Attachment 001 - Statement of Work.docx

DOCX document 129 KB Posted

Attached to
PBA Substation Repair Federal contract opportunity
Solicitation number
W519TC23B2001
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This solicitation is for a substation repair project at Pine Bluff Arsenal in Pine Bluff, Arkansas. The U.S. Army Contracting Command - Rock Island is seeking a contractor to repair two substations, Substation B and Substation C, in accordance with the attached scope of work. A pre-bid site visit will be held on January 4, 2023, with questions due by January 6. Technical proposals are due January 20 and should not include pricing. Only proposals deemed acceptable will proceed to price bidding. Price bids are due February 10 and the bid opening will occur on February 14. This procurement is set aside for women-owned small businesses. The prevailing Davis-Bacon wage determination is included. The period of performance will be governed by the resultant contract.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pine Bluff Arsenal Directorate of Public Works Engineering Plans and Services Division

Project ID:

Date:
05July2022
Project Name:
Substation B and C Repair
Subject:
Scope of Work
By:
Davis Harp

GENERAL STATEMENT OF WORK

The Pine Bluff Arsenal (PBA) has a requirement to repair two locally owned substations, Substation “B” and Substation “C”.

Contractor shall provide all supervision, labor, materials, and equipment necessary to complete the work as described in this SOW.

All works shall comply with IEEE C2 National Electric Safety Code.

Supervisor shall be either a licensed Journeyman Electrician, a licensed Master Electrician, or have 10 years substation supervisory experience.

Substation B Circuit Characteristics Power Company’s Service: 13.8 kV, 3PH, 4W, 60 Cycles Primary Distribution: 7.6/13.2 kV, 3PH, 4W Substation Capacity Transformers: 1 – 15,000 kVA, Wye-Wye (off-site) Feeder Circuit: 4 – 600A Circuits

Substation C Power Company’s Service: 115 kV, 3PH, 3W, 60 Cycles Primary Distribution: 7.6/13.2 kV, 3PH, 4W, Grounded Neutral Substation Capacity Transformers: 2-10/12.5 MVA DELTA WYE Feeder Circuits: 4-800A Circuits

DETAILED SCOPE OF WORK

Coordinating with PBA and Entergy, contractor shall perform the following work.

Substation B

1. Provide pole mounted Voltage regulator bank with bypass between Entergy’s feed and Substation B.

2. Provide and connect three voltages regulators

a. 333 kVA

b. Single phase

c. Matched Bank

d. Automatic 32 position with 16 steps above and 16 steps below.

e. 7620 Volt

f. 437 amp

3. Replace wire running from Entergy-Owned pole to bus.

4. Replace all hardware between Entergy feed and back end of voltage regulator bay.

Substation C

1. Replace Circuit switcher

a. 121 kV

b. 550 BIL

c. 1200A Continuous

d. 20,000 AIC, RIM Symmetrical

e. S&C Series 2010 Circuit Switcher

f. CAT. NO. 197738-B-E12-K-L1-L2-M-T-V-W1

g. Gas-Pressure Indicator is red

2. Replace Tie Switch Load Break

a. 14.4 kV

b. 110 BIL

c. 1200A Continuous

d. Group Operated Rotating Insulator Vertical Break Interrupter Switch for Horizontal Mounting with double offset operating Handle and all mounting hardware switch

e. S&C 32022R9

3. Replace Broken Hardware to include

a. Insulators

b. 12 kV station class lightning arrestor (Metal Oxide Type)

c. Outdoor Current Transformer

4. Close all connections Option

1. Dispose of current three phase transformer

a. Allis-Chalmers

i. Class OA 1500 kVA

ii. Untanking Weight 13,545 lbs

iii. Total weight 26,670 lbs Site Visit A site visit will be held at Pine Bluff Arsenal before quotes are due. While not required, Contractors are strongly encouraged to attend to see the exact site conditions and to account for those conditions in the quote. It is the Contractor’s responsibility to ascertain the condition of the work site.

