. Remove demolished materials from site in accordance with Section 01711.
E. Leave site in clean condition.
SECTION 01505
MOBILIZATION
1.01 DESCRIPTION
This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
1.02 PAYMENT
No separate payment will be made for the work in this Section. See Section 01315.
A. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for Mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
B. When 10 percent or more of the original contract amount is earned from other pay tems, 100 percent of the amount for Mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
C. Upon completion of all work on this project, any unpaid amount for Mobilization will be paid.
D. The total of all payments, including bonding, shall not exceed the original contract amount for this item.
SECTION 01605
MATERIAL SOURCES
1.01 BORROW SOURCES
Borrow sites for material will be available for the Contractors' use from existing borrow pits and staked on the ground or at sites identified by the CONTRACTING OFFICER.
The CONTRACTING OFFICER will determine how much soil may be removed from each borrow site. After borrow is completed, the excavation sites shall be dressed to uniform slopes providing adequate drainage, the bottom smoothed to reduce erosion potential, erosion control devices installed as directed by the CONTRACTING
OFFICER.
1.02 MEASUREMENT AND PAYMENT
No separate measurement and payment will be made for work specified in this Section. See Section 01315.
SECTION 01711
CLEANUP AND DISPOSAL
1.01 SCOPE
A. This work consists of the cleanup required in areas affected by the construction and the disposal of refuse along with demolition and excess materials resulting from construction operations.
1.02 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for the work specified in this Section. See Section 01315.
Not applicable.
PART 3 EXECUTION
3.01 DEMOLITION MATERIALS AND REFUSE (including Hazardous Materials) o All refuse and demolition materials generated by the Contractor's operations including asphalt, concrete, metal, etc., shall be removed from the project site and disposed off National Forest lands in accordance with State and Local regulations. All Material identified as Hazardous shall be removed from the project and transported to approved Hazardous disposed facilities in accordance with all local, County, State and Federal regulations. EPA IDs for USDA Sierra National Forest are as follow:
CAL000453789 Bass Lake Ranger District, 57003 Road 225, North Fork, CA 93643.
CAL000022964 High Sierra Ranger District, 29688 Auberry Road, Prather, CA 93651.
3.02 CLEANUP DURING CONSTRUCTION
Cleanup shall be performed by the Contractor as required to prevent accidents to personnel and protect all work in-place.
Forestwide Buildings Demolition Project Sierra National Forest https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000453789&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=4idB07NR2oWGHiuDDGxJXC%2BvBBNlv5d%2BihDXc7hKf80%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000022964&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=xSRcABgehjXbHcz7zIpitq%2FGfmqQw6pRhgOivGWAqzE%3D&reserved=0
3.03 SALVAGEABLE ITEMS
A. Salvageable items not intended for use in this CONTRACT and not specifically designated to remain the property of the Government shall become the property of the Contractor. See Section 02100.
SECTION 02100
DEMOLITION
1.01 SCOPE
This work shall consist of all site clean up and demolition required to complete the project as indicated in the CONTRACT DOCUMENTS. Work includes, but is not limited to, removal and disposal of on-site debris inside structures. All inorganic material is the responsibility of the Contractor and shall be removed from Forest Service lands, in accordance with Federal, State, and local regulations.
1.02 LOCATION
The project is located Forestwide within the Sierra National Forest, see attached list for each building GPS location.
1.03 DEMOLITION
Work covered under this section includes: Demolition of designated building structure and removal of all miscellaneous items, materials and debris as follow:
• Complete total removal, disposal, and site cleanup of all structures identified in this CONTRACT, that includes ALL items STORED INSIDE the buildings and ALL materials related to each structure above the ground surface and any concrete slab foundation as necessary.
• Abate and dispose of identified hazardous materials (asbestos, flaking lead-based paint, soil contamination, and/or universal waste) in structures in accordance with all Federal, State, and local laws and regulations.
• Excavation, minor clearing, along with removal of concrete slab, above ground utility hardware for electrical, water and sewer is included in this demolition operation.
• Ground plumbing and utilities to be stubbed 2-feet below ground and capped.
Underground and overhead utility service may be existing at the site. All materials and debris designated by the Government shall be removed from the sites, unless identified for salvage as Government property. Close all septic systems if necessary. Closure must be completed in accordance with all Federal, State, and local laws and regulations.
Forestwide Buildings Demolition Project
1.04 PERMITS
As this site is located on Federal land, the County does not require the Contractor to acquire a domolition permit. However, these areas are requlated by the San Joaquin Valley United Air Pollution Control District (SJVUAPCD) for demolition. The Contractor is responsible for submitting the demolition Permit Release form and paying the necessary fees to the SJVUAPCD.
