Attachment 0005 - Schedule of Values.pdf
PDF 78 KB Posted
- Attached to
- UPGRADE FRISCO BEACH ACCESS Federal contract opportunity
- Solicitation number
- 140P5521R0006
About this file
This document contains a schedule of values for upgrading the Frisco Beach access in accordance with the statement of work, specifications, drawings and Davis-Bacon wage determination NC20210065 dated 1 January 2021. The schedule of values breaks down the project into tasks including site improvements, parking lot work, building rehab and decking, a temporary latrine facility, and general conditions. It provides the quantity, unit of measure, material cost, labor cost, equipment cost, unit cost, subtotal, overhead and profit, and total cost for each task. The project will be completed for the Department of the Interior National Park Service Southeast Region in accordance with the requirements laid out in solicitation number 140P5521R0006.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5521R0006_Amd_0002.pdf | ||
| Sol_140P5521R0006_Amd_0001.pdf | ||
| Attachment 0004 - Wage Determination NC20210065.pdf | ||
| Pre-Proposal Meeting Site Map.png | PNG image | |
| Attachment 0003 - 2020_1130_-_CAHA_239718_-_Stamped_Drawings.pdf | ||
| Attachment 0002 - 2020_1130_-_CAHA_239718_-_Specifications.pdf | ||
| Attachment 0001 - Rev_1_Scope_of_Work_Upgrade_Frisco_Beach_Access.Final.pdf | ||
| Sol_140P5521R0006.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF VALUES
Notes
LOCATION: Outer Banks Group, NC
QUANTITY MATERIAL COST LABOR COST EQUIPMENT COST
UNIT UNIT UNIT UNIT Subtotal OH & P Total
TASK DESCRIPTION # UNITS MEASURE PRICE COST PRICE COST PRICE COST Cost Cost Cost Notes
Parking and Site work Site Improvements 1 LS Site Preparation 1 LS
General Conditions Standard General Conditions 1 LS
SUBTOTAL Parking Lot work
Building Rehab and Decking
Foundations 1 LS Superstructure 1 LS Exterior Enclosure 1 LS Interior Construction 1 LS Interior Finishes 1 LS Plumbing Systems 1 LS
HVAC 1 LS
Electrical 1 LS Selective Building Demolition 1 LS
SUBTOTAL Building and Decking
Temporary Latrine Facility 4 Unit Trailer 1 LS Daily Cleaning 1 LS
TOTAL Parking & Building
DATE:
Base Parking & Rehab Work