OPSEC

Access and general protection/security policy and procedures. Contractor and all associated sub‐contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements( FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (TSDB) (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

iWATCH Training. The contractor and all associated sub‐contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

Deliver to:

Pine Bluff Arsenal 23-100 Substation “B” Pine Bluff, AR 71602

Pine Bluff Arsenal 53-600 Substation “C” Pine Bluff, AR 71602

IMPORTANT LOCAL INFORMATION

SECURITY VETTING REQUIREMENTS

The Pine Bluff Arsenal (PBA) Vetting Program is being changed to comply with installation access requirements identified in AR 190-13, HSPD-12 and DTM 09-012. Access policy requires all unescorted persons entering DOD installations to have a valid purpose to enter, have their identity verified and vetted to determine the fitness of the individual requesting and/or requiring access to the installation, and be issued or in possession of an authorized and valid access credential. They also require local passes only be issued to non-DOD cardholder personnel who have successfully passed an NCIC check.

The Directorate of Law Enforcement and Security (D/LE&S) requires background checks to be conducted on all individuals 16 years of age or older who do not possess a valid DOD Identification (ID) credential (i.e. CAC, Military Id) prior to being granted access onto PBA. This change includes 100% of contractors, vendors, commercial carriers, visitors, Natural Resources customers, MWR customers and CYS customers.

The following criteria will prevent access to PBA: Violent Offense Conviction within the last ten (10) years, Felony or Misdemeanor Class A Conviction within the last five (5) years, Current Pending Charges, Active Warrant or Convicted Sex Offender. Habitual Offenders with three (3) or more criminal convictions may also be denied access at the mutual discretion of two Certified ACIC/NCIC Operators. In addition, the following criteria will prevent hunting on PBA: Felony Conviction, Domestic Violence Conviction, DUI/DWI Conviction within the last five (5) years or Active Order of Protection.

AMC-LEVEL PROTEST PROGRAM

If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible contracting officer. However, you can also protest to Headquarters, AMC. The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the General Accounting Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. If you want to file a protest under the AMC-Level Protest Program, the protest must request resolution under that program and be sent to the address below. All other agency-level protests should be sent to the contracting officer for resolution.

Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road

RM: A6SE040.001

Redstone Arsenal, AL 35898-5000

Fax: (256) 450-8840 or e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil Packages sent by FedEx or UPS should be addressed to:

Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road

RM: A6SE040.001

Redstone Arsenal, AL 35898-5000 Fax: (256) 450-8840 or e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil AMC-Level Protest Procedures are located on the Internet. If Internet access is not available, contact the contracting officer or HQ, AMC to obtain the AMC-Level Protest Procedures.

http://www.amc.army.mil/pa/COMMANDCOUNSEL.asp

OSHA STANDARDS

Contractor must comply with all applicable OSHA standards.

INSPECTION AND ACCEPTANCE

a. The work will be conducted under the general direction of the Contracting Officer and is subject to inspection by his appointed inspectors to insure strict compliance with the terms of the contract. No inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the contractor from any requirements of the contract.

b. The Contracting Officer shall designate individuals to act as the Contracting Officer’s Representative (COR) under any resultant contract. Such representative will be designated in writing by the Contracting Officer with a copy of designation to the contractor. The COR will represent the Contracting Officer in the technical phases of the work, but will not be authorized to change any of the terms and conditions of the contract.

c. The COR will act in a liaison capacity to coordinate activities between the contractor and the Government as required in the performance of work under the contract.