1.05 REGULATORY REQUIREMENTS
The Contractor shall conform to applicable codes for demolition of structures, safety of adjacent facilities, dust control, soil erosion control, and disposal. Contractor shall obtain all required permits if applicable to project operations, notify all affected utility companies if necessary prior to commencing work activities, conform to applicable regulatory procedures and safety precautions when hazardous, contaminated or infectious materials and or debris are encountered during project operations.
PART 2 EXECUTION
2.01 GENERAL
All clearing and demolition work shall be confined within the designated construction limits of decommissioning site areas. All existing site facilities and debris inside structures.
2.02 DUST ABATEMENT AND CONTROL
Contractor shall be required to control and abate dust during all demolition and decommissioning activities for the term of this CONTRACT. The Contractor shall submit a method for dust abatement and control in writing for APPROVAL BY THE CONTRACTING OFFICER to ensure dust abatement for all project operations.
2.03 UTILITIES
All above grade utilities shall be removed and disconnected, capped, and plugged below grade to a depth of 2-feet within the decommissioned site areas. Underground or above grade services designated by the CONTRACTING OFFICER to remain in service shall be disconnected and capped at specified lateral lines or locations.
2.04 TRANSPORTATION
The Contractor shall provide adequate and safe methods for trucking and transporting equipment and materials onto and off the project sites. All local, State, and Federal regulations and laws shall be complied by the Contractor during trucking and transporting operations on Local, County, State, and Forest roads.
2.05 DISPOSAL
o All materials designated for removal from the Decommissioned site areas shall be disposed of off National Forest lands, in accordance with State and local regulations. Burning of removed materials will not be permitted on project sites. All HAZMAT materials and waste found anywhere on the site must be treated and disposed of using State and Local regulations. All labeling, manifesting and Department of Transportation (DOT) regulations must be adhered to for the disposal of any waste that is considered hazardous. EPA IDs for USDA Sierra National Forest are as follow:
CAL000453789 Bass Lake Ranger District, 57003 Road 225, North Fork, CA 93643.
CAL000022964 High Sierra Ranger District, 29688 Auberry Road, Prather, CA 93651.
Sierra National Forest https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000453789&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=4idB07NR2oWGHiuDDGxJXC%2BvBBNlv5d%2BihDXc7hKf80%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fhwts.dtsc.ca.gov%2Fhwts_Reports%2FReportPages%2FReport03.aspx%3Fepaid%3DCAL000022964&data=04%7C01%7C%7Cb10ca512e8b140fc013c08d905241f6b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C0%7C0%7C637546474995581716%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=xSRcABgehjXbHcz7zIpitq%2FGfmqQw6pRhgOivGWAqzE%3D&reserved=0
District Bldg No Building Name Pictures Square Feet Year Built Lat Long
1 FS2617 Batterson Gas/Oil Shed 113 1976 37.37846679 ‐119.630449
2 FS2506 NF Gas/Oil Service Shed 128 1990 37.23586927 ‐119.5062487
3 FS2224 Jerseydale Storage 420 1976 37.54369555 ‐119.833112
4 FS2626 Jerseydale Storage 120 1963 37.54378041 ‐119.8330744
5 FS2365
Midpine Storage Shed Located inside
Jerseydale Station 105 2002 37.54371135 ‐119.8369905
6 FS2616 Big Creek Paint Shed 81 1957 37.20087121 ‐119.2526523
7 FS2624 Big Creek Lumber Shed 364 1961 37.20115409 ‐119.2521654
8 FS2660 Big Creek Hose Bibs Shed 66 1984 37.20099857 ‐119.2525637
9 FS1105 Black Rock Residence 706 1940 36.9146 ‐119.0404
10 FS2308 Black Rock Storage 87 1938 36.9146 ‐119.0402
11 FS2323 Black Rock Fire Cache 696 1955 36.9145 ‐119.0401
Sierra National Forest FORESTWIDE BUILDINGS DEMOLITION and SITE CLEANUP PROJECT
M ad e ra C o u n ty
B as s La ke
R an ge r D is tr ic t
M ar ip o sa C o u n ty
Fr e sn o C o u n ty
H ig h S ie rr a R an ge r D is tr ic t
Forestwide Buildings Demolition Project
District Bldg No.Building Name Pictures Square Feet Year Built Lat Long
FORESTWIDE BUILDINGS DEMOLITION and SITE CLEANUP PROJECT
12 FS1901 Glen Mdw Paint Shed 26 1988 37.07708672 ‐119.1855139
13 FS2316 High Sierra Paint Shed 82 1964 37.31653387 ‐119.0413121
14 FS2324 High Sierra Equipment Shed 48 1988 37.31509561 ‐119.0402496
15 FS28017 Jackass Shower House 233 1990 37.28433316 ‐118.9668633
16 FS2833 Kaiser Digging Storage Shed 243 1971 37.36279 ‐119.24189
17 FS2663 Kokanee WC Storage Shed #2 34 1986 37.25540894 ‐119.1560462
18 FS2664 Kokanee WC Storage Shed #1 34 1986 37.25558657 ‐119.1558205
19 FS2512 Trimmer Gas/Oil Service Shed 248 1990 36.91035162 ‐119.307089
20 FS2636 Trimmer Storage 104 1984 36.90841522 ‐119.3060051
21 FS1321 Wishon WC Storage 132 36.98553025 ‐118.9665506
22 FS1904 Wishon WC Generator Storage Shed 37 1982 36.98541456 ‐118.9659729
23 FS2351 Wishon WC Trailer Pad Shed 32 1973 36.98506706 ‐118.9658283
Fr e sn o C o u n ty
H ig h S ie rr a R an ge r D is tr ic t
Forestwide Buildings Demolition Project
Jerseydale Station #2
Glen Meadow Work Ceter!.
