ATT E-Monthly Contractors Progress Management and Status Reports.xlsx
XLSX spreadsheet 212 KB Posted
- Attached to
- API 653 Internal Tank Inspection Robins AFB, GA Federal contract opportunity
- Solicitation number
- W9128F21Q0055
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATT C-Fuel Storage Excel Document.xlsx | XLSX spreadsheet | |
| 1449_Solicitation_21Q0055.pdf | ||
| ATT H - API Out-of-Service Telecon Briefing Template.docx | DOCX document | |
| ATT B-FY21-ROB-FAC 4302-Tank 23.xlsx | XLSX spreadsheet | |
| ATT D - ROB-FY11-FAC 4302-Tank 23-FINAL.pdf | ||
| ATT D - ROB-FY15-FAC 4302-Tank 23-FINAL.pdf | ||
| ATT G - Return To Service Letter.docx | DOCX document | |
| ATT I - API Out-of-Service Example.pdf | ||
| ATT A-General Installation Security Requirements.docx | DOCX document | |
| ATT J - API Out-of-Service Template.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Executive Summary Program Reporting Period: to
Program Manager: Adam Ashton
| 1. Executive Summary |
| Overall Task Order(s) Status: |
Key Accomplishments:
Concerns:
Month look ahead:
&"Arial Black,Regular"&18 Tank Inspection Management Report &G
Status Schedule
| 2. Status/Schedule | ||||||||||||||||||||
| Service | Site Code | Installation | Facility | Type of Inspection | % Comp. | Task Order Award Date | Work Plan / HASP Submitted | Site Coordination/Kick-Off Meeting Date | Inspection Due Date | Inspection Scheduled | OOS Date | Inspection complete | Return to Service | Report Due | DRAFT Report Distributed | FINAL Report Distributed | Recom'd Next Inspection Date | POP Expiration | USACE PM | Contractor PM |
Lessons Learned
| 3. Lessons Learned: |
| Use this section to highlight key lessons and how they can be applied to this or other similar projects/programs in future. Note that this section should not repeat the specific action points summarized in the Executive Summary (Section 1). Instead, it should highlight lessons to inform organizational learning for this and similar projects/programs in the future. |
| 1 |
| 2 |
| 3 |