INSURANCE RQUIREMENTS

The following insurance is required as a minimum in accordance with the Federal Acquisition Regulation and the appropriate clause in Section I:

a. Legally Required Insurance: When certain laws apply, such as state laws governing workman's compensation and employer's liability coverage, etc., the contractor, prior to commencement of work, shall furnish the Contracting Officer a written statement that such laws have been complied with and that compliance will continue throughout the period of contract performance. Minimum coverage of $100,000.00 is required.

b. Comprehensive General Liability and Automobile Liability:

PerProperty
Each PersonOccurrenceDamage
ComprehensiveNone$500,000None
General Liability

Automobile Liability $200,000 $500,000 $20,000

DELIVERY OF MATERIALS

It is the responsibility of the contractor or subcontractor to inform their vendors or truck drivers of the prime contractor's name, contract number and work site. Pine Bluff Arsenal is a controlled access installation therefore, subcontractors, vendors, or delivery persons who do not possess the above information and other proper identification as required by the Security Office may be denied access to Pine Bluff Arsenal. Any delay caused by such denial will be at the contractor's expense and no time extensions for such delays will be allowed. Contractors will provide escorts for suppliers' trucks from the perimeter gates to job site when required.

NOTICE OF POSSIBLE DELAYS

During the time a contractor is working on the Arsenal he may, from time to time, be working in an area where munition test exercises are conducted. While it is not the Arsenal's policy to interfere with a contractor during these test exercises, delay may occur. These delays may involve contractor personnel being withdrawn from an area or being denied access for a period of time. The length of time and frequency of these delays will be held to a minimum. No claim shall be submitted for less than five (5) man-hours per month. Claims may be submitted under the Changes Clause of the contract.

BURIED CABLES AND LINES

The contractor shall submit a Pine Bluff Arsenal Request to Mark Utility Lines and submits the same to the Contracting Officer's Representative (COR) three (3) working days prior to commencing any digging on the Pine Bluff Arsenal. Blank forms will be issued at the Post Award Meeting. If the Contractor fails to provide notification, the Contractor shall be liable for any damages to any buried telephone cables or utility lines regardless of care exercised or drawings followed.

The Government shall not grant time extensions nor pay additional costs incurred because of delays, unless the Contractor has properly notified the Government one working day in advance of the desired digging date.

DISMISSALS

The Contracting Officer may require the contractor to suspend or dismiss from work any employee or employees whose retention is deemed to be not in the public interest, because of the misconduct of the employee or for reasons of security, subject, however, to appeal under the provisions of Articles entitled "Disputes" for reinstatement of such employees.

SUBMITTALS

Should the contractor desire to furnish the brand name and models set forth in the specification, submittals will not be required; however, a certification for the contractor will be required stating the brand name and model which will be used in the performance of this work. Contractors shall be required to furnish samples or descriptive literature on "or equal" products as set forth in the specifications.

SECURITY REQUIREMENTS

During the time that the contractor performs work on post, he is expected to be aware that Pine Bluff Arsenal is a controlled access installation. Specific security requirements as they apply to the project site will be noted during a post –award conference. The contractor will exercise care to prevent unauthorized intrusions by locking gates, closing and locking doors/windows, and performing similar actions. In the event that a breach of security occurs notwithstanding the contractor’s efforts to prevent it, he shall immediately notify the Pine Bluff Arsenal Security Police (540-3505), reporting the occurrence and explaining the nature of the violation.

UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT PERSONNEL

a. The contractor will not accept any instructions by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the designated Contracting Officer’s Representative (COR) acting within the limits of his authority. Contracting Officer’s Representative will be so designated in writing to the contractor and the scope of his authority will be set forth therein.

b. No information, other than that which may be contained in an authorized modification to this purchase instrument duly issued by the Contracting Officer, may be considered a valid obligation. Information received from any other person employed by the U.S. Government will not be considered grounds for deviation from any stipulation of this purchase instrument or referenced drawings and/or specifications.

INSTRUCTIONS FOR PAYMENT OF SUBCONTRACTORS

Offerors are advised that in accordance with regulations, prime contractors shall (if applicable) include on payment requests a certification that sub-contractors have been paid from previous payments and that payments will be paid to subcontractors from payments being requested. The preceding is applicable to procurement documents awarded, renewed or which have options exercised on or after April 1, 1989. Additionally, prime contractors shall make payment to their subcontractors (if performance is satisfactory) seven (7) days after the Government pays the prime. Prime contractors are to pay interest to their subcontractors for late payments.

