About this file

This document contains a price sheet and estimate for roof replacement services on four residential buildings at a federal facility in Arizona. The estimate was prepared by BRF Construction for the Department of the Interior Fish and Wildlife Service opportunity to renovate the service building at the Alchesay National Fish Hatchery.

The price sheet estimates costs for replacing shingles, decking, and insulation for four residential quarters buildings damaged by Hurricane Dolly. It provides itemized costs for materials and labor for each building, along with adjustments for locality, mobilization, and engineering fees. The total estimated price is $63,540.95. The related federal contract opportunity is to renovate the service building at Alchesay NFH, with a solicitation number of 140F0122R0003. The attached price sheet template does not include pricing but lists various construction items and quantities needed to complete the renovation.

View the file

Other files for this federal contract opportunity

Other files attached to ALCHESAY RENOVATE SERVICE BLDG, newest first.
File Type Posted
Attach-4-TERO_Fees_and_Application.pdf PDF
Sol_140F0122R0003.pdf PDF
Attach-2-Specifications.pdf PDF
Attach-5-Past_Performance_and_Clauses.pdf PDF
Attach-1-Drawings.pdf PDF
Attach-6-DBA_Min__Wage_Rates.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shingle Estimate

Project: Quarters Reroofing - Replacement Using Shingles
Prepared by: BRF 11/28/2008
Reference: Hurricane Dolly Estimates prepared by Staff
ITEM NO.DESCRIPTION OF OFFERED ITEMESTIMATED QUANTITYUNITUNIT PRICEESTIMATED AMOUNT
1Quarters 1: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 1: Insulation replacement1700SF$ 1.00$ 1,700.00
3Quarters 1: Deck replacement1700SF$ 1.50$ 2,550.00
4Quarters 1: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 2: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 2: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 2: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 2: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 3: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 3: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 3: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 3: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 4-1 and 4-2: Shingle Replacement2568SF$ 2.00$ 5,136.00
2Quarters 4-1 and 4-2: Deck replacement2568SF$ 1.50$ 3,852.00
3Quarters 4-1 and 4-2: Insulation replacement2568SF$ 1.00$ 2,568.00
4Quarters 4-1 and 4-2: Insulation removal1284CF$ 0.30$ 385.20
Subtotal$ 11,941.20
5Locality Adjustment @42%$ 5,015.30
6Mobilization and preparatory work @20%$ 2,388.24
SubTotal per Asset$ 19,344.74
7Engineering Services @10%$ 1,934.47
Asset Total$ 21,279.22

TOTAL FOR SCHEDULE $ 63,540.95

&"Arial,Bold"&12Confidential Government Estimate

Prepared by Charles Caldwell &D

BUILDING

Project: ALCHESAY NFH - SERVICE BLDG 1 RENOVATION

Attachment-2-Price Sheet 140F0122R0003

ITEM NO.DESCRIPTIONESTIMATED QUANTITYUNITUNIT PRICEAMOUNT
1Bonds & Insurance1LS$ - 0
2Mobilization & Demobilization1LS$ - 0
3Demolition60Hrs$ - 0
4New walls & Finish700SF$ - 0
5Furrr out, Insulate & Finish Walls1,400SF$ - 0
6Add insulation - Attic1,200SF$ - 0
7Replace doors & hardware8Ea$ - 0
8Replace sectional overhead doors5Ea$ - 0
9OH Door Operators5Ea$ - 0
10Window blinds2Ea$ - 0
11New Base Cabinets15LF$ - 0
12New Wall Cabinets15LF$ - 0
13Tile Flooring1,200SF$ - 0
14New Ceilings1,200SF$ - 0
15Replace water heater1Ea$ - 0
16New toilet1Ea$ - 0
17New sinks2Ea$ - 0
18New Bookcases1Ea$ - 0
19Radiant Heater System80LF$ - 0
20Mop Sink1Ea$ - 0
21Toilet Accessories including mirror1LS$ - 0
22Window Wood Trim1LS$ - 0
23Replace HVAC Unit1Ea$ - 0
24Modify HVAC Ducts1LS$ - 0
25Exhaust Fans2Ea$ - 0
26Water Piping1LS$ - 0
27Gas Piping1LS$ - 0
28New Elec. Power, outlets, switches,3,172SF$ - 0
29New Lights3,172SF$ - 0
30TERO Fees- $2,000 Permit + 5% contract Price1LS$ - 0
Subtotal
31O/H$ - 0
Subtotal
32Profit$ - 0
TOTAL PRICE$ - 0