# 6
Trimmer Work Center
#11
Jackass Meadow Station
!.#8
High Sierra Ranger Station
#7
Kaiser Guard Station!.
#9
Kokanee Work Center
#10
North Fork Compound
#3
Wishon Work .
Center #12
Black Rock Station #5
Batterson Work
Center #1
Forestwide Buildings Demolition Project Project Locations¯ 0 105
Miles
!. Demo Building
Demo Areas
Forestwide Buildings Demolition Project
Batterson work center:
Direction: From Herndon/CA-41, take CA-41 NORTH for about 42 miles, pass Oakhurst, turn LEFT onto Batterson Work Center at 43060 CA-41, Oakhurst, CA.
43060 Highway 41 Oakhurst CA 93644
Forestwide Buildings Demolition Project
Jeryseydale Work Center:
6440 Jerseydale Road Mariposa CA 95338
Direction: From Herndon/CA-41, take CA-41 NORTH for about 38.3 miles, turn LEFT onto CA-49 at Oakhurst. Continue on CA-49 for about 14.9 miles, turn RIGHT onto Triangular Road for about 3.1 miles, then turn LEFT and stay on Triangular Road for about 2 miles, then turn RIGHT onto Jerseydale Road for about 2.2 miles until you reach Jerseydale Work Center on the RIGHT at 6440 Jerseydale Road, Mariposa, CA.
Forestwide Buildings Demolition Project
Minarets work center:
Direction: From Herndon/CA-41, take CA-41 NORTH for about 20.6 miles, turn RIGHT onto Road 200 [North Fork Road] at O’Neals for about 16.3 miles, bear RIGHT onto Road 225/Minarets Road for about 4.4 miles, continue straight on Forest Service 04S081 Road for about 35.4 miles until you reach Minarets Work Center on the LEFT.
T6S R24E S16 37.409013, -119.348095
Forestwide Buildings Demolition Project
North Fork Compound:
57003 Road 225 North Fork CA 93643
Direction: From Herndon/CA-41, take CA-41 NORTH for about 20.6 miles, turn RIGHT onto Road 200 [North Fork Road] at O’Neals for about 17.1 miles, bear RIGHT onto Road 225 for about 0.3 mile, then turn LEFT onto Forest Service Road 8S050, Grizzly Road, into North Fork Complex, Bass Lake Ranger District Office, 57003 Road 225, North Fork, CA.
Forestwide Buildings Demolition Project
PLACER GUARD STATION:
Placer Guard Station is located at GPS location:
T7S R24E S29 37.37376259, -119.3634791
Direction: From Herndon/CA-41, take CA-41 NORTH for about 20.6 miles, turn RIGHT onto Road 200 [North Fork Road] at O’Neals for about 16.3 miles, bear RIGHT onto Road 225/Minarets Road for about 4.4 miles, continue straight on Forest Service 04S081 Road for about 34.4 miles, turn RIGHT onto 5S25 Road [Mammoth Pool Road] for about 6.1 miles and then turn RIGHT onto Road 06S25 for about 0.5 mile until you reach Placer Campground ahead.
Forestwide Buildings Demolition Project
Black Rock Station:
T12S R27E S4 36.914670, -119.040363
Direction: From N. Clovis Ave/CA-180, take CA-180 EAST for about 12.4 miles, turn LEFT onto Piedra Road for about 8.5 mile, RIGHT onto E. Trimmer Springs Road for about 21.5 miles, merge onto Forest Service Road 10S012, Black Rock Road for about 1.0 mile, turn LEFT onto Bailey Bridge, turn LEFT to continue on Forest Service 11S12 Black Rock Road for about 14 miles, until you reach Black Rock Station on the RIGHT.
Forestwide Buildings Demolition Project
Glen Meadow Work Center:
50810 Dinkey Creek Road Shaver CA 93664
Direction: From Fowler/CA-168, take CA-168 EAST for about 39.2 miles until you get to town of Shaver, then RIGHT onto Dinkey Creek Road for about 8.4 miles, then turn LEFT into Glen Meadow Work Center.