SAFETY REQUIREMENTS

The contractor will comply with the following factors:

a. Applicable portions of Department of Labor, Occupational Safety and Health Administration (OSHA) Standards 29 CFR 1910 and 1926; etc.; Army Regulation (AR), Department of Army Pamphlets (DA PAM); Pine Bluff Arsenal Regulations (PBAR); PBA Policy Letters; EM 385-1-1; General Safety Requirements (latest issue), whichever is the most stringent. The contractor shall be required to comply with any provisions of the Act/Manual pertaining to this operation. Any violation noted by the Contracting Officer or PBA Safety Officer must be corrected.

b. Where the work requires, the contractor will be required to furnish all personnel, equipment, marking, etc., necessary for the safe movement and flow of traffic at the job site as determined by the Contracting Officer.

c. Warning and Safety Signs – The Contractor shall install warning and safety signs at all strategic locations on the work site. Signs and barricades shall be constructed in accordance with OSHA standards.

d. Illumination – If night operations are carried on, the contractor will be required to furnish all plant, equipment, and labor necessary to insure adequate illumination. Prior to commencing night operations the contractor shall submit a plan to the Contracting Officer for approval showing the illumination layout he proposes to use. Adequate illumination as used herein shall be construed as the minimum lighting required to provide safe working conditions for contractor and Government personnel wherever work on this contract is in progress. There shall be sufficient light to permit the work to be performed in accordance with the plans and specifications and to permit complete inspection of all the work.

e. In certain specified areas, matches, lighters, or other flame producing devices will not be allowed. Smoking is absolutely prohibited in any of the restricted areas, buildings, or in cars and trucks except as authorized by the Contracting Officer.

f. Safety Briefing – The contractor shall allow for a 45 minute, mandatory, Safety briefing for all employees conducted at the Pine Bluff Arsenal Pass and ID office.

g. Notice of Required Seat Belt Use – As a means to increase safety, the Commander, Pine Bluff Arsenal, has established a policy that all occupants of a vehicle on the Pine Bluff Arsenal shall wear a seat belt. This policy extends to contractors and/or sub-contractors. Failure to use seat belts may result in the issuance of a citation or loss of driving privileges on the Pine Bluff Arsenal.

h. The contractor shall provide evidence that the company has a Safety & Occupational Health Plan.

i. The Contractor and Contracting Officer's Representative (COR) will document any hazardous work to be accomplished on the Hazardous Work Permit (Form PBA 387-7) in accordance with PBAR 385-31.

j. The General Contractor is responsible for assuring their sub-contractors comply with the safety items above.

MAGISTRATE SYSTEM

Contractors are hereby notified that in accordance with the United States Code, the Federal Magistrate System has been enacted at Pine Bluff Arsenal. Persons issued a citation on Pine Bluff Arsenal are subject to fines and may be required to appear before a Federal Magistrate in Little Rock, Arkansas.

ORDER AND SCHEDULING OF WORK

a. Unless otherwise expressly provided in the specifications, the contractor shall work only the normal working hours of Pine Bluff Arsenal, 7:00 a.m. to 4:30 p.m., Monday through Thursday and 7:00 a.m. to 3:30 p.m., every other Friday. However, contractor shall coordinate Friday work with the Contracting Officer or Contracting Officer’s Representative, on Government Holidays or days that are observed in lieu of Government holidays or other days that are declared non-work days by the commanding Officer of Pine Bluff Arsenal or official of higher headquarters. Deviations from this requirement must be requested in writing and be approved by the Contracting Officer prior to the proposed extra working hours or work days.

b. Government holidays are as follows:

New Year’s DayIndependence DayLabor Day
Thanksgiving DayChristmas DayMemorial Day
Veteran’s DayColumbus DayPresidents’ Day

Martin Luther King’s Birthday

When one of the above designated holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday by U.S. Government agencies.

c. In the event the Contractor wishes to perform work outside the normal work hours, he shall submit his request through the technical representative to the Contracting Officer for approval. If such request is approved, the Contractor may be required to reimburse the Government for the cost of having an inspector at the work site.

