Attach-3-Price_Sheet.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- ALCHESAY RENOVATE SERVICE BLDG Federal contract opportunity
- Solicitation number
- 140F0122R0003
About this file
This document contains a price sheet and estimate for roof replacement services on four residential buildings at a federal facility in Arizona. The estimate was prepared by BRF Construction for the Department of the Interior Fish and Wildlife Service opportunity to renovate the service building at the Alchesay National Fish Hatchery.
The price sheet estimates costs for replacing shingles, decking, and insulation for four residential quarters buildings damaged by Hurricane Dolly. It provides itemized costs for materials and labor for each building, along with adjustments for locality, mobilization, and engineering fees. The total estimated price is $63,540.95. The related federal contract opportunity is to renovate the service building at Alchesay NFH, with a solicitation number of 140F0122R0003. The attached price sheet template does not include pricing but lists various construction items and quantities needed to complete the renovation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach-4-TERO_Fees_and_Application.pdf | ||
| Sol_140F0122R0003.pdf | ||
| Attach-2-Specifications.pdf | ||
| Attach-5-Past_Performance_and_Clauses.pdf | ||
| Attach-1-Drawings.pdf | ||
| Attach-6-DBA_Min__Wage_Rates.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Shingle Estimate
| Project: Quarters Reroofing - Replacement Using Shingles | |||||
| Prepared by: BRF 11/28/2008 | |||||
| Reference: Hurricane Dolly Estimates prepared by Staff | |||||
| ITEM NO. | DESCRIPTION OF OFFERED ITEM | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT |
| 1 | Quarters 1: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 1: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 3 | Quarters 1: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 4 | Quarters 1: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 2: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 2: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 3 | Quarters 2: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 4 | Quarters 2: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 3: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 3: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 3 | Quarters 3: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 4 | Quarters 3: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 4-1 and 4-2: Shingle Replacement | 2568 | SF | $ 2.00 | $ 5,136.00 |
| 2 | Quarters 4-1 and 4-2: Deck replacement | 2568 | SF | $ 1.50 | $ 3,852.00 |
| 3 | Quarters 4-1 and 4-2: Insulation replacement | 2568 | SF | $ 1.00 | $ 2,568.00 |
| 4 | Quarters 4-1 and 4-2: Insulation removal | 1284 | CF | $ 0.30 | $ 385.20 |
| Subtotal | $ 11,941.20 | ||||
| 5 | Locality Adjustment @42% | $ 5,015.30 | |||
| 6 | Mobilization and preparatory work @20% | $ 2,388.24 | |||
| SubTotal per Asset | $ 19,344.74 | ||||
| 7 | Engineering Services @10% | $ 1,934.47 | |||
| Asset Total | $ 21,279.22 |
TOTAL FOR SCHEDULE $ 63,540.95
&"Arial,Bold"&12Confidential Government Estimate
Prepared by Charles Caldwell &D
BUILDING
Project: ALCHESAY NFH - SERVICE BLDG 1 RENOVATION
Attachment-2-Price Sheet 140F0122R0003
| ITEM NO. | DESCRIPTION | ESTIMATED QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1 | Bonds & Insurance | 1 | LS | $ - 0 | |
| 2 | Mobilization & Demobilization | 1 | LS | $ - 0 | |
| 3 | Demolition | 60 | Hrs | $ - 0 | |
| 4 | New walls & Finish | 700 | SF | $ - 0 | |
| 5 | Furrr out, Insulate & Finish Walls | 1,400 | SF | $ - 0 | |
| 6 | Add insulation - Attic | 1,200 | SF | $ - 0 | |
| 7 | Replace doors & hardware | 8 | Ea | $ - 0 | |
| 8 | Replace sectional overhead doors | 5 | Ea | $ - 0 | |
| 9 | OH Door Operators | 5 | Ea | $ - 0 | |
| 10 | Window blinds | 2 | Ea | $ - 0 | |
| 11 | New Base Cabinets | 15 | LF | $ - 0 | |
| 12 | New Wall Cabinets | 15 | LF | $ - 0 | |
| 13 | Tile Flooring | 1,200 | SF | $ - 0 | |
| 14 | New Ceilings | 1,200 | SF | $ - 0 | |
| 15 | Replace water heater | 1 | Ea | $ - 0 | |
| 16 | New toilet | 1 | Ea | $ - 0 | |
| 17 | New sinks | 2 | Ea | $ - 0 | |
| 18 | New Bookcases | 1 | Ea | $ - 0 | |
| 19 | Radiant Heater System | 80 | LF | $ - 0 | |
| 20 | Mop Sink | 1 | Ea | $ - 0 | |
| 21 | Toilet Accessories including mirror | 1 | LS | $ - 0 | |
| 22 | Window Wood Trim | 1 | LS | $ - 0 | |
| 23 | Replace HVAC Unit | 1 | Ea | $ - 0 | |
| 24 | Modify HVAC Ducts | 1 | LS | $ - 0 | |
| 25 | Exhaust Fans | 2 | Ea | $ - 0 | |
| 26 | Water Piping | 1 | LS | $ - 0 | |
| 27 | Gas Piping | 1 | LS | $ - 0 | |
| 28 | New Elec. Power, outlets, switches, | 3,172 | SF | $ - 0 | |
| 29 | New Lights | 3,172 | SF | $ - 0 | |
| 30 | TERO Fees- $2,000 Permit + 5% contract Price | 1 | LS | $ - 0 | |
| Subtotal | |||||
| 31 | O/H | $ - 0 | |||
| Subtotal | |||||
| 32 | Profit | $ - 0 | |||
| TOTAL PRICE | $ - 0 |