High Sierra Ranger Station:
Direction: From Fowler Ave/CA-168, take CA-168 EAST for about 60 miles pass Shaver Lake and China Peak Resort, turn RIGHT onto Kaiser Pass Road for about 15.7 miles until you reach High Sierra Ranger Station on your RIGHT.
71000 Kaiser Pass Road Lakeshore CA 93634
Forestwide Buildings Demolition Project
Jackass Meadow Station:
Direction: From Fowler and CA-168, take CA-168 EAST for about 60 miles pass Shaver Lake and China Peak Resort, turn RIGHT onto Forest Service 05S008 Road, Kaiser Pass Road, for about 16 miles, pass High Sierra Ranger Station, until you reach the intersection of Kaiser Pass Road and Forest Service 07S001 Road, Florence Lake Road, turn RIGHT onto Florence Lake Road for about 5.6 miles, then turn LEFT onto Forest Service Road 07S070, Jackass Meadow Road, for about 0.7 mile, then turn LEFT onto Forest Service Road 07S070A, Jackass Cabin Road, for about 0.1 mile until you reach Jackass Meadow Station.
Note: Both Roads 07S070 and 07S070A have gate.
T8S R28E S36 37.284334, -118.966934
Forestwide Buildings Demolition Project
Kaiser Digging Guard Station:
37.36279 -119.24189
Direction: From Herndon/CA-168, take CA-168 EAST for about 63.6 miles passing through the town of Shaver and China Peak Ski Resort, turn slight LEFT onto Huntington Lake Road for about 7.1 miles, turn RIGHT onto Big Creek/Eastwood Lane/Huntington Lake Road for about 1.5 miles, continue STRAIGHT onto Forest Service 07S005 Road for about 20 miles to the end of asphalt, then turn LEFT onto Forest Service 06S002 Road for about 1.1 mile until you reach Kaiser Digging Guard Station, the building will be on the RIGHT, about 500 feet off the road.
Forestwide Buildings Demolition Project
Kokanee Work Center:
61725 CA-168 Lakeshore CA 93634
Direction: From Fowler and CA-168, take CA-168 EAST for about 59 miles pass Shaver Lake and China Peak Resort, until you reach Kokanee Work Center on the RIGHT at 61725 CA-168, Lakeshore, CA. If you get to the intersection of CA-168 and Kaiser Pass Road, you have missed the turn off to Kokanee WC.
Note: At the beginning of the Road to Kokanee Work Center, there is a double gate that is locked until June when the snow melted.
Forestwide Buildings Demolition Project
Trimmer Work Center:
34849 Maxon Road Sanger CA 93657
Direction: From Fowler Ave/CA-168, take CA-168 EAST for about 10.8 miles, then RIGHT onto Sample Road for about 3.0 miles, then RIGHT onto Pittman Hill Road for about 1.2 miles, then LEFT onto Wyatt Valley Road for about 7.4 miles, continue STRAIGHT onto Maxon Road about 3.9 miles until you reach you Trimmer Work Center on the RIGHT at 34849 Maxon Road, Sanger, CA.
Forestwide Buildings Demolition Project
Wishon Work Center:
T11 S R28E S7- NE ¼ of the SW 36.984055, -118.965861
Direction: From Fowler/CA-168, take CA-168 EAST for about 39.2 miles until you get to town of Shaver, then RIGHT onto Dinkey Creek Road for about 11.8 miles, then turn RIGHT at the Bridge onto Forest Road 11S40, McKinley Grove Road, for about 19.4 miles, pass the Wishon Reservoir Bridge until you reach Wishon Work Center on the RIGHT.
Note: Wishon Work Center has a gate which is locked between October to June.
Forestwide Buildings Demolition Project
| !!SPECS INDEX Forestwide Demolition Project |
| SPECS INDEX FORESTWIDE DEMOLITION PROJECT |
| Division 2 -Site Work |
| section_01010_Summary |
| section_01040_Coordination |
| section_01060_Regulatory |
| section_01070_Abbr_Symbols |
| section_01315_Schedules_and_Reports |
| section_01442_Quality_Control |
| section_01501 building demolition |
| section_01505_Mobilization |
| section_01605_Material_Sources |
| section_01711_Cleanup_Disposal |
| section_02100_Demolition |
| Project Site Locations and Directions.pdf |
| 1. Batterson WC |
| 2. Jerseydale Work Center |
| 3. Minarets Work Center |
| 4. North Fork Compound |
| 5. Placer Guard Station |
| 6. Black Rock Station |
| 7. Glen Meadow WC |
| 8. High Sierra Ranger Station |
| 9. Jackass Meadow Station |
| 10. Kaiser Digging Guard Station |
| 11. Kokanee WC |
| 12. Trimmer WC |
| 13. Wishon WC |