INSURANCE LIABILITY

a. Workers' compensation and employer's liability. Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statues, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so co-mingled with a contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

b. General Liability. Bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence is required.

c. Automobile Liability. Automobile liability insurance written on the comprehensive form of policy is required. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on the policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

KEY PERSONNEL

The contractor shall notify the Contracting Officer prior to making any changes in key personnel. Key personnel are defined as follows:

a. Personnel identified in the proposal as key individuals to be assigned for participation in the performance of the contract;

b. personnel whose resumes were submitted with the proposal; or,

c. individuals which are designated as key personnel by agreement of the Government and the contractor during negotiations.

The contractor must demonstrate that the qualifications of prospective personnel are equal to or better than the qualifications of the personnel being replaced. Notwithstanding any of the foregoing provisions, key personnel shall be furnished unless the contractor has demonstrated to the satisfaction of the COR that the qualifications of the proposed substitute personnel are equal to or better than the qualifications of the personnel being replaced.

PAYMENT INSTRUCTIONS

Follow WAWF clause 252.232-7006 Wide Area Workflow Payment Instructions located in the contract.

NOTICE AND ACCEPTANCE OF HAZARDS

In Accordance with DA PAM 384-64 and DESR 6055.09. You will be entering an explosion hazard area. Hazards may include: danger of death, serious injury and risk of loss, or damage to equipment. Do not stay longer than necessary.

ENVIRONMENTAL REQUIREMENTS INFORMATION

COMPLIANCE WITH ENVIRONMENTAL LAWS AND REGULATION

Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR).

COMPLIANCE WITH GREEN PROCUREMENT REGULATIONS

Contractor shall follow Federal EPA Comprehensive Procurement guidelines www.epa.gov/cpg) and Army Contracting Command Quick Guide https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.

COMPLIANCE WITH LICENSE AND CERTIFICATION REQUIREMENTS

Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.

NOTIFICATION OF FDERAL AND STATE REGULATORS

Contractor shall immediately notify the Designated Government Representative (DGR) and COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.

INSPECTION OF WORKSITES

Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.

REPORTING NONCOMPLIANCE

Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and DGR.

VERIFICATION OF NATIONAL ENVIRONMENTAL POICY ACT DOCUMENTS

Contractor shall obtain from the COR or DGR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses actions to be taken by contractor. These documents include but is not limited to the analysis-associated decision document of an Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.

CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEM

Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.

COMPETENCY TRAINING FOR CONTRACTOR PERSONNEL

Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.

GENERATION OF SOLID WASTE

Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.

1. Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.

2. Prior to removing any waste from the installation for disposal, the Contractor shall coordinate with the installation Qualified Recycling Program (QRP) Manager, DGR, and COR to arrange for recyclable materials to be removed and diverted from the waste stream.

3. Submit in writing the quantities of waste removed and recycled to the DGR and/or COR on a monthly basis. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and the quantities of materials disposed/recycled by weight.

4. The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

5. The Contractor shall make maximum effort to reduce and prevent waste.

GENERATION OF HAZARDOUS WASTE

Contractor shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the DGR and/or COR to obtain technical assistance from the Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement or Status-of-Forces Agreement. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, then take the manifest to DGR for approval and signature prior to removing any hazardous waste from the installation. Contractor shall contact DGR to obtain the installation’s hazardous waste EPA ID number for the hazardous waste manifest. The Contractor shall notify the DGR 24 hours prior to removing any hazardous waste from the installation. The contractor shall remove and dispose of manifested hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The DGR shall assist contractors with profiling their waste upon request.

USE OF HAZARDOUS MATERIALS

Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR or COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR and/or COR.

