This document is a scope of work for upgrading the Frisco Beach Access area at Cape Hatteras National Seashore in North Carolina. The project includes expanding an existing parking lot to add approximately 25 new spaces, rehabilitating the existing comfort station, and replacing the exterior decking and showers. The period of performance is 120 calendar days from notice to proceed. The contractor must provide temporary latrine facilities with at least four individual unisex toilet rooms, one of which must be ADA compliant, as well as a temporary outdoor shower area with four shower fixtures during construction. The contractor will be responsible for daily cleaning and resupply of the temporary facilities. This scope of work corresponds to the federal contract opportunity to upgrade Frisco Beach Access issued by the National Park Service Southeast Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5521R0006_Amd_0002.pdf | ||
| Sol_140P5521R0006_Amd_0001.pdf | ||
| Attachment 0004 - Wage Determination NC20210065.pdf | ||
| Pre-Proposal Meeting Site Map.png | PNG image | |
| Attachment 0005 - Schedule of Values.pdf | ||
| Attachment 0003 - 2020_1130_-_CAHA_239718_-_Stamped_Drawings.pdf | ||
| Attachment 0002 - 2020_1130_-_CAHA_239718_-_Specifications.pdf | ||
| Sol_140P5521R0006.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Upgrade Frisco Beach Access Area Page 1
CAPE HATTERAS NATIONAL SEASHORE
Outer Banks Group
Scope of Work
Upgrade Frisco Beach Access Area
PMIS # parking: 254066B (Component B includes relocating parking from Frisco Pier site to Frisco Beach Access)
PMIS # building: 239718 (Component A is for building renovation, Component B is design, Component C is exterior deck, showers, and ABA ramp)
1.0 INTRODUCTION
The National Park Service (NPS) Cape Hatteras National Seashore (CAHA) has a requirement to upgrade the Frisco Beach Access Area located immediately south of Frisco, NC. The project includes parking, decking, exterior showers, and rehabilitation of the comfort station
2.0 CONSTRUCTION SITE LOCATION
The construction site is located Approximately 0.1 miles south of the Village of Frisco, NC on the east side of NC Highway 12.
Figure 1: Frisco Beach Access Site
3.0 BACKGROUND AND EXISTING CONDITIONS
The existing Comfort Station was constructed in the mid-1980s. The structure is a wood frame building on wood pile foundation. Exterior walls do not reach the roof but provide a ventilation
Upgrade Frisco Beach Access Area Page 2 space between the top of wall and roof structure to provide for ventilation. This ventilation space has plywood covers installed during cold weather. with walls below the structure roof to provide for ventilation. The hipped roof has asphalt shingles with 2 sky lights installed. Cedar shingle siding is installed on exterior walls.
The NPS had a design project completed for rehabilitation of the structure and surrounding site.
Electricity is supplied from Cape Hatteras Electric Co-op (CHEC) and water service is provided by the Dare County Water Department (DCWD).
The comfort station drains wastewater to a septic tank and drain field.
4.0 STATEMENT OF WORK (SOW): This SOW incorporates the attached 527 page specifications and the attached 45 pages of drawings
The major project components are listed below but are not limited to the following:
4.1 BASE BID: Expand existing parking, Rehabilitate the comfort station, and replace exterior decking and showers according to the associated design documents.
4.1.1 Contractor shall provide parking access to the public (approximately 25 spaces) at the southern end of the parking lot.
4.1.2 Contractor shall submit plan for NPS approval to provide beach access from the public parking spaces to the beach.
4.1.3 Emergency Access shall be established, signed, and left available for emergency vehicles.
4.2 PERIOD OF PERFORMANCE: 120 Calendar Days after issuance of the Notice to Proceed. Work shall generally be performed during normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, excluding Federal Holidays.
However, weekend work and early morning/late evening hours can be requested through the Contracting Officer, if required. Contractor shall provide notice to the CO at least 48 hours prior to the requested date desired to conduct work outside of normal work hours. NOTE: If additional hours are requested and approved, Contractor employees are not authorized to work more than 40 hours per week.
4.3 . Provide Temporary Latrine Facilities.
4.3.1 Provide a temporary latrine facility with at least 4 individual unisex toilet rooms.
4.3.2 Temporary facility shall be connected to electricity and domestic water supply. The Contractor shall coordinate and follow requirements of CHEC and DCWD for electric and water meters, connection stand, backflow preventer, etc.
4.3.3 Temporary facility shall include heating and air conditioning, including a thermostat which can be set and locked.
4.3.4 Temporary facility shall be installed and leveled. The floor and exterior landing/accessible ramp shall be checked weekly for level and adjusted to stay within 1:48 maximum slope for floors and 1:12 max slope for accessible ramp.
Upgrade Frisco Beach Access Area Page 3
4.3.5 Temporary facility shall be anchored into the ground/pavement.
4.3.6 Each restroom shall have a locking door which can be unlocked from the exterior via key. A key shall be maintained securely on site by the Contractor and two keys provided to the NPS point of contact.
4.3.7 Each toilet room shall have a single toilet and sink.
4.3.8 One toilet room shall be Architectural Barriers Act (ABA) compliant.
4.3.9 The temporary latrine facility shall include a porch / landing / stairs / accessible ramp to access the toilet rooms.
4.3.10 The Contractor shall clean and resupply each toilet room daily.
4.3.10.1 Sweep the interior floors.
4.3.10.2 Sanitize and disinfect the toilet and sink fixtures, counter surfaces, flush valves, faucets, door handles, locks.
4.3.10.3 Restock toilet paper daily.
4.3.10.4 Restock antibacterial hand soap daily.
4.3.10.5 Restock paper towels daily. Electric hand dryers may be provided in lieu of paper towels.
4.3.11 Provide a temporary outdoor rinse / shower area with 4 shower faucets.
4.3.11.1 The temporary shower shall consist of a standing platform at grade level, sloped 1:48 to drain away from the shower into the surrounding soil.
4.3.11.2 The temporary shower shall provide 3 shower heads at 7 ft above the platform and 1 shower head at 3 ft above the platform.
Shower heads shall be 3 ft apart.
4.3.11.3 Each shower head shall have a ¼ turn shut off valve with handle. Valve shall be brass or stainless steel.
4.3.11.4 Shower water supply shall be connected to the domestic water supply system.
NOTES:
1. Warranty information including signed warranty certificates shall be provided for any material or equipment which has a warranty longer than 1 year.
2. Steel hardware shall be type 316 stainless steel unless otherwise approved by the
NPS.
3. The NPS follows the International Plumbing Code and International Building Code and National Electric Code (NFPA 70) for construction and alteration of NPS structures. Where questions arise with Code, NPS staff will address each concern on a case by case basis.