PREVENTION OF STORM WATER POLLUTION

The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the Pollutant Discharge Elimination System general permit requirements. Applicable permits include:

1) The installation’s Small Municipal Separate Storm Sewer System (MS4) Permit;

2) The Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activities (MSGP); and,

3) All Construction Activity Storm Water permits minimum control measures include, but not limited to:

• Public Education and Outreach on Storm Water Impacts

• Public Involvement and Participation

• Illicit Discharge Detection and Elimination

• Construction Site Storm Water Run-off Control

• Post Construction Storm Water Management in New Development and Redevelopment

• Pollution Prevention/Good Housekeeping for Municipal Operations Contractors will comply with the MSGP permit when the activity is identified as a permitted industrial activity. BMPs include, but are not limited to:

• Practicing spill prevention and good housekeeping.

• Installing and managing erosion and sediment control.

• Meeting the requirements of the MS4 permit.

• Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). BMPs include, but are not limited to:

• Preparing and implementing a site-specific Storm Water Pollution Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.

• Installing and managing erosion and sediment control.

• Make available, upon request, permit associated documentation.

• Practicing spill prevention and good housekeeping.

• Meeting the requirements of the MS4 permit.

• Schedule inspections and provide corrective actions for noted deficiencies.

STORM WATER MANAGEMENT LOW IMPACT DESIGN/DEVELOPMENT (LID)

The Contractor shall perform, track, participate, implement, and comply with Section 438 of the Energy Independence and Security Act; Executive Order 13514; and the DOA memorandum (2010) for full implementation of low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size. In support of LID, Contractors will adhere to installation landscape codes and the guidance found in the Installation Design Guide concerning Low Impact Design/Development for storm water management.

The following LID practices include, but are not limited to:

• Restoring predevelopment hydrology to the maximum extent technically feasible

• Promoting natural removal of pollutants such as nutrients, oil and grease, and sediments from storm water

• Managing rainfall at the point where it falls

• Meeting the requirements of the MS4 permit

• Important Note: Utilization of permanent retention/detention ponds is prohibited without authorization from the Installation Planning Division.

USE OF PESTICIDES

Contractor shall submit the type and quantity of regulated pesticides to be applied, the application purpose, and location to the DGR and COR for approval 10 working days prior to the initial application. The Contractor shall submit the actual quantities applied (DD1532 or equivalent) to the DGR and COR within 2 working days (48 hours) after each approved application. The Contractor shall utilize Integrated Pest Management (IPM) technology and procedures in strict compliance with all applicable Federal, State, Army, and installation regulations, to include the installation's integrated pest management plan. Pesticide applicators shall be certified and licensed in accordance with the State where work is being performed and/or Department of Defense regulations. The Contractor shall provide evidence of personnel licenses and certifications to the Contracting Officer and the DGR prior to the initial application of pesticides. Only those pesticides registered with the US Environmental Protection Agency (EPA) and approved by Army Materiel Command Pest Management Consultant shall be utilized and then only in strict accordance with product labeling. The installation reserves the right to prohibit and limit the amount and type of pesticides used.

PROTECTION OF WORKSITE RESOURCES

Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the DGR and/or COR. Contractor shall notify the DGR and/or COR if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the DGR or COR.

PREVENTION OF SPILLS

Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

PROTECTION OF SENSITIVE AREAS

Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements:

Cultural Resources Sites Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.

Endangered Species Habitats Do not initiate any action that may disturb, endanger, or damage to any degree the habitat of a threaten and endangered species.

Wetlands Do not excavate or take any action that could fill or damage any wetland unless working under a project specific Corps of Engineers 404 permit. Wetlands include streams, riparian areas, bogs, marshes, and swamps.

CORRECTIVE ACTION FOR NONCOMPLIANCE

Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action. Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.

NOISE

Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the DGR and COR.

MERCURY MATERIALS

Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed. Immediately report to the DGR and COR instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.

UNIVERSAL WASTE / E-WASTE MANAGEMENT

Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.

POLLUTION PREVENTION / HAZARDOUS WASTE MANAGEMENT

Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution Prevention/hazardous waste minimization plan for supporting waste minimization goals.

- End SOW -

Substation B and C Repair work SOW Page 15 of 16 image1.png image2.png

File details come from the government source that posted it. Updated .